NRC Inspection Manual 0612 Appendix E, Examples of Minor Issues

From kanterella
Jump to navigation Jump to search

Examples of Minor Issues

NRC Inspection Manual 0612
Appendix A B C D E F G

text

Issue Date: 10/26/23 1 0612 App E

NRC INSPECTION MANUAL IRAB

INSPECTION MANUAL CHAPTER 0612 APPENDIX E

EXAMPLES OF MINOR ISSUES

Effective Date: 11/01/2023

This guidance applies to thresholds for the minor and more-than-minor (MTM) determination in

Inspection Manual Chapter (IMC) 0612.

Minor findings and violations are below the significance of that associated with Green SDP

findings and are not the subject of formal enforcement action or normal documentation. Failures

to implement requirements that have insignificant safety or regulatory impact or findings that

have no more than minimal risk should normally be categorized as minor. While licensees must

correct minor violations, minor violations or other minor findings do not normally warrant

documentation in inspection reports and do not warrant enforcement action.

NRC IMC 0612 Appendix B, “Issue Screening,” provides guidance for determining if a finding

should be documented and whether the finding can be analyzed using an SDP. When

determining whether identified issues can be considered MTM, inspectors shall compare the

issue to the examples and guidance in this appendix. Inspector should understand that

equipment inoperability is not a pre-requisite for the PD to be MTM.

The purpose of the following examples is not to create a completely mechanistic determination

process but is to provide direction that would allow the agency as a whole to screen

performance deficiencies in a reasonably consistent manner. There may be instances where a

performance deficiency is judged more than minor notwithstanding the example guidance due to

impacts or circumstances not listed in the examples. When applicable, the finding

documentation should describe the impact. It should be noted the performance deficiencies are

written in this guidance are at a generic level and do not include the actual regulatory

requirement or self-imposed standard. When writing PDs, please follow the guidance in

IMC 0611.

1. Record Keeping Issues

Example 1.a Post-maintenance testing was performed on ten glycol air handling units

during an outage of a Westinghouse ice condenser facility. All the

required tests were performed, based on statements from licensee

workers, but there was no record that an actual air flow test was

conducted on two of the units.

The performance The licensee failed to document and evaluate test results in accordance

deficiency (PD): with regulatory requirements or self-imposed standards.

Minor if: Even though the record keeping issue is associated with the mitigating

systems cornerstone attributes of equipment performance and procedure

quality it did not adversely affect the associated cornerstone objective.

Specifically, there was reasonable assurance of operability that test

requirements were met as evidenced by actual air flow being satisfactory

and technical specification temperatures being within limits, or the

licensee subsequently performed the required testing with no issues.

Based on indication in the control room, both air handling units had

comparable air flow to those that had documented test results, and the

ice condenser technical specification required air temperatures were all

well-within specification.

MTM if: The PD adversely affected the mitigating systems cornerstone attributes

of equipment performance and procedure quality and adversely impacted

the cornerstone objective. Specifically, during subsequent testing the air

flow was reduced such that reasonable assurance of operability was

called into question, or a significant number of records associated with

the air handling units was missing such that reasonable assurance of

operability was called into question.

Example 1.b The licensee’s surveillance test records were not complete for a

safety-related pump because the operators skipped a page of the

surveillance procedure and failed to record one section of the test.

The PD: The licensee failed to follow the surveillance procedure as written which is

contrary to a regulatory requirement or self-imposed standard.

Minor if: Even though the failure to complete all sections of the surveillance test

procedure is associated with the mitigating systems cornerstone attribute

of human performance it did not adversely affect the associated

cornerstone objective. Specifically, the portion of the test documented,

the last completed surveillance test, and the licensee’s justification to wait

to perform the surveillance test revealed that the equipment performed its

safety function (or the licensee performed the completed surveillance test

satisfactorily once the issue was identified).

MTM if: The PD adversely affected the mitigating systems cornerstone attribute of

human performance and adversely impacted the cornerstone objective.

Specifically, the subsequent surveillance test showed that the equipment

would not perform some safety-related function, or the licensee was

unable to provide adequate justification to wait to perform the surveillance

test, or some test acceptance criteria was not met.

Example 1.c The inspector noted that the licensee did not establish and maintain MOV

program documents such that they adequately described how the

design-basis capability of the MOVs was developed. Specifically, MOV

program documents and procedures were out-of-date, or contained

contradictory or conflicting information, regarding how load sensitive

behavior was applied, how lubricant degradation margin was determined,

or how test data was extrapolated.

The PD: The licensee failed to establish and maintain MOV program documents

which is contrary to a regulatory requirement or self-imposed standard.

Minor if: The PD did adversely affect the mitigating systems cornerstone attributes

of procedure quality but did not adversely impact the cornerstone

objective. Specifically, the incorrect information did not involve

methodology errors or incorrect assumptions. The issue centers on

administrative vulnerability but had not impacted the site.

MTM if: The PD adversely affected the mitigating systems cornerstone attributes

of procedure quality and adversely impacted the cornerstone objective.

Updating MOV program documents and procedures adversely impacted

design margins of effected MOVs and resulted in reasonable doubt with

respect to the availability, reliability, or capability of an MOV.

Note: Since the inspector identified an impact on equipment resulting

from the outdated procedures, the inspector is encouraged to focus the

PD on the equipment issues (see sections 3 and 4 of this document for

examples which address calculational errors/design inconsistencies or

procedure issues) and consider using the outdated procedures as the

cross-cutting aspect.

2. Licensee Administrative Requirement/Limit Issues

Example 2.a While performing a review of a completed surveillance test, the system

engineer determines that operators performing the test had recorded

information incorrectly when determining the leak rate of a power

operated relief valve'’s nitrogen accumulators. When corrected, the actual

check valve leakage exceeded the surveillance leakage rate'’s

acceptance criterion in the surveillance procedures. The surveillance had

been completed a week earlier and the system had been returned to

service.

The PD: The licensee failed to correctly determine the check valve leakage rates

were within the surveillance test acceptance criterion prior to returning the

system to service. This failure is contrary to a regulatory requirement or

self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the error was identified prior to required actions

specified in the procedure. For example, not meeting the acceptance

criterion required additional monthly testing – the error was caught before

missing the additional testing.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the as-left leakage was such that the licensee had to initiate

actions as required by the procedure and the time period specified had

been exceeded. For example, the as-left leakage resulted in increased

testing frequency to weekly, but the issue was identified after a month.

Example 2.b During a refueling outage, the licensee tested a charging pump at full flow

conditions as required every 18 months. Vibration data taken during this

test indicated vibration of 0.324 inches per second (ips), which exceeded

the test procedure administrative limit of 0.320 ips. The procedure

required the surveillance frequency to be increased to every nine months

after exceeding the administrative limit. The licensee failed to identify that

the test result exceeded the administrative limit, so the test frequency was

not increased. Subsequent vibration testing revealed no further vibration

degradation. The acceptance criterion for vibration measurements is

0.325 ips.

The PD: The licensee failed to perform an in-service test in accordance with the

prescribed procedure, contrary to regulatory requirements or self-imposed

standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective. Specifically, the limit was an optional licensee administrative

limit. Alternatively, the problem was identified less than 9 months after

exceeding the administrative limit and the pump was subsequently tested

at the required frequency.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the problem was identified greater than nine months later

and testing to ensure continued reliability of the degrading pump was not

performed at the required frequency.

Example 2.c The licensee missed an hourly update of a state agency during a

declared Unusual Event because of an oversight by the Shift Manager.

The PD: The licensee failed to perform an hourly update of state agencies during

declared emergencies which is contrary to regulatory requirements or

self-imposed standards.

Minor if: The PD did not adversely affect the emergency preparedness

cornerstone objective. Specifically, there was no impact on public health

and safety, and it did not affect the state agency’s ability to function

during the emergency.

MTM if: The PD was associated with the ERO performance attribute of the

emergency preparedness cornerstone and adversely affected the

cornerstone objective to ensure that the licensee is capable of

implementing adequate measures to protect the health and safety of the

public in the event of a radiological emergency. Specifically, there was a

failure in the communication functions committed to in the emergency

plan which affected the state agency’s ability to respond to the

emergency.

Example 2.d During an inspection of silicon foam penetration seals, an inspector noted

that foam extrusion (3/8 inch) from repaired seals was less than the

amount specified in the seal repair procedure (1/2 inch). However, the

silicon foam vendor'’s instructions permit extrusions as little as 1/4¼ inch.

The PD: The licensee failed to perform the seal repair in accordance with the

licensee’s procedure which is contrary to regulatory requirements or

self-imposed standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the seal was still functional, and the flood or fire

barrier’s functionality was not affected. Specifically, the silicon foam

vendor'’s instructions permit extrusions as little as 1/4¼ inch.

MTM if: The PD was associated with the protection against external factors (i.e.,

fire) attribute of the mitigating systems cornerstone and adversely

affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, both the licensee and vendor

procedure requirements were not met, and the as left condition would

have impacted the ability of the seal to perform its function which affected

the flood or fire barrier’s functionality.

Example 2.e The licensee'’s procedure required that heat tracing be energized in the

diesel fire pump room from September 30 to April 30. In December, an

inspector observed that the heat tracing was de-energized. The room

temperature was 68 degrees, maintained by the steam boiler (50 degrees

was the minimum temperature for operations).

The PD: The licensee did not maintain heat tracing energized as required by a

licensee procedure. This is contrary to a regulatory requirement or

self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the temperature had not dropped below the minimum

temperature for operations. Specifically, although heat trace was not

energized, room temperature was not less than 50 degrees during the

exposure period.

MTM if: The PD was associated with the protection against external factors (i.e.,

weather) attribute of the mitigating systems cornerstone and adversely

affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the room temperature fell below

the minimum temperature of 50 degrees and stayed below 50 degrees for

enough time where it would have resulted in a measurable reduction in

the equipment’s ability to function when called upon.

Example 2.f An operating procedure requires the shift supervisor to advise the station

manager prior to making any mode changes. A mode change is made

without this notification due to an oversight by the shift supervisor.

The PD: The shift supervisor did not advise the station manager prior to making a

mode change as required by the licensee’s operating procedure, contrary

to a regulatory requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective as this notification was purely administrative in nature and had

no impact on safety equipment and no safety consequences.

MTM if: The PD was not purely administrative in nature and adversely affected

the mitigating systems cornerstone objective by impacting safety

equipment. If the inspector identifies an issue of concern beyond this

missed notification, the inspector should consider pursuing a different PD.

3. Dimensional, Time, Calculation, or Drawing Discrepancies

Example 3.a A temporary modification was installed on one of two redundant

component cooling water system surge tanks to restore seismic

qualification. The calculations were found to contain technical errors, such

as incorrect assumptions regarding length of piping.

The PD: The licensee failed to ensure the calculation supporting a temporary

modification accurately reflected the design which is contrary to a

standard or regulation.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

The errors were non-significant or non-consequential. Seismic

qualification was not in question since the error in length was small and

the available margin easily compensated for the error. (i.e., the conditions

described in the MTM description below were not applicable.)

MTM if: The PD adversely affected the mitigating systems cornerstone objectives.

Specifically, regardless of the conclusion of the operability or functionality

determination, the calculation errors resulted in reasonable doubt about

the equipment’s seismic qualifications, which reduced assurance in the

equipment’s availability and reliability and required the licensee to revise

the calculation (see below) or revise or rework the modification to resolve

the seismic concerns.

For example, if the calculation was revised there would be reasonable

doubt if, the licensee: (a) used a different calculation/approach because

the original approach resulted in unfavorable margin (where “unfavorable

margin” means that had the correct values been used originally, the

licensee’s design process would not have accepted the modification); or

(b) revised assumptions solely to obtain favorable results; or (c) revised

other calculations in order to establish operability or functionality; or

(d) determined the remaining margin fell outside the licensee’s design

process acceptance criteria.

Example 3.b A controlled design drawing shows a plug valve where a ball valve is

actually installed. The service water valve design was changed to a ball

valve to support FLEX to a ball valve, but the licensee failed to update the

drawing.

The PD: The licensee’s failure to ensure the design of service water system was

correctly translated into drawings which is contrary to regulatory

requirements or a self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

The correct valve type (ball) was installed, and the error only involves the

drawing and did not have an adverse impact on other structures,

systems, and components (SSCs).

MTM if: The PD adversely affected the mitigating systems cornerstone objective

to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences.

Specifically, this drawing was used to support another modification or

calculation such that the assumption (characteristics) of a plug valve were

carried through to other applications.

Note: If the drawing was correct (that is, a plug valve should have been

installed), the PD should address the incorrect installation – not that the

drawing had an error.

Example 3.c

A licensee procedure required that all valves specified on a locked valve

list be indicated as locked on the plant drawings. The inspectors identified

safety-related valves on the locked valve list that were not indicated as

locked on the plant drawings.

The PD: Activities were not performed in accordance with procedures.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

This is a non-significant drawing discrepancy and this oversight (valves

not indicated as locked on the drawing) only involved the drawing and did

not adversely affect the mitigating systems cornerstone objective by

adversely impacting other SSCs.

MTM if: The PD adversely affected the mitigating systems cornerstone objective

to ensure the availability, reliability, and capability of systems.

Specifically, this drawing was used to support another modification,

calculation, or procedure, and in those applications, the failure to indicate

a locked requirement impacted the reliability of the valve. For example,

during an emergency, this valve may need to be open. Since the drawing

does not indicate the valve is locked, additional time may be needed to

open the valve (obtain a key). In other words, the assumption

(characteristics) of an unlocked valve was carried through to other

applications.

Example 3.d

Technical specifications require that a primary sample to be taken and

analyzed within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of a power change in excess of 20 percent. A

chemistry sample was taken and analyzed within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and 35 minutes

after a recent power increase from 60 to 85 percent.

The PD: The licensee failed to take and analyze a primary sample as required by

TS.

Minor if: This is a failure to implement a requirement that has no safety impact;

therefore, did not adversely impact the barrier integrity cornerstone

objectives. The delayed sample did not impact the validity of the sample

when taken. The licensee’s analysis accounted for the delay and results

remained in specification.

MTM if: The PD impacted the barrier integrity cornerstone objective to provide

reasonable assurance that physical design barriers protect the public

from radionuclide releases caused by accidents or events. Specifically,

the sample was delayed to the extent that the sample results were not

reliable. The licensee’s analysis could not account for the delay.

Example 3.e

During construction of a safety-related concrete wall, an imbedded

structural insert is cocked at an angle of 6 degrees. The specification

required plus-or-minus 3 degrees. The worker who placed the insert failed

to use a level as required.

The PD: The licensee failed to install a structural insert in accordance with

licensee procedures.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

The misoriented insert had no safety impact. The licensee determined

(without other action) that the insert could be abandoned in place or that

the as-found condition of the insert is acceptable (i.e., the conditions

described in the MTM description below were not applicable.)

