Similar Documents at Fermi |
---|
Category:Inspection Report
MONTHYEARIR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 IR 05000341/20220042023-06-22022 June 2023 Non-Concurrence on Fermi Power Plant, Unit 2 - Integrated Inspection Report 05000341/2022004 IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML22313A1032022-11-0909 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20220032022-11-0808 November 2022 Integrated Inspection Report 05000341/2022003 IR 05000016/20220012022-11-0808 November 2022 NRC Inspection Report No. 05000016/2022001(DRSS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20224202022-11-0101 November 2022 Security Baseline Inspection Report 05000341/2022420 IR 05000341/20225012022-10-17017 October 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2022501 IR 05000341/20220052022-08-25025 August 2022 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2022005) IR 05000341/20220022022-08-0404 August 2022 Integrated Inspection Report 05000341/2022002 IR 05000341/20220012022-05-0909 May 2022 Integrated Inspection Report 05000341/2022001 IR 05000341/20224012022-03-21021 March 2022 Security Baseline Inspection Report 05000341/2022401 IR 05000341/20210062022-03-0202 March 2022 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2021006) IR 05000341/20210042022-02-0707 February 2022 Integrated Inspection Report 05000341/2021004 IR 05000341/20210132021-12-17017 December 2021 Temporary Instruction 2515/194 Inspection Report 05000341/2021013 IR 05000016/20210012021-12-13013 December 2021 Subject: NRC Inspection Report No. 050-00016/2021-001 (DNMS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20214022021-12-0909 December 2021 Security Baseline Inspection Report 05000341/2021402 IR 05000341/20210122021-12-0707 December 2021 Biennial Problem Identification and Resolution Inspection Report 05000341/2021012 IR 05000341/20210032021-10-28028 October 2021 Integrated Inspection Report 05000341/2021003 IR 05000341/20215012021-10-21021 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2021501 IR 05000341/20214032021-09-0808 September 2021 Material Control and Accounting Program Inspection Report 05000341/2021403 IR 05000341/20210052021-09-0101 September 2021 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2021005) IR 05000341/20210112021-08-25025 August 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000341/2021011 IR 05000341/20210022021-08-0606 August 2021 Integrated Inspection Report 05000341/2021002 IR 05000341/20213012021-07-13013 July 2021 NRC Initial License Examination Report 05000341/2021301 IR 05000341/20214012021-06-0707 June 2021 Security Baseline Inspection Report 05000341/2021401 IR 05000341/20210012021-05-0404 May 2021 Integrated Inspection Report 05000341/2021001 2024-08-22
[Table view] Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) 2024-09-09
[Table view] |
Inspection Report - Fermi - 2024011 |
---|
|
|
Text
SUBJECT:
FERMI POWER PLANT, UNIT 2 - SAFETY CONSCIOUS WORK ENVIRONMENT ISSUE OF CONCERN FOLLOW-UP INSPECTION REPORT 05000341/2024011
Dear Peter Dietrich:
On January 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Billy C. Dickson, Jr., Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000341 License No. NPF-43
Enclosure:
As stated
Inspection Report
Docket Number: 05000341
License Number: NPF-43
Report Number: 05000341/2024011
Enterprise Identifier: I-2024-011-0017
Licensee: DTE Electric Company
Facility: Fermi Power Plant, Unit 2
Location: Newport, MI
Inspection Dates: January 02, 2024 to March 31, 2024
Inspectors: M. Keefe-Forsyth, Safety Culture Program Mgr.
R. Sigmon, Senior Reactor Systems Engineer
Approved By: Billy C. Dickson, Jr., Chief Reactor Projects Branch 2 Division of Operating Reactor Safety
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Safety Conscious Work Environment Issue of Concern Follow-up Inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
===93100 - Safety Conscious Work Environment Issue of Concern Follow-up
Over the last two years the NRC Resident Inspectors at Fermi had been closely monitoring the safety conscious work environment (SCWE) due to observations and interactions with plant staff. Some of these observations involved Radiation Protection (RP) staff but other examples involved staff from others licensee departments including the Quality Assurance group. These observations did not reach the threshold for documentation in any inspection report.
During the performance of the Biennial Problem Identification and Resolution (PI&R) Inspection at Fermi in late 2023, the NRC inspectors determined that there was a perceived environment that discouraged RP staff from initiating condition reports. Specifically, during the PI&R focus group discussions, all RP technicians participating stated that they were willing to raise safety concerns to their first-line supervisors but would not write condition reports for fear of retaliation, embarrassment, and/or it would be closed out to the initiator just having a beef with management with no actual resolution taken. (See Fermi Power Plant, Unit 2 - Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 (ML23340A032)).
Therefore, the NRC determined that an assessment of SCWE at the Fermi Power Plant, Unit 2, using Inspection Procedure (IP) 93100, Safety Conscious Work Environment Issue of Concern Follow-up was appropriate.
The purpose of this IP 93100 inspection was to determine if indications of a chilled work environment exist; if employees were reluctant to raise safety or regulatory issues; and if employees were being discouraged from raising safety or regulatory issues at Fermi. The inspection consisted primarily of reviewing licensee SCWE assessments, reviewing SCWE related issues documented in the licensees Corrective Action Program (CAP), observing plant activities, and conducting interviews with plant workers. During this inspection, the team conducted focus groups and interviews with individuals from Operations, RP, Maintenance, as well as supervisors and managers. In addition, the team interviewed the department managers for Operations, RP, and Maintenance, the Employee Concern Program (ECP) manager.
