ML22313A103

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010
ML22313A103
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 11/09/2022
From: Karla Stoedter
NRC/RGN-III/DORS/EB1
To: Peter Dietrich
DTE Electric Company
References
IR 2022010
Download: ML22313A103 (18)


See also: IR 05000341/2022010

Text

Mr. Peter Dietrich

Senior VP and Chief Nuclear Officer

DTE Electric Company

Fermi 2 - 260 TAC

6400 North Dixie Highway

Newport, MI 48166

SUBJECT:

FERMI POWER PLANT, UNIT 2 - DESIGN BASIS ASSURANCE INSPECTION

(TEAMS) INSPECTION REPORT 05000341/2022010

Dear Peter Dietrich:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at Fermi Power Plant, Unit 2 and discussed the results of this inspection with

Mr. E. Olson, Site Vice President and other members of your staff. The results of this inspection

are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. One of these

findings involved a violation of NRC requirements. We are treating this violation as a non-cited

violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector

at Fermi Power Plant, Unit 2.

If you disagree with a cross-cutting aspect assignment or a finding not associated with a

regulatory requirement in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the

Regional Administrator, Region III; and the NRC Resident Inspector at Fermi Power Plant,

Unit 2.

November 9, 2022

P. Dietrich

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Karla K. Stoedter, Chief

Engineering Branch 1

Division of Operating Reactor Safety

Docket No. 05000341

License No. NPF-43

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

Signed by Stoedter, Karla

on 11/09/22

ML22313A103

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RIII

RIII

NAME

ESanchez-

Santiago:mb

KStoedter

DATE

11/09/2022

11/09/2022

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000341

License Number:

NPF-43

Report Number:

05000341/2022010

Enterprise Identifier:

I-2022-010-0048

Licensee:

DTE Electric Company

Facility:

Fermi Power Plant, Unit 2

Location:

Newport, MI

Inspection Dates:

August 08, 2022 to September 30, 2022

Inspectors:

C. Baron, Mechanical Contractor

J. Benjamin, Senior Resident Inspector

B. Daley, Senior Reactor Inspector

M. Domke, Reactor Inspector

K. Fay, Reactor Inspector

B. Jose, Senior Reactor Inspector

E. Sanchez Santiago, Senior Project Engineer

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 1

Division of Operating Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a design basis assurance inspection (teams) inspection at Fermi

Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight

Process is the NRCs program for overseeing the safe operation of commercial nuclear power

reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Ensure Operating Experience Review of NRC Information Notice 2017-06 was

Completed with Appropriate Rigor

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

FIN 05000341/2022010-01

Open/Closed

[H.14] -

Conservative

Bias

71111.21M

The inspectors identified a finding of very low safety significance (Green), that was not

associated with a violation of NRC requirements, for the licensees failure to perform a review

of Operating Experience (OPEX) with appropriate rigor to ensure risk to the station was

minimized or eliminated as specified in Fermi 2 Licensing/Safety Engineering Conduct

Manual MLS04, Operating Experience Program, Revision 36. Specifically, the licensee failed

to perform a thorough review for NRC Information Notice (IN) 2017-06, "Battery and Battery

Charger Short-Circuit Current Contributions to a fault on the Direct Current (DC) Distribution

System," with appropriate rigor to ensure the risk to the station from a higher than expected

short circuit current contribution from the battery chargers to the DC system was appropriately

minimized or eliminated.

Failure to Identify Potential Tripping of Emergency Diesel Generators (EDGs) during Tornado

Pressure Transients

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000341/2022010-02

Open/Closed

None (NPP)

71111.21M

The inspectors identified a Green finding and associated Non-Cited Violation (NCV) of Title 10

of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI, Corrective

Action, for the licensees failure to identify a condition adverse to quality. Specifically, the

licensee failed to identify the emergency diesel generators (EDGs) could inadvertently trip

during a tornado due to the rapid reduction of pressure in the EDG rooms and the actuation of

the high crankcase pressure trip. This is a non-conforming condition. The licensee had an

opportunity to identify and correct this vulnerability in response to Corrective Action Review

Document 16-29153 but failed to critically review information provided by the EDG supplier.