MTM if: The PD adversely affected the mitigating systems cornerstone objective.

Specifically, a safety-related attachment had been made to an

out-of-specification insert and placed in service and:

1. The resulting condition was unacceptable, and the licensee had to

perform a modification or maintenance to compensate for the misaligned insert,

-or2. Regardless of the final operability or functionality, the as-found

condition resulted in reasonable doubt about the equipment’s seismic

qualifications, which reduced assurance in the equipment’s availability

and reliability and required the licensee to revise the calculation (see

below) or revise or rework the modification to resolve the seismic

concerns.

For example, there would be reasonable doubt if when revising the

calculation, the licensee (a) used a different calculation/approach

because the original approach resulted in unfavorable margin (where

“unfavorable margin” means that had the correct values been used

originally, the licensee’s design process would not have accepted the

modification); or (b) revised assumptions solely to obtain favorable

results; or (c) revised other calculations in order to establish operability or

functionality; or (d) determined the remaining margin fell outside the

licensee’s design process acceptance criteria.

Example 3.f

The licensee's flood wall is required to be 12 feet tall. The NRC discovers

that, in one section, the wall is only 11 feet, 10.5 inches tall.

The PD: The licensee failed to maintain the flood wall as described in the UFSAR

(or Physical Security Plan), which states that the height is required to be

12 feet tall.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

The height discrepancy is insignificant. The as-found height, though less

than specified, still meets its function of avoiding spill over or meets

security needs. (Note: In making this determination, the conditions

described in the MTM if section below are not applicable.)

MTM if: The PD adversely affected the mitigating systems cornerstone objective

to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. For

example, in order to justify the as-found condition, the licensee (a) used a

different calculation/approach because the original approach resulted in

unfavorable margin (where “unfavorable margin” means that had the

correct values been used originally, the licensee’s design process would

not have accepted the modification); or (b) revised assumptions solely to

obtain favorable results; or (c) revised other calculations in order to

establish operability or functionality; or (d) determined the remaining

margin fell outside the licensee’s design process acceptance criteria.

Example 3.g

The final safety analysis report (FSAR) states the volume of the refueling

water storage tank is 250,000 gallons. The actual volume is 248,000

gallons.

The PD: The facility was not consistent with the FSAR which is contrary to a

required regulation or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

This is a non-significant dimensional discrepancy. Assuming the accident

analysis calculations used a smaller volume, the as-found volume meets

its function.

MTM if: 1) The PD adversely affected the mitigating systems cornerstone

objective. Specifically, regardless of the conclusion of the operability or

functionality determination, the as-found condition resulted in reasonable

doubt with respect to the availability, reliability, or capability of systems

reliant on this volume. For example:

• The accident analysis assumed a value higher than the as-found and

the actual volume required the licensee to re-perform accident

analysis calculations to assure the accident analysis requirements

were met.

-or-

• The accident analysis assumed a value below the as-found; however,

calculations supporting other SSCs or functions requires a higher

value; thus, requiring the licensee to re-perform calculations to

demonstrate operability or functionality.

In these cases, when the calculation is revised to restore operability,

there would be reasonable doubt if the licensee: (a) revised assumptions

solely to obtain favorable results; or (b) revised other calculations in order

to establish operability or functionality; or (c) determined the remaining

margin fell outside the licensee’s design process acceptance criteria; or

(d) used a different calculation/approach because the original approach

resulted in unfavorable margin, meaning that had the correct values been

used originally, the licensee’s design process would not have accepted

the modification.

-or-

(2) The PD if left uncorrected, would have the potential to lead to a more

significant safety concern. Although the as-found volume was above that

assumed in the accident analysis, the licensee did not have procedural

controls to maintain the level above that required in the accident analysis

and absent NRC intervention the licensee may not have maintained the

capability of the RWST to mitigate a large break loss of coolant accident.

Example 3.h

The licensee used a non-conservative value for condensate storage tank temperature as an input to an accident analysis calculation. The value used was 118 degrees Fahrenheit where the actual value can be as high as 120 degrees Fahrenheit. As a result of this error, there was a slight reduction in the net positive suction head (NPSH) available to the safety injection pumps under accident conditions.

The PD:

The licensee failed to ensure design requirements were correctly translated into calculations in accordance with regulatory requirements or self-imposed standards.

Minor if:

The PD did not adversely affect the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.

The reduction in available NPSH was only a few percent of the available margin and there was no reasonable doubt of operability or functionality. (i.e., the conditions described in the MTM description below were not applicable.)

MTM if:

(1) The PD adversely affected the mitigating systems cornerstone objective. Specifically, regardless of the final operability or functionality, the as-found condition was such that there was reasonable doubt with respect to the capability of systems that take suction from this tank. For example, in evaluating the as-found condition, there would be reasonable doubt with respect to the capability of systems if the licensee:

(a) used a different calculation/approach because the original approach resulted in unfavorable margin (where “unfavorable margin” means that had the correct values been used originally, the licensee’s design process would not have accepted the modification); or (b) revised assumptions solely to obtain favorable results; or (c) revised other calculations in order to establish operability or functionality; or (d) determined the remaining margin fell outside the licensee’s design process acceptance criteria.

-or-

(2) The PD if left uncorrected, would have the potential to lead to a more significant safety concern. To use this question, the inspector would need to assess whether there is a declining trend in pump performance such that adequate NPSH would not be maintained prior to an action level to address pump performance. In other words, if left uncorrected, the pump would reach a condition such that it may not be able to maintain adequate NPSH to support accident mitigation before the licensee identified the issue.

Example 3.i

In the procedure for safe shutdown of the plant from the alternate control

panel, the licensee annotated that the operators could complete a time

critical task within 10 minutes. It is later determined that the validation

tests showed that completing the required tasks could take as long as

eleven minutes.

The PD: The licensee failed to ensure procedures met design requirements.

Minor if: The PD did not adversely affect the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. This was a non-significant

error. The licensee’s accident analysis assumed the actions were

completed in 15 minutes.

MTM if: The PD adversely affected the mitigating systems cornerstone objective.

Specifically, regardless of the results of the final operability or functionality

determination, the discrepancy for the time-critical action resulted in a

condition where there was a reasonable doubt of operability or

functionality of a system or component.

For example, in evaluating the as-found condition, there would have been

reasonable doubt with respect to the capability of system or component if:

10 minutes was assumed in the accident analyses and the licensee was

unable to justify using 11 minutes or greater.

-or The licensee was able to justify the additional time, but, in evaluating the

as-found condition, the licensee: (a) used a different calculation/approach

because the original approach resulted in unfavorable margin (where

“unfavorable margin” means that had the correct values been used

originally, the licensee’s design process would not have accepted the

modification); or (b) revised assumptions solely to obtain favorable

results; or (c) revised other calculations in order to establish operability or

functionality; or (d) determined the remaining margin fell outside the

licensee’s design process acceptance criteria.

Example 3.k

A previously identified body-to-bonnet leak on an RHR valve was

increasing in leak rate. A check valve, downstream of the valve,

separated the cool, low pressure RHR system from the high temperature,

high pressure feedwater system. The check valve also had a known

leakage and was being monitored. In their operability determination, the

licensee addressed the potential impact of leakage outside of

containment and monitored and tracked the quantity to ensure it

remained under the established administrative limits identified in the

operability determination. The inspector raised question on the impact of

the shutdown cooling (SDC) mode of RHR.

The PD: The licensee failed to assess the impact on the SDC mode of RHR in

operability determination x which is contrary to self-imposed standards.

(Note: There are no regulatory requirements to “adequately document”

operability determinations.)

(Note: In this case, potential PDs include failure to identify a condition

adverse to quality or failure to follow the licensee’s procedure for

documenting operability determinations. In this example, the PD

associated with the licensee’s procedures was selected to demonstrate

conditions for minor or MTM.)

Minor if: The PD did not adversely affect the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Although the licensee did

not have a lot of detail to justify operability associated with the SDC mode

(causing the inspector to question), the licensee did address the mode. In

the end, the system remained operable. Essentially, this issue of concern

is really focused on the paperwork and not on the status of the

equipment.

MTM if: The PD adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. The inspector identified the

licensee had not addressed the SDC mode such that the operability

conclusion was truly challenged, and the licensee had to perform actions

to continue to demonstrate operability. The outcome of this evaluation is

not a factor in minor or MTM.

Example 3.l

During a review of a licensee’s power operated valve activities, the

inspectors found that the licensee only incorporated test data from their

site when establishing design assumptions and did not include applicable

data from other plants within their fleet or from the nuclear industry. The

inspectors noted the licensee’s procedure stated a suitable testing

program included the results of a minimum population of 15 valves and

that, when available, test results across the fleet would be used in

establishing valve factors. The inspectors noted that the valve factors

used at the site were lower than what was used at other plant sites that

utilized industry data. This led to the inspector to question the valve

factor.

The PD: The licensee did not implement activities that would provide assurance

that specific POVs would meet their design basis functions which is

contrary to a regulatory requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the licensee was able to demonstrate that the site test

data population was sufficiently large to represent the performance

characteristics of the plant POVs. No changes to the POV testing and

maintenance programs for the subject valves were necessary per the site

POV program documents.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the licensee was unable to demonstrate that the site test

data population was sufficiently large to represent the performance

characteristics of the plant POVs. As a result, (for example), (1) factoring

in the fleet data resulted in a reasonable doubt with respect to the

availability, reliability, or capability of plant POVs and the licensee had to

re-perform a number of valve design calculations to demonstrate that they

could meet their design basis functions. or (2) several valves required

additional testing and maintenance per the site POV program documents

because of a loss of margin.

Example 3.m

While reviewing program documents associated with power operated

valves, the inspector noted that the licensee was not applying justified

differential pressure assumptions in calculating the design bases limits for

certain safety-related valves. Specifically, the licensee did not account for

design leakage past pressure isolation valves, which could increase the

differential pressure across several valves. Further review identified five

potentially impacted valves. (Note: at least one valve needs to be

identified.)

The PD: The licensee did not assume pressure isolation valve leakage when

calculating the design basis limits for several safety-related POVs which

is contrary to a regulatory requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective. The differential pressure assumption had a small effect on the

design calculations. Although margin was reduced, the valves did not

need additional testing or preventive maintenance per the licensee’s POV

program documents. In performing the analysis, the conditions described

in the MTM section are not applicable.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective. Specifically,

(1) the final operability determination concluded a valve was inoperable or

nonfunctional; or needed additional maintenance and testing per the site

POV documents; or required interim compensatory actions to maintain

operability/functionality.

-or-

(2) through the process of performing the operability/functionality

determination, there was reasonable doubt regarding the availability,

reliability, or capability of the valves. For example, in evaluating the

as-found condition, there would be reasonable doubt with respect to the

capability of the valves if: the licensee (a) used a different

calculation/approach because the original approach resulted in

unfavorable margin (where “unfavorable margin” means that had the

correct values been used originally, the licensee’s design process would

not have accepted the modification); or (b) revised assumptions solely to

obtain favorable results; or (c) revised other calculations in order to

establish operability or functionality; or (d) determined the remaining

margin fell outside the licensee’s design process acceptance criteria.

Example 3.n

While examining the degraded grid voltage calculations for a

risk-important, safety-related valve, the inspector noted that the licensee

did not have electrical calculations or test data that would support the

settings for thermal overloads protective devices for several safety-related

MOVs. As a result, it was not clear whether these valves would fulfill their

risk-important or safety-related functions during a range of postulated

events. The licensee performed an analysis for each affected valve.

The PD: The licensee failed to ensure the thermal overload protection settings on

safety-related MOVs were adequate to ensure the valves would perform

their function(s) which is contrary to a regulatory requirement or

self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the subject breaker was subsequently found to be in

specification. In performing the analysis, the conditions described in the

MTM section are not applicable or the current MOV testing program did

not need to be modified to address the issue (i.e., the current valve

testing and maintenance program is acceptable, as is.)

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective. Specifically,

(1) the final operability determination concluded a valve was inoperable or

nonfunctional; or needed additional maintenance and testing per the site

MOV documents; or required interim compensatory actions to maintain

operability/functionality.

-or-

(2) through the process of performing the operability/functionality

determination, there was reasonable doubt regarding the availability,

reliability, or capability of the valves. For example, in evaluating the

as-found condition, there would be reasonable doubt with respect to the

capability of the valves if: the licensee (a) used a different

calculation/approach because the original approach resulted in

unfavorable margin (where “unfavorable margin” means that had the

correct values been used originally, the licensee’s design process would

not have accepted the modification); or (b) revised assumptions solely to

obtain favorable results; or (c) revised other calculations in order to

establish operability or functionality; or (d) determined the remaining

margin fell outside the licensee’s design process acceptance criteria.

Example 3.o The inspectors noted the licensee’s safe shutdown analysis credited the

RCIC system for reactor water makeup and decay heat removal for the

alternate shutdown method from the remote shutdown panel (RSP). In

the event of a fire requiring control room evacuation, procedures directed

operators to place RCIC Remote Shutdown Transfer Switches in the

EMERGENCY position at the RSP. This isolated the control circuits for

the RCIC valves from the control room and connected a different set of

control fuses at the RSP for each valve. The new set of control fuses was

fed from a separate 250 volt direct current (VDC) power source.

During the review of MOV 1E51-F022, RCIC Test Bypass to Condensate

Storage Tank, the inspectors noted the main breaker supplied from

250 Vdc Motor Control Center (MCC) 121Y was a 7-Amp breaker, while

the control circuit fuse associated with the valve’s control room circuits

was 10 Amp. The inspectors were concerned that in the event of a control

room fire, fire-induced faults on the control circuits could cause the

associated 7 Amp, 250 VDC breaker to trip upstream of the 10 Amp

protective fuse. If the feed breaker tripped before the control room

protective fuse opened, the associated MOV would lose power for

operation from the RSP until the breaker was reset.

The PD: The licensee failed to ensure that the alternate shutdown capability was

independent of the control room which was contrary to a regulatory

requirement or self-imposed standard.

Minor if: The PD was minor because it did not affect the availability, reliability, and

capability of RCIC in the event of a fire. Specifically,

(1) existing procedures directed operators to reset the affected breakers if

tripped during the transfer and the licensee had demonstrated that the

action to reset the breakers could be performed in a timely manner.

-or-

(2) the licensee verified by walkdown that the breaker was replaced with a

higher rating. As a result, this PD is an administrative error with no

consequence. (Note: Inspector could pursue a PD related to configuration

control.)

MTM if: The PD was associated with the Mitigating Systems Cornerstone attribute

of Protection Against External Events (Fire), and affected the cornerstone

objective of ensuring the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences

(i.e., core damage). Specifically, in the event of a fire in the control room,

fire-induced failures could result in tripping the valve’s power supply

breaker prior to tripping the control power fuse which could impair the

operation of RCIC from the RSP. Actions to reset the associated breakers

were not contained in alternate shutdown procedures or the licensee

could not demonstrate that the action could be performed in a timely

manner.

