Emergency Preparedness Inspection Report 05000341/2024501
ML24281A148
Person / Time
Site: Fermi 
Issue date: 10/08/2024
From: Michael Ziolkowski
NRC/RGN-III/DRSS
To: Peter Dietrich
DTE Electric Company
References
IR 2024501
Download: ML24281A148 (1)


Text

SUBJECT:

FERMI POWER PLANT, UNIT 2 - EMERGENCY PREPAREDNESS INSPECTION REPORT 05000341/2024501

Dear Peter Dietrich:

On August 29, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket No. 05000341 License No. NPF-43

Enclosure:

As stated

Inspection Report

Docket Number:

05000341

License Number:

NPF-43

Report Number:

05000341/2024501

Enterprise Identifier:

I-2024-501-0012

Licensee:

DTE Electric Company

Facility:

Fermi Power Plant, Unit 2

Location:

Newport, MI

Inspection Dates:

August 26, 2024 to August 29, 2024

Inspectors:

J. Dalzell, Technical Assistant

M. Garza, Technical Support Team Leader

D. Johnson, Sr Emergency Preparedness Specialist

J. Kutlesa, Sr Emergency Preparedness Inspector

Approved By:

Michael E. Ziolkowski, Chief

Security, Emergency Preparedness, and Incident Response Branch

Division of Radiological Safety and Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors observed the biennial exercise and evaluated emergency plan performance on August 27, 2024. The exercise scenario simulated an event at the Fermi Power Plant, Unit 2 that initiated with the declaration and notification of an Alert in response to a reactor coolant system (RCS) leak. The scenario conditions simulated the escalation of the significance of the event, requiring the declaration of a General Emergency which was communicated to the required state and local government agencies.

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on July 24,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12)===

(1) April 1, 2023 through August 23, 2024.

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)

(1) April 1, 2023 through August 23, 2024.

EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)

(1) April 1, 2023 through August 23,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 29, 2024, the inspectors presented the emergency preparedness inspection results to you and other members of your staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EP-101

Classification of Emergencies

71114.01

Procedures

TMPLAN

Fermi 2 Radiological Emergency Response Preparedness

Plan

Corrective Action

Documents

Resulting from

Inspection

CR-2024-40826

FERMEX 2024 Scenario Late Submittal

07/10/2024

71114.08

Miscellaneous

FERMEX 2024

Fermi 2024 Exercise Package

07/10/2024

71151

Miscellaneous

EP-540015

Emergency Preparedness Cornerstone - RERP:

Performance Indicator Results

4/01/2023

through

8/31/2024