Additional Tracking Items

None.

3

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21M - Design Bases Assurance (DBA) Inspection

The inspectors evaluated the following components and listed applicable attributes, permanent

modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)

(4 Samples)

(1)

Bus 72F and Bus Regulators, R14005021 and R14005021B

Updated Final Safety Analysis Report, Technical Specifications, Technical

Requirements Manual reviews for license basis requirements

Minimum and maximum short circuit current available at the bus

Minimum voltage available during degraded voltage conditions

Minimum voltage available at the loads fed by the bus

Load breakers coordination with the upstream supply breaker

Short circuit carrying capacity of the supply breaker compared to the available

fault current

Testing or preventive maintenance on the bus and the regulators

Functions of the regulators, how they are monitored, calibrations if any, and

their frequency

Vendor recommended maintenance/regulator replacement frequency.

Review bus and regulator related condition reports.

(2)

Reactor Core Isolation Cooling Pump Discharge Valve, E5150F012

Updated Final Safety Analysis Report, Technical Specifications, Technical

Requirements Manual reviews for license basis requirements

Field walkdown of component E5150F012

Testing and Inspection procedure reviews including acceptance criteria and

recent results for leak rate, in-service testing, and leakage

Translation of vendor specifications to associated procedures

System health (failures, operability evaluations, corrective action review

documents)

Condition Report reviews related to component E5150F012

Licensing changes to reclassify valve from a pressure isolation requirements

due to undersized actuator

4

(3)

Emergency Diesel Generator (EDG) 13,

Updated Final Safety Analysis Report, Technical Specifications, Technical

Requirements Manual reviews for license basis requirements

Evaluation of internal/external flood protection

Evaluation of potential seismic hazards

Evaluation of expendables stored on site

Susceptibility of emergency diesel generator heating and ventilation system to

tornado depressurization transient

EDG area ventilation system design

Air start check valve testing and acceptance criteria basis

Evaluation of EDG frequency and voltage variations

EDG heat exchanger cooling water flow requirements

Fuel oil consumption

Walkdowns to evaluate material condition

Engine trip parameters

Evaluation of operating procedures to manually load/shed loads after accident

Service condition of components

(4)

Division 1 and 2 Battery Chargers

Updated Final Safety Analysis Report, Technical Specifications, Technical

Requirements Manual reviews for license basis requirements

Translation of vendor specifications to associated procedures

System health (failures, operability evaluations, corrective action review

documents)

Electrical design calculations for:

o

Sizing

o

Current limiting setting

o

Duty cycle

o

Short circuit

o

Voltage drop

o

Circuit coordination

o

Fuse sizing and ratings

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)

(1)

Residual Heat Removal Service Water Pump A, E115C001A

Updated Final Safety Analysis Report, Technical Specifications, Technical

Requirements Manual reviews for license basis requirements

Field walkdown

System health (failures, operability evaluations, corrective action review

documents)

Review of condition reports related to the pump and appurtenances

Mechanical design calculations including flow capacity, runout flow, minimum

flow, required submergence, and flow balance

Testing and IPs, acceptance criteria and recent results for quarterly and

comprehensive in-service testing surveillances

5

Modification reviews including pump replacement work order for E115C001A

in 2020

Maintenance effectiveness including Maintenance Rule reviews and

Maintenance procedure reviews

Translation of vendor specifications to associated procedures

Operating procedure reviews during normal, abnormal or accident operations

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1)

70039; Replacement of Various Circuit Breakers and Power Shields

(2)

80065; Permanent Plant Mod to Ensure that the 4160 ESF Bus Degraded Voltage

Load Shed Logic is Inhibited

(3)

70015; E1150F068B-004 Replacement of Lower Stem Bushing for RHR Division 2

Heat Exchanger Service Water Outlet Isolation Motor Operated Valve

(4)