4. Procedural Errors

Example 4.a A scaffold erected between safety-related plant service water strainers

was wedged tightly between the system piping. No engineering

evaluation was performed to assess the seismic impact of the scaffold.

The PD: The licensee failed to perform an engineering evaluation to assess the

seismic impact of an installed scaffold, contrary to a regulatory

requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because a later engineering evaluation determined that there is

no safety concern. Specifically, this is a procedural error that has no

safety impact.

MTM if: The PD was associated with the design control attribute of the mitigating

systems cornerstone and adversely affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond

to initiating events to prevent undesirable consequences. Specifically, the

subsequent engineering evaluation confirmed that the affected pipe would

be subject to seismic induced pipe loads that had not been considered in

the original analysis and increased the probability of pipe failure during

accident mitigation.

Example 4.b While performing a reactor protection system test procedure, an operator

inadvertently operated the bypass switch which caused a single channel

trip condition.

The PD: The operator failed to follow the procedure and adequately self-check to

ensure the right switch was manipulated. This is contrary to a regulatory

requirement or self-imposed standard.

Minor if: The PD did not adversely affect the initiating events cornerstone objective

because this was an insignificant procedural error and there were no

safety consequences.

MTM if: The PD was associated with the human performance attribute of the

initiating events cornerstone and adversely affected the cornerstone

objective to limit the likelihood of events that upset plant stability and

challenge critical safety functions during shutdown as well as power

operations. Specifically, the error caused a reactor trip or other transient.

Example 4.c A valve motor operator was test wired for reading operating current during

testing performed in accordance with Generic Letter 89-10. The valve

was successfully cycled, the data recorded and determined to be within

the acceptable range, and the valve was returned to service. However,

the ammeter used a 0-100 amp scale instead of a 0-10 amp scale as

required by the procedure.

The PD: The licensee failed to follow a test procedure which was contrary to a

regulatory requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because subsequent retest with the proper meter resulted in

satisfactory amperage readings. Specifically, this was a procedural error

that had no impact on safety equipment. The mistake did not result in an

actual equipment problem.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the retest revealed that the valve was returned to service and

because of the inadequate measurement, the licensee did not identify

that the thrust data for the affected MOV was inadequate to perform the

valve function under the limiting design basis event.

Example 4.d During a review of the emergency lighting in the safety injection pump

room, an inspector identified that the lighting was less than FSAR design

levels for operator action.

The PD: The licensee failed to ensure the emergency lighting in the safety

injection pump room was less than the FSAR design levels for operator

action. This is contrary to a regulatory requirement or self-imposed

standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because operators are procedurally required to carry flashlights

and would have no problems functioning in this light condition.

MTM if: The PD was associated with the human performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the degraded lighting condition would significantly impact the

operator’s ability to operate equipment within the safety injection pump

room during implementation of procedures that required manual operator

actions within this room for accident mitigation.

Example 4.e The inspector identified a valve with a missing name-plate; a violation of

plant procedures requiring that all equipment be labeled. This valve

needs to be manipulated as part of an operator time-critical action.

The PD: The licensee did not label plant equipment as required by plant

procedures which is contrary to regulatory requirements or self-imposed

standards. Plant procedures required that equipment be labeled.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because operators referred to the plant drawings and routinely

train on this time-critical action. Specifically, this is a failure to meet

procedural requirements that had no safety impact. The operators used

the drawings and had no trouble identifying the valve location in time to

perform the necessary operator time-critical action.

MTM if: The PD was associated with the human performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, because of the lack of label an improper valve manipulation

occurred that resulted in a plant transient or that rendered a mitigating

system incapable of responding to an initiating event.

Example 4.f A small leak occurs on a welded connection in the diesel generator day

tank causing a slow drip of fuel oil onto the floor in the diesel room.

Maintenance used a sealant to temporarily repair the leak and wrote a

work order for a permanent repair, which was scheduled for the next

outage. Later, the seal failed, and additional leakage occurred, which

dripped on a safety-related solenoid. The licensee subsequently

determined that the wrong sealant was used in the temporary repair.

The PD: The licensee failed to adequately correct a condition adverse to quality

which is contrary to a regulatory requirement or self-imposed standard.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because this is a failure to correct a condition adverse to quality

that had no adverse impact on both the solenoid valve and the diesel

generator.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the inadequate repair led to additional leakage from the day

tank and a safety-related solenoid valve was soaked in fuel oil preventing

the valve from performing its safety function.

Example 4.g The reach rod for a safety-related valve was jammed and could not be

used. However, the valve could be operated manually one level down.

This condition existed for 2 years and, despite complaints from the

operators, it was not fixed. The NRC inspector noted that this

work-around cost about 1 minute in operator response time and

recognized that manual manipulation of this valve was required by certain

off-normal procedures.

The PD: The licensee failed to promptly correct a condition adverse to quality as

required by regulatory requirements or self-imposed standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because this is a failure to implement a corrective action that

had little to no safety impact. The valve was accessible during all these

off-normal events and could still be operated and the extra time

requirement would not affect recovery operations.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, there are credible scenarios within the current

abnormal/emergency procedures where access to the effected valve

would be restricted for environmental reasons (heat, radiation, oxygen,

etc.), or a time critical action could not be performed within the timeline

credited in the design basis.

Example 4.h An inspector discovered that 3 of 150 emergency response organization

(ERO) members who are on the duty roster in different functional areas

were not current in their training. The licensee’s emergency plan required

that all members be trained annually.

The PD: The licensee failed to follow and maintain the effectiveness of their

emergency plan which is contrary to regulatory requirements or

self-imposed standards.

Minor if: The PD did not adversely affect the emergency preparedness

cornerstone objective because there are others on the duty roster in each

functional area whose qualifications are current.

MTM if: The PD was associated with the ERO readiness attribute of the

emergency preparedness cornerstone and adversely affected the

cornerstone objective to ensure that the licensee is capable of

implementing adequate measures to protect the health and safety of the

public in the event of a radiological emergency. Specifically, emergency

response personnel qualification lapses occur in such a manner that ERO

minimum staffing positions cannot be staffed by qualified individuals.

Example 4.i An inspector found that the evaluation of the adequacy of emergency

preparedness procedures in the annual audit was not in sufficient depth in

one functional area.

The PD: The licensee did not evaluate the adequacy of EP procedures which is

contrary to regulatory requirements or self-imposed standards.

Minor if: The PD did not adversely affect the emergency preparedness

cornerstone objective because the licensee reviewed the areas

insufficiently covered and found no problems. Specifically, no problems

were identified and the revisions of the procedures that were not audited

addressed improvements identified in drills.

MTM if: The PD was associated with the procedure quality attribute of the

emergency preparedness cornerstone and adversely affected the

cornerstone objective to ensure that the licensee is capable of

implementing adequate measures to protect the health and safety of the

public in the event of a radiological emergency. Specifically, the

procedures that were not evaluated were in a condition that would

adversely affect the licensee’s response to an emergency.

Example 4.j NRC inspectors identified three 10-foot lengths of wood left from a

scaffold disassembled the previous week in the auxiliary feedwater pump

room. The licensee had not completed an engineering evaluation

approving this temporary storage location for transient combustible

materials as required by the fire protection plan.

The PD: The licensee failed to complete an engineering evaluation to compensate

for all transient combustibles in an area which is contrary to regulatory

requirements or self-imposed standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because this is a failure to implement a fire protection program

requirement that has little or no safety impact. Specifically, the transient

combustibles could not affect equipment important to safety and did not

exceed any licensing basis requirements. The licensee was able to show

that the transient combustibles were well below the fire hazards analysis

limits.

MTM if: The PD was associated with the protection against external factors (i.e.,

fire) attribute of the mitigating systems cornerstone and adversely

affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, one of the following occurred:

(a) the fire loading was not within the fire hazard analysis limits; (b) a

credible fire scenario involving the identified transient combustibles could

affect equipment important to safety; (c) the identified transient

combustibles were in excess of those permitted by an NRC safety

evaluation report which formed the licensing basis for the plant; or (d) the

identified transient combustibles adversely affected a combustible free

zone's function to prevent fire spread (e.g., a large fire on one side might

propagate to the other side).

Example 4.k The TS require that one-third of all safety-related molded case circuit

breakers be tested each refueling outage (such that all are tested every

three outages) and that the instantaneous trip currents be recorded for

trending purposes. The NRC inspector found that two outages ago during

testing, the instantaneous trip current for a breaker was not tested due to

the breaker not being listed for the instantaneous trip current test. The

last recorded trip current for this breaker was five outages ago.

The PD: The licensee failed to perform required breaker testing within three

outages as specified by regulatory requirements or self-imposed

standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the subject breaker was subsequently found to be in

specification. Specifically, this is a failure to implement a procedural

requirement that has no safety impact. All other tests on the breaker were

satisfactory at the time of testing and the trip current was subsequently

found to be in specification.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, the subject breaker was out of specification and adversely

affected the equipment’s availability, reliability, and/or capability.

Example 4.l The TS require that 10 percent of all safety-related snubbers be tested

each refueling outage and that if one failure occurs, an additional

10 percent sample be tested during the same outage. One snubber in the

original population of 17 snubbers (there are a total of 168 snubbers)

fails, necessitating an additional sample of 17 snubbers. However,

because of an oversight by the licensee, only 16 additional snubbers are

tested with no failures.

The PD: The licensee failed to perform the snubber testing as required by

regulatory requirements or self-imposed standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because this is a failure to implement a procedural requirement

that has no safety impact since none of the additional snubbers tested

failed.

MTM if: The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, a failure had occurred in the additional (missed) sample,

necessitating yet another expansion of the sample, and this expansion of

the sample did not occur.

Example 4.m The inspector identified a motor operated valve (MOV) torque switch was

not installed properly. Specifically, the licensee’s procedure to re-install

MOV RH-6833 did not include a step to reset the MOV torque switch to

previously installed torque switch settings. Once identified, the licensee

had to enter an unplanned maintenance window to reset the toque switch.

The PD: The licensee failed to ensure torque switch settings were included in

installation procedures which is contrary to regulatory requirements or

self-imposed standards.

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because the inadequate procedure would not have resulted in

equipment damage. Specifically,

• although not required by the procedure, maintenance worker training

would have the worker set the torque switch to the prior setting

-or-

• the licensee analysis confirmed the worst-case torque switch setting

would not have damaged the valve subcomponents had the valve

actuated.

MTM if: The PD was associated with the procedure quality attribute of the

mitigating systems cornerstone, and it adversely affected the cornerstone

objective. Specifically, regardless of the final operability or functionality,

the as-found condition was such that there was reasonable doubt whether

the valve would have been capable of performing its function had it been

called upon. For example, in evaluating the as-found condition, the

licensee (a) used a different approach because the original approach

resulted in unfavorable margin (where “unfavorable margin” means that

had the correct values been used originally, the licensee’s design process

would not have accepted the modification); (b) revised assumptions solely

to obtain favorable results; (c) revised other calculations in order to

establish operability or functionality; (d) determined the remaining margin

falls outside the licensee’s design process acceptance criteria; (e) had to

replace equipment because of damage or licensee was unable to

demonstrate operability.

5. Work in Progress Findings

Example 5.a Prior to system restoration following a modification, the NRC inspectors

identified that the modification package that replaced the spent fuel pool

cooling system suction piping did not include the siphon because the

engineers failed to identify the requirements of the original design. The

siphon hole was not installed. Due to the location of the piping, a

siphoning event would lower spent fuel pool level below the TS limit, but

not to the point where fuel would have been uncovered.

The PD: The pipe design was not correctly translated into work instructions and

drawings, in accordance with regulatory requirements or self-imposed

standards.

Minor if: The PD, if left uncorrected, would not have led to a more significant safety

concern. Work was still in progress, and it is reasonable to conclude the

PD would have been identified through the post modification testing or

licensee processes prior to the return to service. Therefore, it would not

have been left uncorrected nor would it have adversely affected the

associated cornerstone objectives since the system was would have been

fully restored and able to perform/support any safety function.

MTM if: Work was still in progress; however, it is reasonable to conclude the PD

would not have been identified prior to return to service. The PD, if left

uncorrected, would have the potential to lead to a more significant safety

concern. Specifically, the condition wasn’t identified during post

modification testing or during restoration activities. The performance

deficiency was identified at a point in the process where there were no

more licensee review or approval barriers that could reasonably preclude

the system’s return to service with this design error present. If left

uncorrected, the lack of siphon hole would have the potential to lead to a

more significant safety concern, i.e., could allow the licensee to reach a

condition outside of that allowed by its TS.

The PD if left uncorrected, would have the potential to lead to a more

significant safety concern. Absent NRC intervention the licensee would

not have identified the condition until the spent fuel level decreased to a

point that resulted in an increase in radiation levels in areas frequented by

outage workers and cause unnecessary radiation exposure (e.g., not

ALARA).

Example 5.b During installation of a modification, the licensee failed to follow the

installation procedures and a check valve required for the system to

perform its function is installed backward.

The PD: The licensee failed to install a check valve correctly in accordance with

licensee procedures which is contrary to regulatory requirements or

self-imposed standards.

Minor if: The PD was identified through a planned post modification test, or other

process-driven review, without causing any actual adverse effects to

other operating systems. Therefore, the degraded condition did not

adversely affect the associated cornerstone objectives since the system

caused no adverse interactions and was itself out of service and not

being relied upon at the time of discovery.

MTM if: Prior to system restoration (for example, during the post modification

test), the PD results in an event that adversely affects one of the

cornerstone objectives, such as: impacting the capability of another SSC

or causing an initiating event (e.g., a feedwater transient resulting in a

rapid downpower or reactor scram; or causing an unanticipated

occupational radiation safety hazard by overfilling a tank that creates a

contaminated spill).

Example 5.c A solenoid that did not meet its safety-related procurement specifications

was inadvertently screened through receipt inspection and placed in the

warehouse. When the solenoid was about to be installed during the

maintenance window, an electrician noted that it was not the correct type

called out in the work order instructions.

The PD: The licensee failed to assure that purchased equipment conformed to the

procurement documents in accordance with 10 CFR 50, App B, Criterion

VII, “Control of Purchased Material, Equipment, and Services.”

Minor if: The discrepant solenoid was not installed in the plant and an extent of

condition review confirms the discrepant solenoid was not installed in any

system in the plant. The licensee’s process (last barrier) worked. The PD

had no effect on the associated cornerstone objectives since no SSC in

the plant was impacted.

MTM if: An extent of condition review revealed that this incorrect model solenoid

had already been installed in other trains or systems currently in

operation at the plant, thereby adversely impacting the associated

cornerstone objectives of ensuring the reliability, capability, or availability

of an SSC.