Safety Conscious Work Environment Issue of Concern Follow-up===
- (1) Review of SCWE at Fermi
INSPECTION RESULTS
Assessment 93100 Safety Conscious Work Environment
Overall Assessment of SCWE The team did not note any current indications of a chilled work environment within the RP department. Licensee staff in this department and other staff who were interviewed were all willing to identify and raise nuclear safety issues and did not fear retaliation. The team interviewed all available employees
- (22) from the RP department, some randomly selected employees from the Maintenance and Operations departments, as well as supervisors and managers, and the ECP manager.
Willingness to Raise Safety or Regulatory Issues Based on focus group discussions held with employees, focusing on the RP department but also including personnel from the Operations and Maintenance departments, the team determined that employees generally felt free to raise nuclear safety concerns without fear of retaliation. However, the team noted that with the recent transition of the sites Corrective Action Program (CAP) system to a new software package, some workers, particularly contractors, felt challenged with the new program due to a lack of familiarity and training that was not uniformly available to everyone. This lack of familiarity and training caused some individuals to express reluctance about using the new software, relying instead on supervisors to initiate condition reports. The team noted that steps already underway to provide one-on-one training for the new software within the RP department were well-received by those who had participated.
Corrective Action Program There appears to be a misconception about the purpose of the CAP amongst the staff the team interviewed. Condition Reports (CRs) are not meant to be punitive, but some communications imply that if action is not taken, a CR will be written, which could lead to a perception that initiating a CR is intended to have negative consequences for someone.
Employees also expressed skepticism that raising concerns would make a difference, as it was felt that if a CR was initiated, it would be closed to trending, closed to a work order that would never be scheduled, or assigned as work back to the originator of the issue. This appears to represent a fundamental lack of understanding about what the purpose of the CAP is - that owning a CR does not mean that person is required to do the work; that trending failures, even if the problem was immediately fixed has safety value; and that writing a CR is not in any way some kind of negative action. It is a way to initiate the process for ensuring deficient conditions are appropriately addressed.
ALARA and Work Process Controls There were concerns raised in discussions with RP department personnel, validated in interviews with members of other departments, that there is a perception amongst the licensee staff that radiological safety is not held to the same standard as industrial safety. The licensee staff provided examples regarding choices made across the organization up to management levels to sacrifice dose impacts in the name of efficiency, a production-over-(radiological) safety mentality. The RP department feels they shoulder the burden for radiological safety for the entire site, especially in contrast to industrial safety, which is recognized as the responsibility of every individual. There appears to be an opportunity to incorporate ALARA better (as low as reasonably achievable) and dose planning into the work planning process to raise awareness of radiological safety while better coordinating work in high radiation areas across the departments to minimize dose. This effort could also alleviate concerns in the RP department about whether current staffing levels will be adequate to meet the workload demands.
Other Observations The team heard from long-term contractors that they dont feel they are as respected as in-house DTE employees. When asked about hesitancy with raising concerns, some contractors stated that there is a potential that a contractor could be seen as rocking the boat if they were to raise a concern, and that could potentially impact their jobs. It should be noted that every contractor interviewed stated they would be willing to (and had) raised safety concerns. However, the inherent tension of the more tenuous nature of a contractors job is a management and communication challenge that requires maintaining awareness of the need to reinforce that raising safety concerns is a good thing constantly.
The licensee captured the teams observations in the CAP as follows:
CR-2024-36020, NRC SCWE Inspection Observation - Perception of Production Over Safety (Radiation Safety)
CR-2024-36022, NRC SCWE Inspection Observation - Site Over-Reliance on RP CR-2024-36023, NRC SCWE Inspection Observation - Long-Term Contractor Support
No violations or findings of significance were identified during this inspection.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On January 31, 2024, the inspectors presented the Safety Conscious Work Environment Issue of Concern Follow-up Inspection results to Peter Dietrich and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
93100 ALARA Plans 231029 Drywell/Reactor Building Steam Tunnel Emergent Work 08/18/2023
Corrective Action CR-2023-32672 Prioritization of Refuel Floor Work Activities Increased Both 08/29/2023
Documents Industrial Safety and Radiological Risk
CR-2023-32778 Unnecessary Dose Received When Two Techs Were 09/02/2023
Directed to Enter the Drywell Basement to Take Pictures of a
Condition Already Reported
CR-2023-33183 NRC Identified: Lack of Written Guidance for Initial ECP 09/20/2023
Screening of Anonymous CRs
CR-2023-33970 PO 23-01 Drywell 2nd Floor Entry Deviations from RWP 10/24/2023
Instructions
CR-2023-33980 Potential Safety Culture Concern 10/25/2023
Corrective Action CR-2024-36020 NRC SCWE Inspection Observation - Perception of 02/01/2024
Documents Production Over Safety (Radiation Safety)
Resulting from CR-2024-36022 NRC SCWE Inspection Observation - Site Over-Reliance on 02/01/2024
Inspection RP
CR-2024-36023 NRC SCWE Inspection Observation - Long-Term Contractor 02/01/2024
Support
Miscellaneous NAQA-22-0045 2022 Nuclear Safety Culture Assessment Report 09/19/2022
NG-22-0011 Second Trimester 2022 Nuclear Safety Culture Report 11/21/2022
NG-23-0003 Third Trimester 2022 Nuclear Safety Culture Report 02/10/2023
NG-23-0007 First Trimester 2023 Nuclear Safety Culture Report 06/30/2023
6