80127; ECCS [Emergency Core Cooling System] Pump CST [Condensate Storage

Tank] Vortex Suppression Device

(5)

37362; Residual Heat Removal and Core Spray Strong Pump/Weak Pump Interaction

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1)

OE-2020-0175; Grid Disturbance Causes Loss of Spent Fuel Pool Cooling Pump

(2)

NRC Information Notice 2017-06, Battery and Battery Charger Short-Circuit

Contribution to a Fault on DC System

INSPECTION RESULTS

Failure to Ensure Operating Experience Review of NRC Information Notice 2017-06 was

Completed with Appropriate Rigor

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

FIN 05000341/2022010-01

Open/Closed

[H.14] -

Conservative

Bias

71111.21M

The inspectors identified a finding of very low safety significance (Green), that was not

associated with a violation of NRC requirements, for the licensees failure to perform a review

of Operating Experience (OPEX) with appropriate rigor to ensure risk to the station was

minimized or eliminated as specified in Fermi 2 Licensing/Safety Engineering Conduct

Manual MLS04, Operating Experience Program, Revision 36. Specifically, the licensee

failed to perform a thorough review for NRC Information Notice (IN) 2017-06, "Battery and

Battery Charger Short-Circuit Current Contributions to a fault on the Direct Current (DC)

Distribution System," with appropriate rigor to ensure the risk to the station from a higher than

expected short circuit current contribution from the battery chargers to the DC system was

appropriately minimized or eliminated.

Description:

IN 2017-06 discussed test results published in NUREG/CR-7229 by Brookhaven National

Laboratories on different types of battery chargers under short circuit conditions. The test

results showed short circuit current contribution from a Silicon Controlled Rectifier (SCR) type

6

battery charger could be as high as 7 to 10 times the charger's full load rating during the first

100 milliseconds. Fermi 2 has 100 ampere SCR type battery chargers and therefore, the

short circuit current could contribute approximately 700 to 1000 amperes if a fault occurred in

the DC system. NRC inspectors reviewed the licensees response to the IN titled, "OPEX

review of NRC IN 2017-06." During this review, the inspectors noted the original review

performed by the licensee under Corrective Action Report Document

(CARD) 18-21882 was questioned by the 2019 Design Basis Assurance Inspection (DBAI)

team for its adequacy. Subsequently, the licensee revised the OPEX review under

CARDs 19-23579 and 19-23651. During the review of CARD 19-23651, the 2022 DBAI team

identified the licensee had not properly calculated the maximum short circuit current.

Specifically, the licensee had only looked at the maximum short circuit current at the

non-safety-related volt meters closest to the batteries and chargers. Because of the cables

feeding the volt meters were number 12 American Wire Gage (AWG), the maximum fault

current calculated was incorrectly determined to be less than 10,000 Amperes. Since the DC

distribution panel busses were rated for 10,000 Amperes, the licensee concluded that higher

fault current contribution from the battery chargers would only result in loss of one DC division

and no additional damage would occur. However, as a conservative measure, the licensee

replaced the DC distribution panel feeder fuses with 20,000 ampere interrupting capacity. The

inspectors noted the licensees conclusion may not be appropriate as they had neither

evaluated the maximum fault current at the DC busses nor did they verify interrupting ratings

of the battery charger internal fuses and the charger output breaker.

Based on the concerns raised by the 2022 DBAI team, the licensee performed additional

analysis which resulted in fault currents exceeding 10,000 amperes at the Division 2 DC

busses. The licensee-initiated CARDs 22-2900, "2022 NRC DBAI Inspection: NRC identified

technical error in Engineering Design Package (EDP) 70287, Revision 0," and 22-29053

"2022 NRC DBAI Inspection NRC Identified: Information Notice 17-06 not appropriately

evaluated/resolved." The licensee also contacted Sargent and Lundy Engineers to review the

Fermi 2 DC short circuit calculations to see if a more realistic loading pattern could be used in

the calculation. Sargent and Lundy Engineers removed certain DC loads to mimic a more

realistic loading scenario under various conditions and revised the DC load model in the

Electrical Transient Analyzer Program (ETAP) which resulted in less than 10,000 ampere

short circuit current at the Fermi 2 Division 2 DC Busses. As a long-term solution, the

licensee plans to replace the Division 2 DC Busses with more than 10,000 Ampere fault

current carrying capacity. The inspectors did not identify any other technical concerns. The

inspectors reviewed the battery chargers internal fuse characteristics and coordination with

the downstream protective devices and did not identify any concerns.