Note: If the extent of condition review indicated a systemic problem in the

procurement area, each case would need to be evaluated for

significance. If the discrepant equipment was not installed in the plant,

this trend would not be more than minor as long as other barriers via the

licensee’s procurement, work management process, or both still existed

to prevent installation of the unqualified material parts into the plant.

Example 5.d The licensee identified indications on the reactor vessel weld RPV-1 while

performing an examination required the ASME Code Section XI. The

licensee detected indications by ultrasonic examination (UT) to be of

acceptable size and returned the reactor vessel weld to service.

Subsequently, the inspectors identified errors in calibration of the UT

examination equipment used by the licensee to size these indications and

were concerned that the indications may not be acceptable.

The PD: The licensee failed to perform an adequate calibration of UT equipment

used to size flaws in on the reactor vessel weld RPV-1 which is contrary

to regulatory requirements or self-imposed standards.

Minor if: The PD did not adversely affect the Initiating Events cornerstone attribute

of equipment performance because when the licensee repeated the UT

examination with appropriate calibrated UT instruments, the verified flaws

met ASME Code Section XI acceptance criteria.

MTM if: The PD adversely affected the Initiating Events cornerstone attribute of

equipment performance and adversely affected the cornerstone objective

because when the licensee repeated the UT examination with appropriate

calibrated UT instruments, the flaws did not meet ASME Code Section XI

and required further analysis or repairs to be accepted for continued

service. The PD adversely affected the Initiating Events cornerstone

attribute of equipment performance and adversely affected the

cornerstone objective because absent NRC intervention, the licensee’s

incorrect application of UT would have likely been repeated and

continued incorrect application of UT would result in missed flaws in the

reactor coolant system resulting in increased likelihood for inservice

failures (e.g., a LOCA).

6. Health Physics

General Screening Criteria: A radiation protection program is composed of several barriers to

ensure adequate protection of occupational and public health and safety through

defense-in-depth. A radiation protection barrier is program element that serves a specific

radiation safety function. For example, procedures provide a barrier whose main function is to

provide employees with sufficient instruction, so they can safely perform their duties as radiation

workers. Other examples of barriers include ALARA plans and controls, radiological surveys

and monitoring, labeling and posting, access controls, and respiratory protection programs.

A minor PD in the implementation of a single radiation protection barrier results in a minimal

reduction in the protection of health and safety. However, a PD that renders a radiation

protection program barrier ineffective, or indicates that a barrier is ineffective, would be

appropriately classified as a more-than-minor PD.

When determining if a PD could reasonably be viewed as a precursor to a significant event,

inspection staff should evaluate whether the PD could have resulted in, or did result in, an

overexposure to a real individual (i.e., a “significant event” is viewed as an exposure beyond the

dose limits contained in 10 CFR Part 20 or other radiation safety-related criteria in section 04.05

of IMC 0309). To determine if an overexposure was a reasonable potential outcome, inspection

staff should consider whether events, as they occurred, or with a minor, realistic alteration of

circumstances (e.g., timing, source strength, distance and shielding), would have resulted in an

over-exposure to a real individual, and not merely whether a series of events could be

postulated that could result in an over-exposure.

When determining if a PD would have the potential to lead to a more significant safety concern,

inspection staff should evaluate if events, as they occurred, or with a minor, realistic alteration of

circumstances, were indicative of a failure of a radiation protection program barrier, or if the PD

resulted in an actual personnel safety concern (e.g., faulty respiratory protection equipment). In

applying this guidance, inspection staff can consider mitigating measures for the deficient

barrier that were in place at the time of occurrence (e.g., use of electronic alarming dosimeter

with appropriately conservative dose rate alarm set points), and (2) the actual radiological risk

introduced by the PD. The radiological risk consists of resultant doses, or doses that could have

reasonably occurred with minor, realistic adjustments to events as they occurred. In general, the

radiological risk is expressed in terms of dose to real individuals; however, in certain

circumstances the risk to health and safety is not adequately reflected in the resulting dose and

thus other factors must be considered in determining the level of radiological risk (e.g.,

magnitude of radiological hazards).

When determining if a PD adversely affected the associated cornerstone objective, inspection

staff should consider whether the PD impacted the effectiveness of a radiation protection

program barrier such that the licensee’s ability to provide adequate protection to a worker or a

member of the public was challenged. These PDs generally result in actual unplanned or

uncontrolled doses to workers or members of the public, or actual unplanned or uncontrolled

releases of radioactive material to the unrestricted area.

Example 6.a A licensee performed a required radiation survey, but the survey was not

documented properly, or a mistake occurred in the documentation of the

survey.

The PD: The licensee failed to document a radiation survey as required by

regulations and/or licensee procedures.

Minor if: The required survey was actually performed, AND the lack of a survey

record did not result in the licensee failing to establish appropriate

radiological controls (e.g., access controls, dosimetry, and respiratory

protection); failing to properly inform workers of the radiation hazard; or

failing to adequately control the release of radioactive material from the

site.

MTM if: The PD had the potential to lead to a more significant radiation safety

concern because of an ineffective radiation program barrier. Specifically,

the lack of a survey record resulted in the licensee not establishing

appropriate radiological controls; not properly informing workers of the

radiation hazard; or not adequately controlling the release of radioactive

material from the site.

Example 6.b Radiation detection instruments (e.g., portable instruments or installed

area radiation monitors) were not calibrated properly, or not response

checked prior to use in accordance with site procedures.

The PD: The licensee did not calibrate or response check radiations protection

instrumentation as required by regulatory requirements or self-imposed

standards.

Minor if: When recalibrated or response checked, the as-found condition of the

instrument was within acceptance criteria for the calibration or response

check, or the instrument provided conservative measurement (i.e.,

over-response), or if the installed area radiation monitor would still have

adequately performed its alarm function.

MTM if: The PD had the potential to lead to a more significant radiation safety

concern because of an ineffective radiation program barrier. Specifically,

when recalibrated or response checked, the as-found condition of the

instrument was not within acceptance criteria for the calibration, or

response check, or if the installed area radiation monitor would not have

adequately performed its alarm function.

Example 6.c Licensee personnel missed a step in the procedure for setting alarm set

points for effluent control/monitoring equipment associated with normal

operations (i.e., non-emergency planning (EP) program activities)

resulting in incorrect set points.

The PD: Licensee personnel did not comply with the procedure for establishing set

points for equipment used for effluent control/monitoring as required by

regulatory requirements or self-imposed standards.

Minor if: The effluent monitor alarm set point would have allowed the

instrumentation to perform its intended function (e.g., trip or alarm

function) to prevent an instantaneous effluent release in excess of the

applicable technical specification instantaneous concentration limit for

liquids or dose rate limits for gases.

MTM if: The PD was associated with the plant facilities/equipment and

instrumentation attribute of the public radiation safety cornerstone and

adversely affected the cornerstone objective to ensure adequate

protection of public health and safety from exposure to radioactive

materials released into the public domain as a result of routine civilian

reactor operation. Specifically, the effluent monitor with its alarm set point

would have failed to perform its intended function (i.e., trip or isolation

function) to prevent an effluent release in excess of the applicable

technical specification instantaneous concentration limit for liquids or

dose rate limits for gases.

Example 6.d A health physics technician provided job coverage or performed a task

that the technician was not fully qualified to perform.

The PD: The licensee did not utilize qualified health physics technicians as

required by regulatory requirements or self-imposed standards.

Minor if: The work performed by the technician (e.g., radiological surveys and

monitoring) provided an adequate level of radiological protection.

MTM if: The PD had the potential to lead to a more significant radiation safety

concern because of an ineffective radiation program barrier. Specifically,

one or more errors of consequence to radiological safety were made by

the technician such that the work performed by the technician did not

provide an adequate level of radiological protection.

Example 6.e An item (e.g., tool, dirt, secondary resin) containing detectable licensed

radioactive material (RAM) was inadequately released from further

radiological control (e.g., item was inadequately surveyed).

The PD: Licensee did not control licensed material as required by regulatory

requirements or self-imposed standards.

Minor if: The follow-up survey concludes that the item contained radioactive

material with a measured dose rate that is indistinguishable from

background (as measured in a low background area, at a distance of

30 cm from the item with a micro-rem per hour-type instrument that

typically uses a 1 inch by 1 inch scintillation detector) and the calculated

dose using a realistic exposure scenario is less than or equal to 1 percent

of applicable public dose limits.

MTM if: The PD is associated with the program and process attribute of the public

radiation safety cornerstone and adversely affected the objective to

ensure adequate protection of public health and safety from exposure to

radioactive materials released into the public domain as a result of routine

civilian nuclear reactor operation. Specifically, an uncontrolled release of

RAM occurred as determined by a follow-up survey with measured dose

rate that is distinguishable from background (as measured in a low

background area, at a distance of 30 cm from the item with a micro-rem

per hour-type instrument that typically uses a 1 inch by 1 inch scintillation

detector) or the calculated dose using a realistic exposure scenario is in

excess of 1 percent of applicable public dose limits.

Note: A PD does not occur in the situation where an item with RAM has been properly

surveyed using appropriate survey techniques, is evaluated as not having detectable

RAM and released, and is later discovered as containing RAM when surveyed using

a more sensitive survey method.

Example 6.f A radiation survey did not identify a radiation area, high radiation area

(HRA) or locked high radiation area (LHRA).

The PD: The licensee did not perform an adequate survey to appropriately post a

radiation area, HRA or LHRA.

Minor if: Radiological conditions existed in the previously unknown radiation area

such that the dose to an uninformed worker (e.g., a worker who had not

been briefed on or reviewed radiological conditions) was unlikely to

exceed an unplanned dose of 10 mrem, OR

For deficiencies occurring in HRAs, all the following conditions were met:

  • the accessible dose rate did not exceed 1,000 mrem/hr at 30 centimeters
  • all workers with access to the dose rate were wearing electronic alarming dosimeters (EADs) with dose rate alarm setpoints sufficiently low to allow workers to take appropriate actions before encountering dose rates exceeding 100 mrem/hr
  • the accessible dose rate was identified by an EAD dose rate alarm
  • all affected workers responded to the alarm per licensee procedures MTM if: The PD had the potential to lead to a more significant safety concern because of an ineffective radiation program barrier. Specifically, any of the following occurred:
  • the inadequate survey, or failure to survey, resulted in an accessible dose rate that exceed 1,000 mrem/hr at 30 centimeters (i.e., area was an unposted LHRA).
  • an unknown radiation area existed, and the dose to an uninformed worker (e.g., a worker who had not been briefed on or reviewed

radiological conditions) was likely to exceed an unplanned dose of 10 mrem

  • The inadequate survey, or failure to survey, resulted in an unposted HRA and any of the following conditions were met:
  • a worker with access to the dose rate was not wearing an EAD
  • the EAD dose rate alarm setpoint was not sufficiently low to allow

workers to take appropriate action before encountering dose rates

exceeding 100 mrem/hr

  • A worker was aware of an EAD alarm and did not respond per licensee procedures

Note 1: For the purposes of this appendix, HRAs are defined as areas with accessible dose

rates that are greater than 100 mrem/hour at 30 centimeters but that do not exceed

1,000 mrem/hr at 30 centimeters. Locked high radiation areas (LHRA) are defined as

areas with accessible dose rates greater than 1,000 mrem/hr at 30 centimeters.

Example 6.g A worker improperly entered a posted HRA or LHRA (i.e., not in

accordance with Technical Specifications and plant procedures).

The PD: Licensee personnel did not comply with procedures for entry into an HRA or LHRA.

Minor if: The improper entry occurred in a conservatively posted HRA (i.e., the

highest actual radiation level in the posted area was less than or equal to

100 mrem/hr at 30 cm), OR

The improper entry occurred in an actual HRA (i.e., highest actual

radiation level in the posted area exceeded 100 mrem/hr at 30 cm, but did

not exceed 1000 mrem/hr at 30 cm) and all the following conditions were

met:

  • the worker was wearing an EAD
  • the EAD dose rate alarm setpoint was sufficiently low to alert workers before encountering dose rates exceeding 100 mrem/hr
  • if an EAD alarm was received the worker responded to the alarm per licensee procedures MTM if: The PD had the potential to lead to a more significant safety concern because of an ineffective radiation program barrier. Specifically, an improper entry was made into an LHRA, OR The improper entry was made into an HRA and any of the following conditions were met:
  • the worker was not wearing an EAD
  • the EAD alarm setpoint was not sufficiently low to alert workers before encountering dose rates exceeding 100 mrem/hr
  • A worker was aware of an EAD alarm and did not respond per licensee procedures

Note 1:For the purposes of this appendix, HRAs are defined as areas

with accessible dose rates that are greater than 100 mrem/hour at 30

centimeters but that do not exceed 1,000 mrem/hr at 30 centimeters.

Locked high radiation areas (LHRA) are defined as areas with accessible

dose rates greater than 1,000 mrem/hr at 30 centimeters.

Example 6.h Radiological controls were not established or utilized such that an

unplanned internal exposure occurred or was likely to occur with a minor

alteration of circumstances. The failure may have involved an inadequate

radiological survey, improper ventilation controls, or an individual’s failure

to follow RWP requirements.

The PD: The licensee failed to adequately survey (or implement ventilation

controls or follow licensee procedures) in an area that in a reasonable

exposure scenario could have been the source of internal exposure.

Minor if: The worker did not receive or was unlikely to receive greater than

10 mrem committed effective dose equivalent (CEDE).

MTM if: The PD is associated with the program and process attribute of the

occupational radiation safety cornerstone and adversely affected the

cornerstone objective to ensure adequate protection of the worker health and safety from exposure to radiation from radioactive material during

routine civilian nuclear reactor operation. Specifically, the PD resulted in

inadequately controlled radiological conditions such that the worker

received or was likely to receive greater than 10 mrem CEDE.

Example 6.i PDs occurred in ALARA planning and/or job execution that resulted in the

actual collective dose exceeding the planned (or adequately re-planned),

intended dose for a work activity.

The PD: The licensee’s ALARA planning or radiological controls did not prevent

unplanned, unintended dose for a work activity per regulatory

requirements or self-imposed standards.

Minor if: The actual collective dose was ≤ 5 person-rem, OR the actual collective

dose was greater than 5 rem but did not exceed the planned (or

adequately re-planned), intended dose by more than 50 percent.

MTM if: The PD is associated with the program and process attribute of the

occupational radiation safety cornerstone and adversely affected the

cornerstone objective to ensure the adequate protection of the worker

health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation. Specifically, the licensee

did not effectively implement procedures or engineering controls to

achieve doses that are ALARA as indicated by actual collective dose

exceeding 5 person-rem AND exceeding the planned (or adequately

re-planned), intended dose by more than 50 percent (e.g., a task planned

for 4 person-rem received 6.1 person-rem, or a task re-planned for 14

person-rem received 22 person-rem).

