Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update
ML24240A353
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/27/2024
From: Frank E
DTE Electric Company
To:
Office of Nuclear Reactor Regulation, Document Control Desk
Shared Package
ML24240A352 List:
References
NRC-24-0049
Download: ML24240A353 (1)


Text

DTE Electric Company 6400 N. Dixie Highway Newport, MI 48166 10 CFR 50.55a August 27, 2024 NRC-24-0049 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Fermi 2 Power Plant NRC Docket No. 50-341 NRC License No. NPF-43

Subject:

Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update In accordance with the American Society of Mechanical Engineers (ASME) OM Code, Section ISTA ³General Requirements', 2012 Edition, attached for your information is a copy of the Fermi 2 IST Program for the Fourth 10-Year Interval. The Fourth 10-Year Interval IST Program Plan complies with the requirements of the ASME Section ISTA-3120 2012 Code Edition. The Fourth 10-Year Interval began on February 17, 2020, and concludes on February 16, 2030. This submittal is being made to document changes made to Part 5 (Valve Scope Table) and Part 11 (Valve Basis). All parts of the fourth 10-Year IST Program plan are included in this submittal for completeness.

No new commitments are being made in this submittal.

Should you have any questions or require additional information, please contact me at (734) 586-4772.

Sincerely, Eric Frank Manager - Nuclear Licensing

Enclosure:

IST Program Plan (Parts 1-12) cc: NRC Project Manager NRC Resident Office Regional Administrator, Region III

Enclosure to NRC-24-0049 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 IST Program Plan (Parts 1-12)