Section 4.4.4 of Fermi 2 Licensing/Safety Engineering Conduct Manual MLS04, Operating

Experience Program, Revision 36, stated, "Complete CARD evaluations with appropriate

rigor to ensure risk to the station is minimized or eliminated." The inspectors determined the

licensee's initial and subsequent OPEX evaluations for IN 2017-006 did not meet the

licensee's standard for OPEX review stated in MLS04, Section 4.4.4 because the evaluation

was not completed with appropriate rigor to determine the short circuit current contribution

was exceeded 10,000 amperes and impacted the operation of the Division 2 DC busses. The

licensees failure to perform the OPEX reviews within CARDs 18-21882, 19-23579, and

19-23651 with appropriate rigor to minimize or eliminate risk to the station was contrary to the

Fermi 2 Procedure MLS04 and was a performance deficiency. No violations of NRC

requirements were identified since this procedure was not safety-related and, therefore, not

subject to 10 CFR Part 50 Appendix B requirements.

7

Corrective Actions: The licensee revised the OPEX evaluation for IN 2017-06 and concluded

the larger short circuit current contribution from the charger did not exceed the interrupting

ratings of equipment/isolation devices.

Corrective Action References: CARD 22-29053; 2022 NRC DBAI Inspection NRC Identified:

IN 17-06 not Appropriately Evaluated/Resolved.

Performance Assessment:

Performance Deficiency: The inspectors determined the licensees failure to perform a

rigorous OPEX evaluation for IN 2017-06 which minimized or eliminated risk to the station

was contrary to Fermi 2 Procedure MLS04, Operating Experience Program. Specifically, the

licensee failed to appropriately calculate the short circuit current expected and determine the

impact on the Division 2 DC busses.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Mitigating Systems

cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the failure to perform a rigorous OPEX evaluation for

NRC IN 2017-06 resulted in a condition where there was a reasonable doubt that

equipment/isolation devices were able to withstand the larger short circuit conditions provided

by the chargers as described in the IN.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, the finding screened as very low safety significance (Green) because the

inspectors answered 'yes' to the question: "If the finding deficiency affecting the design or

qualification of a mitigating SSC, does the SSC maintain its operability or PRA functionality?

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision making-practices

that emphasize prudent choices over those that are simply allowable. A proposed action is

determined to be safe in order to proceed, rather than unsafe in order to stop. Specifically,

the licensee's initial and subsequent evaluations for IN 2017-06 failed to evaluate the effect of

the larger short circuit current contribution from the charger on the interrupting rating of the

equipment/isolation devices. Instead, the licensee only verified that the short circuit current as

specified in the revised calculation did not exceed the plant equipment/isolation devices

interrupting rating.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

Failure to Identify Potential Tripping of Emergency Diesel Generators (EDGs) during Tornado

Pressure Transients

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000341/2022010-02

Open/Closed

None (NPP)

71111.21M

The inspectors identified a Green finding and associated Non-Cited Violation (NCV) of Title

10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI,

8

Corrective Action, for the licensees failure to identify a condition adverse to quality.

Specifically, the licensee failed to identify the emergency diesel generators (EDGs) could

inadvertently trip during a tornado due to the rapid reduction of pressure in the EDG rooms

and the actuation of the high crankcase pressure trip. This is a non-conforming condition. The

licensee had an opportunity to identify and correct this vulnerability in response to Corrective

Action Review Document 16-29153 but failed to critically review information provided by the

EDG supplier.