Note 1: The 10 CFR 20.1101 regulations establish a regulatory requirement to use, to the

extent practical, procedures and engineering controls to achieve doses that are

ALARA. Licensees that establish and maintain ALARA programs and procedural

controls will normally meet this regulatory requirement and will not be in violation of

10 CFR 20.1101 for not reducing doses to an absolute minimum. However, a PD

meeting the MTM criteria can still be dispositioned as inspection finding without an

associated violation.

Note 2: In cases where the licensee arbitrarily divides the radiological work into very small

work activities, or dose estimates were over-estimated for the purpose of avoiding

inspection findings, the criteria can apply to a reasonable grouping of work and

reasonable dose estimates as determined by NRC inspection staff (i.e., consistent

with prior history or industry norms).

Note 3: The expanded work scope could have resulted from several factors related to

additional maintenance or repair that the licensee would not have been reasonably

expected to have foreseen before the work began. Once a work activity is started,

and the expanded work scope is fully understood, it may be necessary to re-plan the

activity and revise the dose estimate. The revised dose estimate should be based on

the full scope of the work had it been known at the time of the initial planning.

Example 6.j A licensee failed to perform environmental monitoring for a significant

liquid or gaseous effluent exposure pathway due to several missed

sample collections or erroneous analyses.

The PD: A licensee failed to conduct adequate environmental monitoring sufficient

to evaluate the relationship between effluent releases and radiation doses

to individuals from principal pathways of exposure.

Minor if: The exposure pathway did not contain radioactivity or radiation levels that

exceeded 10 percent of the 10 CFR 50, Appendix I, section II ALARA

objectives.

MTM if: The PD was associated with the program and process attribute of the

public radiation safety cornerstone and adversely affected the

cornerstone objective to ensure adequate protection of public health and

safety from exposure to radioactive materials released into the public

domain as a result of routine civilian nuclear reactor operation.

Specifically, an inadequately monitored exposure pathway contained

radioactivity or radiation levels that exceeded 10 percent of the 10 CFR 50, Appendix I, section II ALARA objectives (excluding C-14).

Note 1: Per NUREG-1301 and NUREG-1302, the significant liquid effluent exposure

pathways are potable water, aquatic foods, shoreline deposits, and irrigated foods;

and the significant gaseous effluent exposure pathways are noble gas submersion,

inhalation, ingestion and external (direct) radiation. For the purposes of

environmental monitoring programs, the terminology “significant” effluent exposure

pathway and “principal” effluent exposure pathway is interchangeable.

Example 6.k A licensee failed to label a container of licensed material being stored

within the restricted area, as required.

The PD: The licensee failed to ensure that each container of licensed material

bears a label that includes sufficient information to permit individuals

handling or using the containers, or working in the vicinity of the

containers, to take precautions to avoid or minimize exposures.

Minor if: The radiation level from the unlabeled containers did not exceed 5

mrem/hr at 30 centimeters, OR the unlabeled container was in an

adequately posted area and subject to plant procedures to verify

adequate labelling before removal from the posted area.

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective radiation program barrier. Specifically, the

radiation level from the unlabeled container exceeded 5 mrem/hr at

30 centimeters, AND the unlabeled container was not in an adequately

posted area and subject to plant procedures to verify adequate labelling

before removal from the posted area.

Example 6.l A licensee ships radioactive material in correct packaging but with an

error in the shipping papers.

The PD: The licensee did not adequately describe hazardous material in shipping

papers as required by regulatory requirements or self-imposed standards.

Minor if: The error does not impact the emergency telephone number; exclusive

use status; consignee address; identification number; proper shipping

name; hazard class; label (as applicable); physical/chemical form of the

material; the name of each radionuclide; and the error did not exceed

20 percent of the mass, volume or activity of the material.

MTM if: The PD is associated with the program and process attribute of the public

radiation safety cornerstone and adversely affected the cornerstone

objective to ensure adequate protection of public health and safety from

exposure to radioactive materials released into the public domain as a

result of routine civilian nuclear reactor operation. Specifically, the

licensee committed an error in the shipping papers for radioactive

material that impacted the emergency telephone number; exclusive use

status; consignee address; identification number; proper shipping name;

hazard class; label (as applicable); physical/chemical form of the material;

the name of each radionuclide shipped, or the error exceeded 20 percent

of the mass, volume or activity of the material.

Example 6.m The licensee established by procedure an administrative limit of

occupational exposure of 2 rem per year. Documented approval from the

site radiation protection manager (RPM) was required for any individual to

exceed the procedural limit. Contrary to the licensee’s program, an

individual received 2.7 rem in one year without documented approval.

The PD: Licensee personnel did not comply with procedures for personnel

monitoring as required by regulatory requirements or self-imposed

standards.

Minor if: The failure was administrative in nature in that the RPM was involved in

the planning and decision-making associated with exceeding the

administrative limit (i.e., the PD is limited to the documentation associated

with the approval).

MTM if: The PD is associated with the program and process attribute of the

occupational radiation safety cornerstone and adversely affected the

cornerstone objective to ensure adequate protection of worker health and

safety from exposure to radiation from radioactive material during routine

civilian nuclear reactor operation. Specifically, the licensee did not

effectively implement procedures to monitor and control radiation

exposure to workers resulting in an unplanned and uncontrolled exposure

of a worker over the administrative limit.

Example 6.n A licensee intends to use respiratory protection to limit intakes of

radioactive material (i.e., the respiratory protection will not be used to

protect workers from occupational hazards other than airborne radioactive

contamination) and conducts respirator fit testing using a different type of

harness than that which is assigned to workers for use in the field.

The PD: The licensee did not conduct respirator fit testing with the same make,

model, style, and size of respirator that will be used in the field as

required by regulatory requirements or self-imposed standards.

Minor if: The PD does not result in a personnel safety issue resulting from the use

of equipment whose purpose is to limit intakes of radioactive material,

AND the performance deficiency did not impact the required fit factor of

the respirator issued to the worker for use in the field.

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective radiation protection program barrier.

Specifically, the PD resulted in a personnel safety concern resulting from

the use of equipment whose purpose is to limit intakes of radioactive

material, OR the PD adversely impacted the required fit factor of the

respirator issued to the worker for use in the field.

7. Part 37 – Physical Protection of Category 1/Category 2 Quantities of Radioactive Material

General Guidance: Licensee programs to protect category 1 and category 2 radioactive

material, or “Part 37 material,” from theft and diversion consist of several barriers (e.g., access

authorization programs and multiple security provisions), which provide defense-in-depth. An

isolated performance deficiency in the implementation of an element of the licensee’s program

can be considered a minor violation because the existence of multiple barriers would provide

adequate protection of the material. A missing or ineffective element would be considered

more-than-minor because this condition represents a reduction in defense-in-depth.

Administrative issues (e.g., not meeting training documentation requirements) are minor

provided they do not result in the failure of a program element.

Because material in transit is at a higher risk of theft or diversion than material stored at a site in

general, PDs which occur during the transport of category 1 or category 2 material are

more-than-minor unless they are of a purely administrative nature (e.g., failure to document

preplanning or coordination provided such efforts did occur) or they result in a minor impact on

the security of the shipment (e.g., temporary loss of redundant form of communication,

temporary loss of telemetric position monitoring).

Performance deficiencies that are within the scope of EGM-2014-001 are considered minor

violations. However, these performance deficiencies shall be documented in inspection reports

in accordance with IMC 0611, section 0611-12 and, for tracking purposes, issued a new

enforcement action number each time enforcement discretion is granted. In these cases, the

justification for the issue being dispositioned as minor is the very low risk of theft and diversion

associated with large components and robust structures as described in EGM-2014-001.

Note: A PD associated with a licensee’s Part 73 security plan used to provide equivalent

protection for Part 37 materials should be dispositioned using section 14 by a qualified security

inspector.

Example 7.a A licensee allows unescorted access to a category 2, or greater, quantity

of radioactive material to a person whose background investigation was

deficient.

The PD: The licensee’s access authorization program did not ensure that an

individual whose assigned duties require unescorted access to category 1

or category 2 quantities of radioactive material are trustworthy and

reliable.

Minor if: The deficiency did not impact information that was relevant to access

approval and thus would not have changed the licensee’s trustworthiness

and reliability determination.

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective program barrier. Specifically, an unauthorized

person who would not have been granted unescorted access had they

completed the licensee’s access authorization program requirements was

granted unescorted access to category 2, or greater material.

Example 7.b A licensee established a temporary security zone, outside of the

Protected Area (PA) but inside a continuous physical barrier, and the

licensee failed to establish and maintain adequate means of monitoring

and detection.

The PD: The licensee failed to maintain the capability to continuously monitor and

detect without delay all unauthorized entries into its security zones which

was contrary to a regulatory requirement or a licensee standard.

Minor if: The following conditions were met:

  • The licensee’s security force regularly surveils (e.g., several times per day), either through direct line of sight or remote visual surveillance the location of the temporary security zone.
  • Per the licensee’s procedures, security would be alerted to and respond to an individual who trespasses into temporary security

zones, and * The licensee recognizes and responds to the failure in a timely manner (i.e., within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of discovery).

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective program barrier. Specifically, category 1 or

category 2 material was left unsecured and any of the following conditions

were met:

  • The deficient temporary security zone was established in an area not regularly surveilled by the licensee’s security force,
  • Security would not be alerted to or respond to a trespasser of the temporary security zone, or
  • The licensee does not recognize or respond to the failure in a timely manner (i.e., within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />).

Example 7.c The licensee’s Part 37 plan does not describe a physical protection

measure used to protect Part 37 material from theft and diversion, or the

licensee’s Part 37 plan does not describe how a Part 73 measure is used

to provide a level of protection equivalent to Part 37 requirements.

The PD: The security plan failed to describe the measures and strategies used to

satisfy requirements which was contrary to a regulatory requirement or a

licensee standard.

Minor if: The physical protection measure was in place and functional.

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective program barrier. Specifically, the physical

protection measure was not in place or functional.

Example 7.d The licensee did not coordinate with the local law enforcement agency

(LLEA) regarding the protection of category 1 or category 2 material

within the 12-month limits.

The PD: The licensee failed to coordinate with the LLEA at least every 12 months

which was contrary to a regulatory requirement or a licensee standard.

Minor if: The licensee had an existing relationship with the LLEA and coordinated

with the LLEA within an 18-month period.

MTM if: The PD had the potential to lead to a more significant safety concern

because of an ineffective program barrier. Specifically, the licensee had

not coordinated with the LLEA for responding to threats to the licensee’s

facility in over 18 months.

8. Maintenance Rule

Example 8.a During an inspector’s review of the licensee’s 10 CFR 50.65a(3) periodic

evaluations of the site maintenance program, the inspector noted that two

evaluations exceeded the 24 month interval by approximately 2 and

6 months, respectively.

The PD: The licensee did not perform periodic maintenance evaluations with a

periodicity specified in regulatory requirements or self-imposed standards.

Minor if: The objectives of the mitigating systems cornerstone were not adversely

affected because the failure to perform the periodic 50.65(a)(3) evaluation

within the required interval did not adversely affect the balance of

reliability and unavailability and no adjustments to the maintenance

program were warranted.

MTM if: The objectives of the mitigating systems cornerstone were adversely

affected because the failure to perform the periodic 50.65(a)(3) evaluation

within the required interval affected the balance between reliability and

unavailability and adjustments to the maintenance program were

warranted but not completed.

Example 8.b The inspectors identified that during an (a)(3) periodic evaluation, the

licensee failed to include the system unavailability time during TS

required surveillance testing of the emergency diesel generators (EDG).

Although the licensee conducts monthly EDG testing, the EDGs are

unavailable to perform their intended safety function during TS

surveillance testing for a few minutes during each monthly test.

The PD: The licensee failed to consider all unavailability when conducting the

(a)(3) evaluation which was contrary to a regulatory requirement or a

licensee standard.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected since the contribution to unavailability due to the surveillance

testing was insignificant when compared to total unavailability, and it did

not impact the balancing of availability and reliability.

MTM if: The mitigating systems cornerstone objectives were adversely affected

because the contribution to unavailability due to the surveillance testing

was significant enough to affect the balancing determination such that a

change in the maintenance program was warranted.

Example 8.c The inspectors identified that the licensee had not included some

components of the augmented off-gas system within the scope of its

program for implementation of the Maintenance Rule. Failure of these

components could result in a plant transient or scram and are therefore

required to be in scope.

The PD: The licensee failed to scope certain components of the augmented offgas system which could have caused a plant transient or scram if failed,

which was contrary to a regulatory requirement or a licensee standard.

Minor if: Cornerstone objectives were not adversely affected since the licensee

had been performing appropriate preventive maintenance and there were

no equipment performance problems. Had the components been scoped,

the preventive maintenance being performed would demonstrate effective

control of equipment performance and condition as provided in paragraph

(a)(2) of the Maintenance Rule.

MTM if: Cornerstone objectives were adversely affected because effective control

of equipment performance or condition for equipment that should have

been scoped was not demonstrated, for example through performance

criteria that were not met.

Example 8.d In accordance with the guidance of IP 71111.13, inspectors reviewed the

plant’s maintenance risk assessment performed pursuant to

10 CFR 50.65(a)(4) for in progress maintenance activities and identified

that the risk assessment was inadequate. Specifically, one or more of the

following were identified: (a) not all ongoing maintenance activities

affecting SSCs within the licensee’s established (a)(4) scope had been

taken into account; (b) one of the maintenance activities was taking

longer than assumed in the risk assessment; (c) plant

conditions/operations, including TS requirements, were not consistent

with the assumptions used in the risk assessment; or (d) relevant

information provided to the risk assessment tool/process was

inaccurate/incomplete.

The PD: The licensee failed to perform an adequate risk assessment when

required by regulatory requirements or self-imposed standards.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected because the overall corrected risk assessment would not result

in a higher licensee-established risk category and would not require

additional risk management actions (RMAs) under licensee procedures*.

MTM if: The mitigating systems cornerstone objectives were adversely affected

because either: (1) the overall corrected risk assessment would result in a

higher licensee-established risk category or would require additional

RMAs under plant procedures*; (2) the risk assessment failed to correctly

account for (at least qualitatively) the loss or significant uncompensated

impairment of a key operating or shutdown safety or probabilistic risk

assessment function; or (3) the credited function would not have been

maintained due to the failure to identify or implement RMAs.

  • Note: Under certain circumstances regarding an assessed risk level, the inspector may

identify RMAs that should be taken which could be contrary to the required RMAs in

accordance with licensee procedures. In such cases, management review is required

for more-than-minor determination, including consultation with the regional

Maintenance Rule subject matter expert and then the Maintenance Rule lead in NRR

if necessary.

Example 8.e In accordance with the guidance of IP 71111.13, inspectors reviewed the

plant’s maintenance risk assessment for in progress maintenance

activities required by 10 CFR 50.65(a)(4) and identified that a risk

assessment had not been performed prior to commencing maintenance

activities or maintenance support activities that increased plant risk.

