L-2002-136, June 2002 Monthly Operating Report for Turkey Point Units 3 & 4

From kanterella
(Redirected from L-2002-136)
Jump to navigation Jump to search
June 2002 Monthly Operating Report for Turkey Point Units 3 & 4
ML022120172
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/15/2002
From: Mcelwain J
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2002-136
Download: ML022120172 (3)


Text

JUL 1 5 2002 FPL L-2002-136 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - June 2002 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the June 2002 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours, JZohn P. McElwain Vice President Turkey Point Plant SM Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

aEi FPL Group company

DOCKET NO.: 50-250 UNIT: Turkey Point Unit 3 DATE: 7/3/2002 COMPLETED BY: Stavroula Mihalakea TELEPHONE: (305) 246-6454 Reporting Period June, 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720_u Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 720 4343 190122.8 No. of hours generator was on line (service hours) 720 4343 187791.5 Unit reserve shutdown hours 0 0 121.8 Net Electrical Energy (MWH) 509779 3091916 122235563 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other Summary Of Monthly Operatina Experience Unit 3 operated at essentially 100% for the month of June 2002.

DOCKET NO.: 50-251 UNIT: Turkey Point Unit 4 DATE: 7/3/2002 COMPLETED BY: Stavroula Mihalakea TELEPHONE: (305) 246-6454 Reporting Period June, 2002 Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net). 693 MnnthI Year-to-date I uumulai~ive I No. of hours reactor was critical 720 3976.2 186945.7 No. of hours generator was on line (service hours) 720 3967.5 182542.6 Unit reserve shutdown hours 0 0 577.2 Net Electrical Energy (MWH) 1 507086 2766611 119871622 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation 5 - Other (Explain)

E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other Summary Of Monthly Operating Experience Unit 4 operated at essentially 100% for the month of June 2002.

Text

JUL 1 5 2002 FPL L-2002-136 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - June 2002 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the June 2002 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours, JZohn P. McElwain Vice President Turkey Point Plant SM Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

aEi FPL Group company

DOCKET NO.: 50-250 UNIT: Turkey Point Unit 3 DATE: 7/3/2002 COMPLETED BY: Stavroula Mihalakea TELEPHONE: (305) 246-6454 Reporting Period June, 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720_u Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 720 4343 190122.8 No. of hours generator was on line (service hours) 720 4343 187791.5 Unit reserve shutdown hours 0 0 121.8 Net Electrical Energy (MWH) 509779 3091916 122235563 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other Summary Of Monthly Operatina Experience Unit 3 operated at essentially 100% for the month of June 2002.

DOCKET NO.: 50-251 UNIT: Turkey Point Unit 4 DATE: 7/3/2002 COMPLETED BY: Stavroula Mihalakea TELEPHONE: (305) 246-6454 Reporting Period June, 2002 Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net). 693 MnnthI Year-to-date I uumulai~ive I No. of hours reactor was critical 720 3976.2 186945.7 No. of hours generator was on line (service hours) 720 3967.5 182542.6 Unit reserve shutdown hours 0 0 577.2 Net Electrical Energy (MWH) 1 507086 2766611 119871622 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation 5 - Other (Explain)

E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other Summary Of Monthly Operating Experience Unit 4 operated at essentially 100% for the month of June 2002.