Description:

The inspectors reviewed the design of the EDGs, including their automatic trip features. The

inspectors noted the high crankcase pressure trip (two out of three logic for each EDG) was

considered essential and would not be bypassed during an emergency EDG start in the event

of an accident or loss of offsite power (LOOP). Because the high crankcase pressure trip

instruments measure the pressure difference between the diesel engine crankcases and the

EDG rooms, the inspectors questioned if the EDGs could be subject to an inadvertent trip if

the room pressures were suddenly reduced as a result of a postulated tornado event.

Updated Final Safety Analysis Report (UFSAR) Section 8.3.1.1.8.2 stated, "the RHR complex

structure serves to contain, protect, house, and support the equipment of the EDG system

and protect it from the outdoor environment." Section 8.3.1.1.8.2.i states, "the EDG system is

designed to be operable during and after a design-basis tornado that has the following

characteristics Differential pressure between inside and outside of fully enclosed areas -

3 lb/in.2 All building structures housing equipment necessary for safe shutdown are designed

to withstand a tornado-induced depressurization rate of 1 lb/in.2/sec for 3 seconds."

The inspectors questioned if the EDG rooms in the RHR complex were considered to be fully

enclosed areas and if the tornado-induced depressurization rate of those rooms had been

previously analyzed to determine if the EDGs could inadvertently trip. In response, the

licensee stated an evaluation had been performed in 2016 based on industry experience.

Corrective Action Review Document (CARD) 16-29153 had been initiated on November 14,

2016, to investigate the potential impact of a tornado on the EDGs. This investigation was a

result of a similar concern at another facility where high crankcase pressure switches, as

originally supplied by the diesel generator vendor, which are susceptible to actuation due to

pressure differentials during a tornado event. The consequence is that a trip of the crankcase

pressure switch, while in standby, causes actuation of the shutdown relays. This in turn

causes a lockout, keeping the EDG from being able to start during an emergency condition.

The cause was that the design of the crankcase pressure switch trip logic did not consider the

effect of outside atmospheric pressure during a tornado event." This CARD concluded that

there was no design deficiency present in the Fermi EDGs and no engineered/installed

modifications were required. This conclusion was based on input from the EDG supplier,

Fairbanks-Morse Engine.

The licensee also provided correspondence from the EDG supplier, dated November 17,

2016, which explained why the specific concern addressed on the CARD (activation of a

crankcase pressure switch when the EDG is in standby) was not applicable to Fermi.

However, this correspondence also addressed the potential of a trip when an EDG was

already operating. This portion of the correspondence was based on an unsubstantiated

assumption. Specifically, it stated the crankcase pressure switches are within the engine

room (the engine space) and are monitoring the differential between the pressure in the room

and the pressure (vacuum) in the crankcase. Even with the engine in operation, the pressure

outside of the building should not have an effect on the operation of these pressure switches.

9

And, in fact, because the outlet of the ejector is in the exhaust system (subject to the

pressure outside the building), the lower pressure created by the tornado would have a

tendency to lower the pressure at the outlet of the ejector which would in turn tend to lower

the pressure in the crankcase.

The inspectors questioned whether the assumption that the pressure outside of the building

should not have an effect on the operation of these pressure switches, which was implied in

the vendors correspondence, had been verified by the licensee. Specifically, the inspectors

asked if the EDG rooms were isolated from the outside atmospheric pressure and if the EDG

crankcase air ejector had sufficient capacity to reduce the crankcase pressure and prevent a

trip during a design basis tornado pressure transient event. The licensee stated a quantitative

analysis had not been performed and stated the vendor would be contacted for additional

information.

After performing additional investigation, the licensee-initiated CARD 22-28738 on August 15,

2022. The CARD stated that it is clear the high crankcase pressure trip would be activated if

the EDG were operating prior to the depressurization of the RHR complex (which houses all

four EDGs). In addition, the licensee-initiated CARD 22-28763 on August 16, 2022, to

evaluate elimination of the EDG crankcase pressure trips or converting the trips to

non-essential (bypassed on an emergency start).