The PD: The licensee’s failure to perform a risk assessment when required is

contrary to a regulatory requirement or self-imposed standard.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected since the overall elevated plant risk would not put the plant into a

higher licensee-established risk category and would not require RMAs or

additional RMAs under licensee procedures*.

MTM if: The mitigating systems cornerstone objectives were adversely affected

since (1) overall elevated plant risk would put the plant into a higher

licensee-established risk category or would require RMAs or additional

RMAs under plant procedures*, (2) the risk assessment failed to correctly

account for (at least qualitatively) the loss or significant, uncompensated

impairment of a key operating or shutdown safety or probabilistic risk

assessment function, or (3) the credited function would not have been

maintained due to the failure to identify or implement RMAs.

Example 8.f In accordance with the guidance of IP 71111.13, the inspectors reviewed

the plant’s maintenance risk assessment for in progress maintenance

activities required by 10 CFR 50.65(a)(4) and determined that a risk

assessment had been performed when required and was adequate. Upon

inspection of the plant, the inspectors identified that one of the RMAs

prescribed by the licensee, the hanging of protected equipment signs on

entry doors to the 1A EDG room, had not been effectively implemented in

that the signs were not hung.

The PD: The licensee failed to manage risk which was contrary to a regulatory

requirement or a licensee standard.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected. There were no unauthorized individuals in the room, no work

was ongoing and, while protected equipment signs were not hung,

Operations was aware that the 1A EDG was considered protected

equipment as an RMA. Thus, the work control center would have known

the actual protected equipment status of the 1A EDG when determining

whether to authorize activities in the room.

MTM if: The mitigating systems cornerstone objectives were adversely affected.

There were unauthorized individuals in the room, work ongoing in the

vicinity of protected equipment that was not specifically authorized to be

conducted in the vicinity of protected equipment, or Operations was

unaware that the 1A EDG should have been considered protected and

thus may have authorized inappropriate work in the area.

Example 8.g The inspectors identified that the licensee did not properly identify or

process a Maintenance Rule functional failure of an SSC scoped into the

licensee’s Maintenance Rule program and currently in 10 CFR 50.65(a)(2) status.

The PD: The licensee’s failure to properly identify or process a Maintenance Rule

functional failure of an SSC scoped into the Maintenance Rule is contrary

to regulatory requirements or self-imposed standards.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected because, when the Maintenance Rule functional failure is

considered, it is still demonstrated that performance of the SSC was

being effectively controlled through appropriate preventive maintenance

such that the SSC remained capable of performing its intended function

(i.e., the requirements of 10 CFR 50.65(a)(1)/(a)(2) were always met).

MTM if: The mitigating systems cornerstone objectives were adversely affected

because, when the Maintenance Rule functional failure is considered,

performance indicates that the SSC was is not being effectively controlled

through appropriate preventive maintenance, and that the SSC was not

moved to 10 CFR 50.65(a)(1) (i.e., the requirements of 10 CFR 50.65(a)(1)/(a)(2) were not met).

9. Thermal Power Limits

Example 9.a While operating at 99.9 percent rated thermal power (RTP), operators

conducted a pre-planned evolution to swap operating feed pumps.

Operators did not comply with a licensee procedure prerequisite to

reduce thermal power 0.5% below RTP prior to the pre-planned feed

pump swap; which is in place to account for the anticipated 0.2 percent to

0.4 percent increase in thermal power. Upon starting the second feed

pump, thermal power increased to 100.2 percent RTP.

The PD: The licensee did not comply with procedural requirements for reducing

power prior to swapping the feed pumps.

Minor if: The PD was associated with the human performance attribute of the

Barrier Integrity Cornerstone but did not adversely affect the cornerstone

objective of providing reasonable assurance that the fuel cladding

protects the public from radionuclide releases caused by accidents or

events because operators, after realizing that thermal power had

exceeded RTP, promptly decreased thermal power below or at RTP and

thermal power remained bounded by the reactor safety analysis (i.e.

thermal power did not enter an unanalyzed region) and no safety limits

were exceeded.

MTM if: The PD was associated with the human performance attribute of the

Barrier Integrity Cornerstone and adversely affected the cornerstone

objective of providing reasonable assurance that the fuel cladding

protects the public from radionuclide releases caused by accidents or

events because either operators did not recognize that they had

exceeded RTP; operators recognized they exceeded RTP, but did not did

not take adequate or timely action to lower thermal power to or below

RTP due to actions that were not considered willful; fuel integrity limits

were exceeded; or maximum thermal power entered an unanalyzed

region. See Nuclear Energy Institute (NEI) Position Statement, referenced

in RIS 2007-21, Revision 1 (ML090220365) for more guidance.

Example 9.b Following several days of steady state operation at or below RTP,

operators operated the unit in excess of RTP as indicated by the 1-hour

core thermal power (CTP) indication.

To monitor and control reactor power in accordance with the operating

license, operators rely on computer-generated time-averaged indications

of CTP that are updated every 10 seconds, providing running averages

for 15-minute, 1-hour, 2-hour, and 8-hour CTP. A licensee procedure

requires operators to review 15-minute average CTP and make

necessary adjustments to maintain the 1-hour average CTP at or below

RTP. Similarly, it requires operators to review 1-hour average CTP and

make necessary adjustments to maintain the 2-hour average CTP at or

below RTP.

Contrary to this guidance and license RTP requirements, when the

15-minute average CTP indication exceeded RTP, operators did not

make necessary adjustments to maintain 1-hour CTP at or below RTP.

The PD: The licensee did not comply with procedure requirement to monitor

15-minute-, 1-hour-, and 2-hour average CTP and to make timely CTP

adjustments as necessary to maintain 1-hour average CTP within the

RTP limit as required by regulatory requirements or self-imposed

standards.

Minor if: The PD was associated with the human performance attribute of the

Barrier Integrity Cornerstone but did not adversely affect the cornerstone

objective of providing reasonable assurance that the fuel cladding

protects the public from radionuclide releases caused by accidents or

events because even though the 1-hour average CTP exceeded RTP, the

operators completed adequate and timely action to re-establish

compliance with procedure and license RTP requirements.

MTM if: The PD was associated with the human performance attribute of the

Barrier Integrity Cornerstone and adversely affected the cornerstone

objective of providing reasonable assurance that the fuel cladding

protects the public from radionuclide releases caused by accidents or

events. Specifically, one of the following occurred: after the 1-hour

average CTP exceeded the RTP, operators did not take adequate or

timely action to prevent exceeding the 2-hour average CTP from

exceeding RTP; fuel integrity limits were exceeded; or maximum thermal

power entered an unanalyzed region. See NEI Position Statement,

referenced in RIS 2007-21, Revision 1 (ML090220365) for more

guidance.

10. Worker Fatigue

Example 10.a Failure to Limit Work Hour Waivers for Covered Workers As Necessary

For Safety or Security. The licensee is required by regulation or standard

to manage fatigue for covered workers. This includes the number of work

hours, waivers and exceptions, self-declarations, and fatigue

assessments.

The PD: The licensee failed to provide individual waivers when individuals

exceeded working hour guidance which was contrary to a regulatory

requirement or a licensee standard.

Minor if: This incident did not adversely affect a cornerstone objective because it

was reasonably determined not to have demonstrated the potential to

erode the effectiveness of work hour controls.

MTM if: The licensee’s inappropriate use of a waiver adversely impacted a

cornerstone objective. Various cornerstones could become impacted

depending upon the waiver, the work performed, and the consequence of

the issue. For example, the inappropriate use of waivers allowed workers

to become fatigued. Because of the workers fatigue, a maintenance error

was introduced which adversely impacted the function of a safety-related

or risk significant SSC. This adversely affected the equipment

performance and human performance attributes of the mitigating systems

cornerstone objective. Specifically, the configuration error resulted in a

challenge to a critical safety functions and fatigue could not be ruled out

as a contributor.

Example 10.b Failure to Assess Individuals Competency to Perform Duties Prior to

Granting Work Hour Waivers. The licensee is required by regulation or

standard to manage fatigue for covered workers. This includes the

number of work hours, waivers and exceptions, self-declarations, and

fatigue assessments.

The PD: The licensee failed to evaluate fatigue on an individual basis which was

contrary to a regulatory requirement or a licensee standard.

Minor if: The failure to assess a covered worker face to face prior to granting work

hour waivers did not adversely affect a cornerstone objective because it

was reasonably determined not to have demonstrated the potential to

erode the effectiveness of work hour controls.

MTM if: The licensee’s inappropriate use of a waiver adversely impacted a

cornerstone objective. Various cornerstones could become impacted

depending upon the waiver, the work performed, and the consequence of

the issue. For example, a licensed operator, working under a waiver,

without having received a face-to-face assessment, incorrectly

reconfigured a safety-related structure, system, or component. The failure

to assess covered workers face-to-face prior to granting work hour

waivers was associated with the equipment performance and human

performance attribute of the initiating events cornerstone objective.

Specifically, the configuration error resulted in an at-power event that

upset plant stability and challenged critical safety functions and fatigue

could not be ruled out as a contributor.

11. Cybersecurity

Example 11.a NEI 08-09, Appendix A, Section 3.1.6 – Mitigation of Vulnerabilities and

Application of Cyber Security Controls

A critical digital asset (CDA) was classified by the licensee as a direct

CDA and the inspectors discovered that the licensee had inadequately

implemented some of the technical controls in Appendix D of NEI 08-09,

“Cyber Security Plan for Nuclear Reactors”.

The PD: The licensee’s failure to implement the required controls for a direct CDA

as required by regulatory requirements or self-imposed standards.

Minor if: Upon reassessment, the CDA met the criteria for an indirect CDA in

accordance with NEI 13-10 and all the required baseline controls were in

place for an indirect CDA. The PD can also be minor if the CDA met the

criteria for an indirect CDA in accordance with NEI 13-10 and alternate

controls were in place that were commensurate to the required baseline

controls.

MTM if: If the required baseline controls for an indirect CDA were not in place, or

the required Appendix D & E security controls were not in place for a

direct CDA, or adequate alternate security controls were not in place for

either indirect or direct CDA.

Example 11.b NEI 08-09, Appendix D, Section 1.17 – Wireless Access Restrictions

The CSP requires that scans are conducted every 31 days for

unauthorized wireless access points in accessible areas. Inspectors

found that the licensee had missed a scan as required by site procedures,

the scan was required within 31 days, but was not performed until

35 days.

The PD: The licensee failed to follow procedures which was contrary to a

regulatory requirement or a licensee standard.

Minor if: Once the scan was completed, no wireless access points were identified.

This is a failure to implement a requirement that had no safety, security,

or emergency preparedness impact. The scanning delay was not

significant (e.g., less than 25 percent of the required frequency – in this

case less than 7 days) and review of logs indicates that no rogue

connections occurred during the delay period.

MTM if: The PD adversely affected the security cornerstone objective because

multiple scans were being routinely missed or significantly delayed (e.g.,

more than 25 percent of the required frequency – in this case more than

7 days), or because rogue wireless access points were identified after the

scan was conducted or logs were reviewed.

Example 11.c NEI 08-09, Appendix D, Section 4.3 – Password Requirements

The inspector performed an initial review of the cybersecurity control

assessment that was completed for an auxiliary feedwater control system

which was determined to be a direct CDA. During the review, the

inspector observed that the evaluation for the password security control

stated that a password was not required and there was not an alternate

control evaluation performed. The digital device had the capability to store

a password in order to provide protective measures for access control

and multiple threat vectors existed. All other security controls had been

properly evaluated and implemented.

The PD: Failure to implement the required password security control for a direct

CDA as required by regulatory requirements or self-imposed standard.

Minor if: This is an isolated incident and alternate controls were implemented (e.g.,

component was in a locked vital area and had a locked cover protecting

the device from being reconfigured) even though the alternate control

evaluation was not performed and documented in the cybersecurity

control assessment. However, the licensee was able to provide an

evaluation that demonstrated that alternate controls/countermeasures

mitigate the consequences of the threat/attack vectors.

MTM if: The PD adversely affected the security cornerstone objective because

alternate controls were not implemented to protect this device. While the

device was located in a vital area, the device could be reconfigured, or

alternate controls were implemented to protect this device, but the

licensee was not able to provide an evaluation demonstrating that the

alternate controls/countermeasures mitigate the consequences of the

threat/attack vector(s) (mitigated the consequences of an attack the

control was designed to protect).

Example 11.d NEI 08-09, Appendix E, Section 10.3 – Baseline Configuration

The inspector performed a review of the cybersecurity control

assessment for a CDA. The licensee failed to implement the

cybersecurity control E10.3 “Baseline Configuration” which requires

licensees to document and maintain an up-to-date, complete, accurate,

and readily-available baseline for each CDA. When the inspector asked

for the running configuration of software on the CDA, a discrepancy

between the documented baseline configuration and the running

configuration was identified.

The PD: Failure to implement baseline configurations of digital devices within the

scope of 10 CFR 73.54 as required by regulatory requirements or

self-imposed standard.

Minor if: This is an isolated incident and the discrepancy between the baseline and

running configuration was an incorrect parameter – such as a version

number - related to software that did not impact the effectiveness of other

security measures (e.g., vulnerability management). Missing attributes did

not introduce a new vulnerability or an unmitigated vulnerability.

MTM if: The baseline configuration did not list software identified in the running

configuration, the gap was not an isolated incident, or an incorrect version

impacted the effectiveness of other security measures.

Example 11.e NEI 08-09, 4.4 Ongoing Monitoring and Assessment

The inspector performed a review of the cybersecurity control

assessment for a digital device within the scope of 10 CFR 73.54. When

performing verification of implemented security controls, the inspector

identified a security control that should have been implemented on the

digital device but was not. The inspector also determined that the

licensee had provided no documented evidence verifying ongoing

monitoring of the controls for the selected digital device.

The PD: Failure to implement the required verification of the security controls for a

digital device within the scope of 10 CFR 73.54 as required by regulatory

requirements or self-imposed standard. NEI 08-09 4.4 Ongoing Monitoring

and Assessment states “Ongoing assessments to verify that the

cybersecurity controls implemented for CDAs remain in place throughout

the life cycle of the CDA.”

Minor if: If an undetected or unauthorized change to a single security control would

not result in a reduction in the effectiveness in the defense in depth

protective strategy or there are no unmitigated vulnerabilities. An example

would be a reboot of a CDA that resulted in an unneeded application or

service running that had previously been disabled. If the running

application or service did not introduce any known vulnerabilities required

to be assessed per the vulnerability management policy, and other

defense in depth measures – such as a security information and event

management (SIEM) identifying new traffic from a port used by the

application – could mitigate the effect of the change, then the violation

would be minor.

