L-2003-302, November 2003 Monthly Operating Report for Turkey Point Units 3 and 4

From kanterella
Jump to navigation Jump to search
November 2003 Monthly Operating Report for Turkey Point Units 3 and 4
ML033560256
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 12/12/2003
From: Jones T
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2003-302
Download: ML033560256 (3)


Text

DEC 1 2 2003 FPL L-2003-302

.10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - November 2003 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the November 2003 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours Terry O. or1 Vice President Turkey Point Plant LDT Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

an FPL Group company

I -

DOCKET NO.: 50-250 UNIT: Turkey Point Unit 3 DATE: 11/02/2003 COMPLETED BY: Linda Tudor TELEPHONE: (305) 246-6408 Reporting Period November, 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 -______ --;;_______ -____- _;;___-_- _

Maximum Dependable Capacity (MWe-Net) 693  ;- _._____,________;

Month Year-to-date Cumulative No. of hours reactor was critical 7249.8 201789.2 No. of hours generator was on line (service hours) 720 7207.8 199416 Unit reserve shutdown hours 0 0 121.8 Net Electrical Energy (MWH) 518556 4961554 130320631 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/AN/A N/A NIA N/A N/A NIA (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G -Operational Error (Explain)

H -Other Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% power for the month of November 2003.

DOCKET NO.: 50-251 UNIT: Turkey Point Unit 4 DATE: 11/02/03 COMPLETED BY: Linda Tudor TELEPHONE: (305) 246-6408 Reporting Period November, 2003 Design Electrical Rating (MWe-Net) 720 .-  ; ._- -r -: a - I-.-__ _ _ ;

Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 642.1 7313.1 198675.8 No. of hours generator was on line (service hours) 618.2 7289.2 194234.4 Unit reserve shutdown hours 0 0 577.2 Net Electrical Energy (MWH) 421178 5018871 127977961 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2) 20030023 11/01/2003 S 101.8 C N/A RF21 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2- Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/LUcense Examination 5 - Other (Explain)

F- Administrative G - Operational Error (Explain)

H - Other Summarv Of Monthiv Overatina Experience The unit was placed on-line on November 5, 2003 and has operated at essentially 100% for the remainder of the month.

Text

DEC 1 2 2003 FPL L-2003-302

.10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - November 2003 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the November 2003 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours Terry O. or1 Vice President Turkey Point Plant LDT Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

an FPL Group company

I -

DOCKET NO.: 50-250 UNIT: Turkey Point Unit 3 DATE: 11/02/2003 COMPLETED BY: Linda Tudor TELEPHONE: (305) 246-6408 Reporting Period November, 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 -______ --;;_______ -____- _;;___-_- _

Maximum Dependable Capacity (MWe-Net) 693  ;- _._____,________;

Month Year-to-date Cumulative No. of hours reactor was critical 7249.8 201789.2 No. of hours generator was on line (service hours) 720 7207.8 199416 Unit reserve shutdown hours 0 0 121.8 Net Electrical Energy (MWH) 518556 4961554 130320631 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2)

N/AN/A N/A NIA N/A N/A NIA (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G -Operational Error (Explain)

H -Other Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% power for the month of November 2003.

DOCKET NO.: 50-251 UNIT: Turkey Point Unit 4 DATE: 11/02/03 COMPLETED BY: Linda Tudor TELEPHONE: (305) 246-6408 Reporting Period November, 2003 Design Electrical Rating (MWe-Net) 720 .-  ; ._- -r -: a - I-.-__ _ _ ;

Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 642.1 7313.1 198675.8 No. of hours generator was on line (service hours) 618.2 7289.2 194234.4 Unit reserve shutdown hours 0 0 577.2 Net Electrical Energy (MWH) 421178 5018871 127977961 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours) (1) Shutting S=Scheduled Down (2) 20030023 11/01/2003 S 101.8 C N/A RF21 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2- Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/LUcense Examination 5 - Other (Explain)

F- Administrative G - Operational Error (Explain)

H - Other Summarv Of Monthiv Overatina Experience The unit was placed on-line on November 5, 2003 and has operated at essentially 100% for the remainder of the month.