Corrective Actions: CARD 22-28738 was initiated on August 15, 2022, to address this issue.

Corrective Action References: CARDs 22-28664, "Previous Fermi Evaluation of OE in

Regard to Potential for Tornado," 22-28738, "IOD Not Supported"

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensees failure to identify the

potential tripping of the EDGs due to atmospheric pressure transients caused by a postulated

tornado is a performance deficiency. Specifically, the licensee failed to identify a design

vulnerability that could result in the inadvertent tripping of one or more EDGs. The licensee

had an opportunity to identify and correct this vulnerability in response to CARD 16-29153 but

failed to critically review information provided by the EDG supplier.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Mitigating Systems

cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the atmospheric pressure transient resulting from a design basis

tornado could result in the inadvertent tripping of one or more EDGs.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, the finding screened as having very low safety significance (Green) because

they answered 'yes' to the questions: "If the finding is a deficiency affecting the design or

qualification of a mitigating SSC, does the SSC maintain its operability or PRA functionality?

The inspectors determined the finding did not cause a loss of PRA functionality.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to

this finding because the inspectors determined the finding did not reflect present licensee

10

performance. The last update of the crankcase pressure trip setpoints and associated

analysis was greater than 3 years ago.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, states, in part,

measures shall be established to assure that conditions adverse to quality, such as failures,

malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected.

Contrary to the above, on November 14, 2016, the licensee failed to identify a condition

adverse to quality. Specifically, the licensee performed a review of CARD 16-29153 as a

result of operating experience related to the potential impact of a tornado on the EDGs and

failed to identify the effects of a tornado could cause the EDGs to trip during a LOOP due to a

high crankcase pressure signal. The EDGs tripping during a tornado event is nonconforming

with Section 8.3.1.1.8.2.i of the UFSAR which states, "the EDG system is designed to be

operable during and after a design-basis tornado that has the following characteristics

Differential pressure between inside and outside of fully enclosed areas -3 lb/in.2 All building

structures housing equipment necessary for safe shutdown are designed to withstand a

tornado-induced depressurization rate of 1 lb/in.2/sec for 3 seconds."

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 30, 2022, the inspectors presented the design basis assurance

inspection (teams) inspection results to Mr. E. Olson, Site Vice President and other

members of the licensee staff.

On August 26, 2022, the inspectors presented the interim design basis assurance

inspection (teams) inspection results to Mr. E. Olson, Site Vice President and other

members of the licensee staff.