MTM if: The PD adversely affected the security cornerstone objective because

failure to perform ongoing assessments of implemented cybersecurity

controls does not provide adequate protection by not verifying that the

cybersecurity controls implemented for CDAs remain in place throughout

the life cycle of the CDA. Failure to perform ongoing assessments of

cybersecurity controls also does not provide adequate protection for

detecting unauthorized changes to data or software that could adversely

affect safety, security, and emergency preparedness (SSEP) functions.

Example 11.f NEI 08-09, Appendix D, Section 5.1 Removal of Unnecessary Services

and Programs

The inspector performed an initial review of the cybersecurity control

assessment of an engineering workstation between security levels 3

and 4. The review found numerous unnecessary services installed and

not disabled on the workstation.

The PD: The licensee failed to remove and/or disable software components that

are not required for the operation and maintenance of the device which

was contrary to a regulatory requirement or a licensee standard.

Minor if: If the service or program does not introduce an unmitigated vulnerability

on the device. An example would be Server Message Block (SMB) on a

device where the operating system has been patched for the vulnerability.

MTM if: If the licensee has an unnecessary service or program and failure to

implement this control would result in a reduction of the defense-in-depth

protective strategy – such as not establishing an accurate baseline

configuration, not adequately screening vulnerability notices or having the

ability to detect an exploitable vulnerability, not having the ability to

determine that the unnecessary service has been enabled or an

unnecessary port in processing unidentified or unauthorized traffic, etc.

Example 11.g NEI 08-09, Appendix E, Section 5.5 Physical Access Control

The inspector performed a review of the cybersecurity control

assessment and a walkdown of an x-ray machine located in a warehouse

outside of the protected area. The review determined that insufficient

physical security controls were implemented for the x-ray machine.

The PD: Failure to implement controls for CDAs as required by the licensee's

Cybersecurity Plan. Specifically, the licensee failed to implement all

necessary controls for CDAs located outside the protected area.

Minor if: The licensee can demonstrate functionality and adequate defense in

depth protections to determine if the security function provided by the

x-ray machine has been compromised prior to operation. Adequate

alternate controls for a real-time intrusion protection (i.e., automated

detection capabilities) to immediately facilitate dispatching security

personnel to investigate and/or remediate a potential cybersecurity

concern include a combination of the following—physically protecting the

x-ray machine with serialized tamper seal tape, random security guard

patrols, cameras monitored by Site Security 24/7 and/or testing to verify

operability prior to use of searching packages/materials for contraband.

See NEI 08-09 Appendix E.3.6 for the security control “Security

Functionality Verification.”

MTM if: The licensee failed to implement or implemented inadequate alternate

controls to prevent and detect a compromise of near real time detection of

compromise of the security function of the x-ray machine.

Example 11.h NEI 08-09, appendix E, section 12, “Evaluate and Manage Cyber Risk,”

(Vulnerability Management).

The inspector performed a review of the cybersecurity control

assessment for a device within the scope of 10 CFR 73.54. The licensee

stated that they were following NEI 08-09 Addendum 5 for their

vulnerability management process. The inspector determined that the

licensee had not adequately implemented vulnerability assessments.

The PD: Failure to implement a vulnerability management process as required by

regulatory requirements or self-imposed standard.

Minor if: Vulnerability notices for applicable CDA software or firmware are tracked

in the licensee’s vulnerability management process using the periodicity

specified in their cybersecurity plan but the inspection identified an

isolated vulnerability not identified by the licensee.

MTM if: Review of vulnerability notices was based on limited input (i.e., not based

on multiple credible sources) or incorrectly performing vulnerability

assessments using the Common Vulnerability Scoring System (CVSS) as

specified in NEI 08-09 Addendum 5.

12. External Events

Example 12.a During the inspectors’ review of the ignition sources in a given fire area,

the inspectors discovered that the licensee’s fire PRA failed to identify

and evaluate all targets within an ignition source’s zone of influence that

could potentially contribute to the risk analysis of fire scenarios.

The PD: Failure to address the risk contribution associated with all potentially risk

significant fire scenarios for a given fire compartment/area, in the fire PRA

is contrary to regulatory requirements or self-imposed standard.

Minor if: When corrected, the risk significance of fire scenarios in the fire

compartment/area did not increase. The initiating events cornerstone

objective was not adversely affected since the fire protection strategies

for the area/zone remained sufficient even with the error.

MTM if: The fire PRA and the safe shutdown strategy had to be revised to

address the risk contribution associated with the fire scenarios. The

initiating events cornerstone objective was adversely affected because

the actual risk of fire scenarios was not known, and sufficient prevention

and mitigation measures were not in place (i.e., revisions to fire response

procedures or detection or suppression equipment were necessary).

Example 12.b The licensee relocated FLEX equipment as part of refueling outage

preparations because the normal haul path was impacted by outage

equipment staging. The inspectors identified that pre-outage staging and

relocation of FLEX equipment resulted in N and N+1 FLEX equipment

being stored in an unprotected manner, though still functional, for 23 days

without appropriate compensatory protective measures being taken.

The PD: Failure to meet NEI 12-06, Revision 4, which the licensee is committed to

for pre-staging FLEX equipment, is contrary to regulatory requirements or

self-imposed standards.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected. ‘N’ FLEX capability was met with unprotected equipment that

lacked appropriate compensatory measures for less than or equal to

14 days as allowed by NEI 12-06, Revision 4, or ‘N’ FLEX capability was

met though with unprotected equipment with appropriate compensatory

measures that were implemented for less than or equal to 90 days, as

allowed by NEI 12-06, Revision 4.

MTM if: The mitigating systems cornerstone objectives were adversely affected

since equipment unavailability exceeded previously approved limitations

in NEI 12-06, Revision 4. The FLEX equipment was unprotected without

compensatory protective measures for greater than 14 days, was

unprotected with appropriate compensatory protective measures for

greater than 90 days, or both trains were non-functional or unavailable for

greater than 7 days.

Example 12.c The inspectors identified that licensee procedures for FLEX equipment

storage did not ensure that FLEX equipment would be maintained at a

temperature that ensured its likely function when called upon. Specifically,

licensee procedures did not address protection of FLEX equipment from

cold weather in the event of a power loss to the FLEX storage buildings.

NEI 12-06, Section 8.3.1.2, states, in part, “Storage of FLEX equipment

should account for the fact that the equipment will need to function in a

timely manner.

The PD: The licensee did not provide direction on ensuring FLEX equipment

remained protected from cold weather upon a loss of power to the FLEX

storage buildings which was contrary to a regulatory requirement or a

licensee standard.

Minor if: The mitigating systems cornerstone objectives were not adversely

affected since cold weather conditions severe enough to impair the likely

ability of FLEX equipment to function never occurred and are not

expected to occur. A review of meteorological data from the site show

that typical cold weather experienced by the site would not drop FLEX

storage building temperature below the temperature range at which the

equipment would be likely to function when called upon (i.e., the typical

duration for low temperatures would not adversely affect the functionality

of the equipment).

MTM if: The mitigating systems cornerstone objectives were adversely affected

since cold weather conditions sufficient to impair the likely ability of FLEX

equipment to function had occurred, was occurring, or is known to occur

occasionally at the site. Actual FLEX storage building temperatures

dropped below the temperature at which FLEX equipment would be likely

to function when called upon, or typical cold weather experienced by the

site would be cold enough for a sufficient duration to raise reasonable

doubts about the likeliness that FLEX equipment would function when

called upon.

Example 12.d The inspectors identified that cabling associated with two independent

channels of spent fuel pool level instrumentation installed as part of postFukushima requirements, were routed in such a way that they came into

physical contact with each other. The licensee is committed to a design in

which there are two fully independent and redundant spent fuel pool level

monitoring systems that will provide continuous wide range water level

indication.

The PD: The licensee did not maintain two independent spent fuel pool level

monitoring channels in accordance with self-imposed standards.

Minor if: The barrier integrity cornerstone objective was not adversely affected.

The minor contact of the shielded jackets of the coaxial signal cables at a

single point did not impair the function of the spent fuel pool level

instruments. Further, the minor contact would not be expected to

significantly increase the likelihood of a common mode failure due to the

flexible nature of the cables and outer protective layer of the coaxial

cables being resistant to abrasion.

MTM if: The barrier integrity cornerstone objective was adversely affected. The

function of one or more of the spent fuel pool level instrumentation

channels was impaired or there were indications of ongoing damage to

the cables that did not yet impair the function of the spent fuel pool level

instrumentation but would be expected to had the condition not been

identified and corrected. Incorrect or unreliable spent fuel pool level

indication can impair the ability to ensure adequate spent fuel pool

cooling.

13. Service life

Example 13.a In 2005, the licensee assessed (as required by regulatory requirements or

self-imposed standards) a Vendor Bulletin which stated the period of time

that a Molded-Case Circuit Breakers (MCCBs) can be installed without

refurbishment or replacement is 20 years for mild environment

applications. Vendor Bulletin stated that this time interval could be

extended through preventive maintenance, testing, and aging analysis

based on operational usage (number of demands or cycles) and actual

plant conditions. The licensee’s engineering evaluation of the Bulletin

concluded that based on the environmental conditions and usage of the

affected MCCBs, the MCCBs should either be refurbished or replaced

before exceeding 20 years of service. The licensee planned to revise their

MCCB preventive maintenance procedures by 2008 to require

refurbishment or replacement of all MCCBs in safety-related systems

prior to exceeding 20 years of service.

During this inspection (2016), the preventive maintenance procedures

had not been updated thus the affected MCCBs remained in service for

26 to 28 years, well beyond their 20 year refurbishment or replacement

interval. To date, no MCCBs failures have occurred at the licensee’s site.

The PD: The licensee failed to translate MCCB refurbishment/replacement

schedules into maintenance instructions contrary to regulatory

requirements or self-imposed standards.

Minor if: If left uncorrected, it is not reasonable to conclude the PD would have the

potential to lead to a more significant safety concern. Specifically,

• the licensee re-evaluated existing preventive maintenance procedures

and determined the intent of the Vendor Bulletin was met,

-or-

• the licensee re-analyzed the existing engineering evaluation (or

performed a new one after NRC identification of the issue) and

determined the newly calculated time period extended beyond the

expiration of the operating license. In performing the new engineering

evaluation, the conditions in MTM below did not apply.

MTM if: If left uncorrected, the PD has the potential to lead to a more significant

safety concern. Specifically, absent NRC’s intervention, the license’s

failure to establish and perform appropriate preventative maintenance

refurbishments or replacements can lead to in-service component

deterioration and resultant failures of MCCBs to perform their

safety-related functions.

-or

The PD was associated with the equipment performance attribute of the

mitigating systems cornerstone and adversely affected the cornerstone

objective to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences.

Specifically, exceeding the previously analyzed time period for

replacement or refurbishment caused reasonable doubt on the continual

ability of the MCCBs to perform their safety-related functions. In

re-analyzing the existing engineering evaluation (or in performing a new

one after NRC identification of the issue), the licensee (a) used a different

approach because the original approach resulted in unfavorable margin;

or (b) revised assumptions solely to obtain favorable results; or

(c) revised other calculations in order to establish operability or

functionality; or (d) determined the remaining margin falls outside the

licensee’s design process acceptance criteria. Unfavorable margin means

that had the correct values been used originally, the licensee’s design

process would not have accepted the modification.

Example 13.b The inspectors noted that for the nuclear grade valve actuators,

Limitorque only specified a life expectancy of 40 years or 2000 cycles,

whichever came first. With implementation of extended 20-year plant

licenses, EPRI conducted Limitorque actuator testing to develop a

methodology that may be applied to justify extension of the life of an

actuator to 60 years and 4000 cycles. Licensees referencing this

methodology must implement the conditions specified in the EPRI report

to extend the life of their actuators. The Limitorque actuator fatigue life

extension process requires additional engineering review, analysis, and

thrust evaluation of each actuator to justify the life extension. Limitorque

has approved the use of the EPRI methodology for actuator fatigue life

extension. While reviewing MOV program documents, the inspector noted

that the licensee had extended the service life of its Limitorque MOVs

without a corresponding engineering analysis. The inspector noted the

licensee already entered their period of extended plant operation.

The PD: The licensee failed to analyze the acceptability of extending the service

life of MOV (specific name(s)) which is contrary to 10 CFR 50,

Appendix B, Criterion V, “Instructions, Procedures, and Drawings,” (or for

MOVs, 10 CFR Part 50.55a(b)(3)(ii))

Minor if: The PD did not adversely affect the mitigating systems cornerstone

objective because once performed, the additional engineering review,

analysis, and thrust evaluation of each actuator demonstrated the

actuators met their design basis functions for their extended design life

and the subject valves do not need additional testing or maintenance as a

result of the verification per the site MOV program documents. In

performing the reviews and analysis, the conditions in MTM below did not

apply (i.e., for minor, design assumptions were not changed to obtain

favorable results).

MTM if: (Assuming an actuator exceeded 40 years or 2000 cycles) The PD was

associated with the equipment performance attribute of the mitigating

systems cornerstone and adversely affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond

to initiating events to prevent undesirable consequences. Specifically,

(1) the licensee was unable to verify that the valves were operable based

on the assessment of the conditions in the EPRI report; or (2) as a result

of this issue, the licensee now needs to conduct maintenance or testing of

the subject valves per the site MOV program documents; or

(3) regardless of the final operability or functionality, the as-found

condition was such that there was reasonable doubt with respect to the

assurance of availability and reliability. For example, to ensure

qualification, the licensee (a) used a different approach because the

original approach resulted in unfavorable margin (where “unfavorable

margin” means that had the correct values been used originally, the

licensee’s design process would not have accepted the modification); or

(b) revised assumptions solely to obtain favorable results; or (c) revised

other calculations in order to establish operability or functionality; or

(d) determined the remaining margin falls outside the licensee’s design

process acceptance criteria.

(Use if the actuator did not exceed 40 years or 2000 cycles) If left

uncorrected, the valve’s actuator would have been installed beyond its

demonstrated life - challenging the capability and reliability of the valve to

perform its safety function when called upon in a harsh environment

during a design basis accident. Specifically, without NRC identification,

the actuator would likely have exceeded its demonstrated life because the

licensee had not scheduled a replacement prior to the identification and

(1) the licensee was unable to verify that the valves would remain

operable based on the assessment of the conditions in the EPRI report;

or (2) to ensure qualification beyond the 40 years/2000 cycles, the

licensee (a) used a different approach because the original approach

resulted in unfavorable margin (where “unfavorable margin” means that

had the correct values been used originally, the licensee’s design process

would not have accepted the modification); or (b) revised assumptions

solely to obtain favorable results; or (c) revised other calculations in order

to establish operability or functionality; or (d) determined the remaining

margin falls outside the licensee’s design process acceptance criteria.

14. Security

Example 14.a The licensee revised their target set(s) by removing a common element

from multiple sets but failed to provide training to security personnel for

the changes.

The PD: The licensee failed to train security personnel on site specific target sets

as required by 10 CFR Part 73, Appendix B, requirements (Section VI,

C.2(c)(10)).

Minor if: Removal of the target set elements did not affect the defense-in-depth

approach used in the licensee’s strategy to protect against design basis

threats nor would it have reduced the assurance of protection.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the licensee’s protective strategy could deploy or potentially

redirect security personnel to protect the removed target set elements,

leaving other target set equipment unprotected. The defense in depth

approach and assurance of protection against design basis threats was

adversely affected.

Example 14.b The location(s) to disable target set equipment were not identified.

The PD: The licensee failed to document and maintain an adequate process to

develop and identify target sets, to include the site-specific analyses and

methodologies used to determine and group the target set equipment or

elements as required by 10 CFR Part 73.55(f)(1).

Minor if: The location missed was collocated with other target set locations already

considered.

MTM if: The inadequate process to identify target set element locations could lead

to a more significant safety concern. Specifically, if the licensee’s process

does not have guidance to identify alternate locations, as evident through

multiple identified examples, it could result in locations not being

adequately protected, impacting the physical protection program’s ability

to prevent significant core damage and/or spent fuel sabotage.

Example 14.c Target set elements were not identified.

The PD: (a) If the target set element is not currently protected by the protective

strategy:

The licensee failed to analyze and identify site-specific conditions,

including target sets, that may affect the specific measures needed to

implement the requirements of this section and account for these

conditions in the design of the physical protection program as required by

10 CFR Part 73.55(b)(4).

(b) If the target set element(s) is currently protected by the protective

strategy:

The licensee failed to document and maintain an adequate process to

develop and identify target sets, to include the site-specific analyses and

methodologies used to determine and group the target set equipment or

elements.

Minor if: (a) The element of a target set that was missed is currently being

protected by the protective strategy (i.e., by virtue of proximity to other

target set equipment) and the element is being appropriately considered

in the insider mitigation program (i.e., by virtue of proximity of other target

set equipment).

(b) The target set element was not a standalone target set and it was an

isolated incident.

MTM if: (a) The PD adversely affected the security cornerstone objective.

Specifically, the licensee’s target set process did not identify the target set

element, or a standalone target set, to inform the site’s physical protection

program, thereby compromising the protection of target set equipment.

The defense in depth approach and assurance of protection against

design basis threats was adversely affected.

(b) The inadequate process to identify target set elements could lead to a

more significant safety concern. Specifically, if the licensee’s process

does not have guidance to identify target set elements, as evident

through multiple identified examples, it could result in target set elements

not being adequately protected, impacting the physical protection

program’s ability to prevent significant core damage and/or spent fuel

sabotage.

Example 14.d Cyberattacks were not considered in the identification of target sets.

The PD: The licensee failed to consider cyberattacks in the development and

identification of target sets, as required by 10 CFR Part 73.55(f)(2).

Minor if: The licensee’s assessment showed that any identified critical digital

assets not already included in target sets are protected (i.e., by virtue of

proximity to other target set equipment already identified).

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the licensee’s process to identify and develop target sets did

not identify critical digital assets that would compromise the ability of a

target set element to perform its function of preventing significant core

damage or radiological sabotage. The defense in depth approach and

assurance of protection against design basis threats was adversely

affected.

Example 14.e Security personnel were not properly suited, trained, equipped, or

qualified to perform their assigned duties and responsibilities in

accordance with their Commission-approved training and qualification

plan.

The PD: The licensee failed to implement required training requirements for

security personnel in accordance with Part 73, Appendix App B

(section VI.A.2).

Minor if: Security personnel did not receive all the required training; however, they

did not work at a post that required the missed training.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, security personnel were not trained in accordance with

training requirements and performed duties associated with the missed

training.

Example 14.f Licensee did not perform testing of perimeter intrusion detection system

(IDS) using the most likely penetration methods as required by the

security plan.

The PD: The licensee failed to test and verify that security systems and equipment

remained capable of performing their intended security function as

required by 10 CFR 73.55(n)(i).

Minor if: The IDS zone was retested with the most likely penetration method, and it

detected in accordance with requirements.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the IDS zone failed to detect when using the most likely

penetration method.

Example 14.g Licensee failed to add critical personnel to the critical group. This resulted

in critical personnel not receiving periodic clinical interviews and

reinvestigations.

The PD: The licensee failed to ensure critical personnel would receive periodic

clinical interviews as part of their psychological reassessments and

periodic reinvestigations as required by 10 CFR 73.56.

Minor if: None of the affected personnel exceeded the critical group

reinvestigation/reassessment period.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, personnel exceeded the critical group

reinvestigation/reassessment period.

Example 14.h Licensee security personnel, in a ready room or staging area, do not have

all required contingency equipment readily available.

The PD: The licensee failed to ensure that all firearms, ammunition, and

equipment necessary to implement the site security plans and protective

strategy are in sufficient supply, are in working condition, and are readily

available for use as required by 10 CFR 73.55(k)(2).

Minor if: All responders were aware of the location of the equipment and would be

able to retrieve the necessary security equipment in-route to the response

position without exceeding the response timeline as described in the

licensee’s protective strategy.

Not minor if: The PD adversely affected the security cornerstone objective.

Specifically, the responders would not be able to retrieve the necessary

security equipment within the predetermined timeline and the time

difference between the responder timeline and the adversary timeline

precludes the ability to intercede (as determined by the training timelines

to open port, ready weapon, and engage).

Example 14.i Responder’s predetermined timelines were not analyzed or identified.

The PD: The licensee failed to analyze and identify site-specific conditions,

including target sets, that may affect the specific measures needed to

implement the requirements of 10 CFR 73.55 and account for these

conditions in the design of the physical protection program as required by

10 CFR 73.55(b)(4). 10 CFR 73.55(k)(4) requires measures to provide

armed response personnel consisting of armed responders which may be

augmented with armed security officers to carry out armed response

duties within predetermined timelines specified by the site protective

strategy.

Minor if: Upon identification, the licensee was able to demonstrate that the timeline

for the responder to arrive at their defense position would not have

exceeded the adversary timeline and provided adequate time to intercede

(as determined by the training timelines to open port, ready weapon, and

engage).

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the responder’s timeline could exceed the potential

adversary time or did not provide enough time to intercede.

Example 14.j The tactical weapons course of fire did not include all the elements

required by the Commission-approved training and qualification plan. For

example, the licensee did not require tactical reloading while conducting

specific maneuvers, and this was not included in the handgun or rifle

course of fire.

The PD: The licensee failed to conduct weapons training and qualification in

accordance with 10 CFR Part 73, Appendix B, requirements; the

licensee’s training and qualification plan; and associated implementing

procedures.

Minor if: The elements are contained in another course of fire used for qualification

and officers are trained at the same periodicity and proficiency standards

as the tactical weapons training course of fire.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, security personnel are not trained on all the elements

required by the Commission approved training and qualification plan.

Example 14.k Vehicle left unattended/unsecured inside the protected area (PA).

The PD: The licensee failed to exercise control over all vehicles inside the PA to

ensure that they are used only by authorized persons and for authorized

purposes as required by 10 CFR 73.55(g)(3)(i).

Minor if: The vehicle could not reasonably be assumed to have the capability and

opportunity to damage target set or vital equipment.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the vehicle was a large vehicle (i.e., larger than a standard

passenger car or truck that consumers might purchase at a dealership)

and could reasonably be assumed to have the capability and opportunity

to damage target set equipment.

Example 14.l Tours or observations associated with unattended openings or

compensatory measures are not being conducted at the frequency

required by the security plan, procedures, or analyses.

The PD: The licensee failed to conduct tours or observations at the frequency

required by their security plan.

Minor if: The frequency at which tours or observations were being conducted was

sufficient to prevent an adversary from exploiting a vulnerability even

though the frequency did not meet the requirement imposed by the site’s

security plan or procedures.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the frequency at which tours or observations were being

conducted was insufficient to prevent an adversary from exploiting a

vulnerability.

Example 14.m Training program did not simulate the specific conditions of the protective

strategy.

The PD: The training program fails to simulate, as closely as practicable, the

specific conditions under which the individual shall be required to perform

assigned duties and responsibilities as required by 10 CFR 73, Appendix

B,Section VI.A.5.

Minor if: The failure does not reasonably impact the implementation of the

protective strategy, or the training inadequacy has existed for less than 6

months.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the failure reasonably impacts the implementation of the

protective strategy and has existed for more than 6 months.

Example 14.n Vital area (VA) access was not limited to only those who need access.

The PD: The licensee fails to limit access to vital areas to only those individuals

who have a continued need for access to specific vital areas as

documented on their VA access list required by 10 CFR 73.56(j).

Minor if: The issue was an isolated human error that did not adversely affect the

security cornerstone objective.

MTM if: The PD adversely affected the security cornerstone objective.

Specifically, the failure provided VA access to populations of people that

did not actually need it or failed to distinguish access to specific vital

areas.

Example 14.o A document labeled as safeguards information was discovered in an

unsecured location.

The PD: The licensee failed to secure unattended safeguards information in a

locked security storage container in accordance with the requirements.

Minor if: A subsequent review of the document determined that it did not contain

safeguards information or that the information contained in the document

no longer needed to be protected as safeguards. Specifically, the

information was determined to be generic in nature or no longer reflects

the current configuration of the licensee’s physical protection program.

MTM if: The PD adversely affected the security cornerstone objective to provide

assurance that the licensee’s security program used a defense-in-depth

approach and could protect against the design basis threat of radiological

sabotage from external and internal threats. Specifically, a subsequent

review of the document confirmed the presence of current and accurate

safeguards information and the licensee’s failure to properly secure that

safeguards information increased the potential that physical protection

program information associated with the design basis threat common to

all power reactor licensees or associated with site specific considerations

could be compromised.

END

Attachment 1: Revision History for IMC 0612 Appendix E

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training

Required and

Completion

Date

Comment Resolution and

Closed Feedback Forms

Accession Number (PreDecisional, Non-Public

Information)

N/A ML031610641

06/24/2003

CN 03-021

Initial issuance of Appendix E to IMC-0612 which

provided numerous new examples of minor

violations in Appendix E.

N/A N/A

N/A ML051400260

05/19/2005

CN 05-014

Appendix E was revised to add minor issue

examples pertaining to maintenance risk

assessments and risk management issues

resulting from baseline inspection procedure IP 71111.13, Maintenance Risk Assessments and

Emergent Work Evaluation. In addition, additional

clarifications have been made to the existing

maintenance rule minor issues examples.

N/A N/A

N/A ML052700276

09/30/2005

CN 05-028

Appendix E was revised to provide additional

examples of cross-cutting aspects and additional

examples of minor findings were added.

N/A N/A

N/A 02/10/2006 Revision history reviewed for the last four years. N/A N/A

N/A ML0607301310

6/22/06

CN 06-015

Appendix E was revised to remove discussion of

cross-cutting aspects of inspection findings. A new

appendix, Appendix F, was created to provide

examples of cross-cutting aspects of inspection

findings which reflected the work by the safety

culture working group.

Yes

07/01/2006

N/A

NA ML070720202

09/20/07

CN 07-029

Appendix E Section 4, Example k (fire loading) was

revised to provide more detail in aid of a minor

versus more-than-minor determination.

N/A ML071560246

N/A ML083040261

07/08/09

CN 09-017

Appendix E was revised to add Health Physics,

Thermal Power, Maintenance Rule, and Worker

Fatigue Examples.

N/A ML083040254

Issue Date: 10/26/23 Att1-2 0612 App E

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training

Required and

Completion

Date

Comment Resolution and

Closed Feedback Forms

Accession Number (PreDecisional, Non-Public

Information)

NA ML092190386

08/11/09

CN 09-020

Appendix E, Section 6, Example e: was revised to

correct a logic error in the “Minor because”

paragraph. The example is minor only if both the

activity is indistinguishable from background, and

the dose to an individual was less than 1% of the

occupational or public dose limit.

N/A N/A

N/A ML18093B550

10/01/18

CN 18-033

Appendix E, Section 10 was added to provide

minor and more than minor examples for Cyber

Security Violations

N/A ML18093B551

ML19247C385

12/23/19

CN 19-042

Appendix E went through a major revision to

address feedback forms, OIG 16-A-21

recommendation 2, and Browns Ferry Lessons

Learned Recommendation 13. The examples were

revised to mirror the language in the more-thanminor screening questions in IMC 0612 Appendix B

to illustrate when the examples in Appendix E were

more than minor.

New examples were added in the areas of physical

security, worker fatigue, service life, Part 37 and

external events.

ML19247C919

FBF 0612E-1379

ML19226A028

FBF 0612E-1431

ML19316A007

FBF 0612E-1470

ML19226A030

FBF 0612E-1473

ML19226A032

FBF 0612E-1546

ML19226A033

FBF 0612E-1582

ML19316A020

FBF 0612E-1613

ML19226A034

Issue Date: 10/26/23 Att1-3 0612 App E

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training

Required and

Completion

Date

Comment Resolution and

Closed Feedback Forms

Accession Number (PreDecisional, Non-Public

Information)

FBF 0612E-1615

ML19226A035

FBF 0612E-1644

ML19226A036

FBF 0612E-1687

ML19226A037

FBF 0612E-1695

ML19226A038

FBF 0612E-1705

ML19226A039

FBF 0612E-1784

ML19226A040

FBF 0612E-1789

ML19226A041

FBF 0612E-1913

ML19226A042

FBF 0612E-1931

ML19226A043

FBF 0612E-2036

ML19226A044

FBF 0612E-2037

ML19226A045

FBF 0612E-2139

ML19226A057

FBF 0612E-2140

ML19226A046

FBF 0612E-2150

ML19316A029

FBF 0612E-2195

ML19226A047

FBF 0612E-2213

ML19226A048

FBF 0612E-2252

ML19316A074

Issue Date: 10/26/23 Att1-4 0612 App E

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training

Required and

Completion

Date

Comment Resolution and

Closed Feedback Forms

Accession Number (PreDecisional, Non-Public

Information)

ML20274A210

12/10/20

CN 20-070

Incorporated recommendations from two feedback

forms. Removed the abc and xyz in the PDs from the

last revision. Removed the programmatic issue

reference in example 10.b. Revised example 13.a.

Added examples for POV, fire protection, service life

and security. Improved the consistency of the MTM if

statements.

ML20275A011

FBF 0612E-1526

ML19316A015

FBF 0612E-1723

ML20275A204

ML23214A343

10/26/23

CN 23-031

Updated section 11 minor examples for cybersecurity.

Example 11.a was changed to address a violation

relating to security control application because of

incorrect classification of a CDA. New minor examples

were added in the areas of baseline configurations,

ongoing monitoring and assessment, removal of

unnecessary services and programs, physical access

control, and vulnerability management. See

ML23227A094 for regional working group comment

resolution. Clarified note regarding example 5.c.

N/A