11

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC-4953

RHR Complex - Abnormal Operation Damper Lineups

I

DC-5367

Seismic Evaluation of 480V and 4160V Switchgears and

Motor Control Center Breakers

0

DC-5426

PBOC - High and Moderate Energy Line Break Evaluation

D

DC-5489

Ventilation Air Quality for Diesel Generator Room 11

B

DC-5803

RHRSW Design Basis Requirements

C

DC-5804

DGSW Design Basis Requirements Calculation

F

DC-5866

RHR Complex Evaluation During Site Flood

0

DC-6249

Service Water Systems Calibrated Hydraulic Model

0

DC-6309

Design Basis of EDG Fuel Oil and Day Tank Level

Requirements and Setpoints

B

DC-6447

Auxiliary Power System Analysis

F

DC-6480

130/260V DC System Analysis

C

DC-6482

260/130V and 48/24V DC Protective Device Coordination

Calculation

D

Calculations

DC-6774

Fuel Oil Storage Tank Room Minimum Temperature

0

05-26492

Design Calculation for RHR Complex Depressurization is not

Available

11/17/2005

13-24840

EDG Steady State Voltage and Frequency Tech Spec

Ranges

07/10/2013

16-29153

Potential Impact of a Tornado on the Emergency Diesel

Generator

11/14/2016

17-28611

E1150F068B Packing Leak

1

19-28434

Request Revision to Scope of Outage Work Orders for Bus

Inspections

05/11/2019

20-20568

Request Work Orders for Replacement of 1SA62 and 1SB62

Relays

01/17/2020

20-20637

Tracking CARD for Revision of 24.205.05

06/22/2020

20-22467

IST to Investigate Implementing 2 Pump Testing of the RHR

SW Pumps

03/06/2020

71111.21M

Corrective Action

Documents

20-25227

Shoulder Bolt for Breaker Slide Bracket Stripped - 72F

Position 2B

04/26/2020

12

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20-25312

Open Light Socket Failure on 72F Position 3A Breaker

04/28/2020

20-25559

Blown Fuse Found for ESF 2B1-2 Battery Charger

05/05/2020

21-20678

While Racking out 72F Position 5A (Feed to MCC 72F-5A),

the Racking Shutter would not Fully Close

01/25/2021

22-28575

Indication Lights were Burnt Out on X4103F130

08/08/2022

22-28576

POS 2A Was Illuminated However it Was Very Dim

08/09/2022

22-28577

X41K003B TCE Flashing Low Battery

08/09/2022

22-28616

2022 NRC DBAI Inspection (NRC Identified): 72F Position

5B Racked out with no Tag Nearby

08/10/2022

22-28627

EDG DBD Revision

08/10/2022

22-28664

Previous Fermi Evaluation of OE in Regard to Potential for

Tornado

08/11/2022

22-28687

2022 DBAI Inspection -Revise Procedure 43.401.515 "RCIC

Pressure Isolation Valve Test"

08/12/2022

22-28738

IOD Not Supported

08/15/2022

22-28763

Evaluate EDG Crankcase Trips

08/16/2022

22-28800

Evaluate EDG Essential Trips

08/17/2022

Corrective Action

Documents

Resulting from

Inspection

22-28801

2022 DBAI Inspection: 3071-128-EZ-01 Discrepancy

08/17/2022

6SD721-2530-10

260/130V ESS Dual Battery 2PA Distribution - Division 1

AP

6SD721-2581-14

Schematic Diagram/Wiring Diagram, 1500 KVA Regulator

Bus 72F R1400S021B

0

Drawings

M-5734

Emergency Diesel Generator - Functional Operating Sketch

BL

37362

RHR and Core Spray Strong Pump/Weak Pump Interaction

B

70130

Replacement of EDG 14 Fuel Oil Transfer Pump Flowmeter

R30R411D

0

80122

Update Design Specification 3071-012 -Valves with Anti-

Rotation Key Repair or Upgrade Guidance for Safety

Related Powell Globe Valves

0

80122.001

Guidance for Safety Related Powell Globe Valve Anti-

Rotation Key Repair or Upgrade

0

80127

ECCS Pump CST Vortex Suppression Device

C

Engineering

Changes

80142

Replacement of Residual Heat Removal Service Water

(RHRSW) Valve E1150F068A

0

13

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations20-001

ISI/NDE-IST Program Evaluation

0

3071-019

Design Specification - RHR Complex

E

3071-517

Design Specification - RHR Complex

E

DBD R32-00

DC Electrical System Design Basis Document

B

FAI/20-0183

Testing Results CST Vortex Suppressors

2

Fairbanks Morse

Letter, Response

to FQ13-46

Postulated Tornado Crankcase Pressure Trip

11/17/2016

LCR 20-025-ISI

TSR-38230 changed the Pressure Isolation Boundary in the

HPCI and RCIC Systems

06/29/2020

MES54001

EDG 13 Air Coolant HX

0

MES54001

EDG 13 Jacket Coolant Hx

0

MES54001

EDG 13 Lube Oil Hx

0

R30-00

DBD for Emergency Diesel Generator

I

TMPE-02-0342

Evaluation of Increased Ambient Temperature in the RHR

Complex

12/13/2002

TSR-38268

Technical Service Request, Thermal Recombiner System

Abandonment per License Amendment 159

0

VME 11-2

C&D 3Phase, 6 Pulse SCR Float Chargers

09/05/2007

VME 5-12

Main DC Fuse Cabinets

0

VME 8-1.1

Vendor Manual Emergency Diesel Generators

AC

VMS22-1.3

2 Stage Vertical Pump Instruction Manual

0

X41-03

DBD for Residual Heat Removal Complex Heating and

Ventilating System

B

Miscellaneous

XXX-02

DBD for Design Basis Event Combinations

A

23.307

Emergency Diesel Generator System

135

23.324.01

Operation of CTG 11-1 from CTG 11 Peaker Yard

4

23.324.05

Supervisory Control- Standby Diesel Operation

3

24.307.001

Emergency Diesel Generators - Inspection and Preventive

Maintenance

86

Procedures

24.307.12

Emergency Diesel Generator 13 - ECCS Start Test and

Logic Functional Tests of Bus 65E Breakers

48

14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

24.307.16

Emergency Diesel Generator 13 - Start and Load Test

61

24.307.37

DGSW, DFOT and Starting Air Operability Test - EDG 14

63

35.205.011

E1150F068A(B) Globe Valve Maintenance

0

74.000.18

Chemistry Shift, 72 Hour, and Situation Surveillances

60

ARP 1D73

RCIC Pump Suction Pressure High/Low

14

MLS04

Operating Experience Program

36

37526767

REPLACE FRN-R-400 FUSE PER ERE 45322 AT

R3200SO07A (2A-1 BATT')

10/22/2013

37526832

REPLACE FRN-R-400 FUSE PER ERE 45322 AT

R3200SO07B (2A-2 BATT)

10/22/2013

44152012

Perform 24.206.02 SEC-5.2 RCIC Valve Position Indication

Verification/Manual Initiate

04/16/2017

46456433

Perform 5-Year verification of time critical actions

08/30/2017

47548189

Final 43.401.515 RCIC Pressure Isolation Valve Leakage

(Test-2:E5150F012)

04/19/2020

48650178

Perform 42.309.04 Div 1 Battery Charger Load Test -2A-2

Only

09/10/2019

48778616

Remove/Reinstall Actuator in Support of WO 48774938

10/02/2017

50084239

Perform 24.206.01 RCIC System Pump Operability and

Valve Test at 1000PSIG

08/17/2019

50917153

Perform 24.206.01 RCIC System Pump Operability and

Valve Test at 1000PSIG

11/08/2019

51561321

Perform 42.309.04 Div 1 Battery Charger Load Test - 2A-1

Only

09/10/2020

51745473

Perform 24.206.01 RCIC System Pump Operability and

Valve Test at 1000PSIG

02/04/2020

52178219

Perform 24.206.02 Sec-5.2 RCIC Valve Position Indication

Verification/Manual Initiate

07/20/2020

52866184

Perform 42.309.04 Div 1 Battery Charger Load Test - 2A1-2

Only

09/08/2020

53719849

Partial 24.205.05, PMT Strokes for E1150F068A

04/17/2019

54453528

Perform 42.309.04 Div 1 Battery Charger Load Test - 2A-2

Only

05/10/2021

Work Orders

54529464

Perform 24.205.05 Partial for E1150F068A

07/16/2019

15

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

54768485

Perform 24.205.05 Division 1 RHRSW Pump and Valve

Operability

01/13/2021

54796258

Replace RHRSW Pump A

01/16/2020

57114597

Perform 42.309.04 Div 1 Battery Charger Load Test - 2A-1

Only

06/01/2021

57242836

Perform 42.309.06 DIV 2 18 Month 130/260 VDC Battery

Check (2B-2 Only)

04/09/2022

57243522

Perform 42.309.06 DIV 2 18 Month 130/260 VDC Battery

Check (2B-1 Only)

04/08/2022

58276397

Perform 24.205.05 Division 1 RHRSW Pump and Valve

Operability

01/10/2022

59933741

Perform Partial 24.205.05 to Stroke Test E1150F068A

01/12/2021

60290633

Perform 24.205.05 Division 1 RHRSW Pump and Valve

Operability

07/12/2022

64803407

Perform 24.205.05 Division 1 RHRSW Pump and Valve

Operability

03/24/2022