Advises That Amend to License Condition 14 for License NPF-21 Initiated by Working W/Nrr to Obtain SER on Fire Protection Program.Util Expects to Submit Final Response to NRC Question During Wk of 860630
ML20202G674
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/01/1986
From: Powers C
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO2-82-615, NUDOCS 8607160054
Download: ML20202G674 (3)


Text

,

.. $WWEIy WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968

  • 3000 George \\'ashington \\'ay
  • Richland, \\'ashingtorYN5355 ~3 pg y ,

%C:; y : , -

July 1, 1986 G02-86-615 Docket No. 50-397 Mr. J. B. Martin, Regional Administrator U.S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Dear Mr. Martin:

Subject:

NUCLEAR PLANT NO. 2 LICENSE NO. NPF-21, LICENSE CONDITION (14),

FIRE PROTECTION PROGRAM

References:

1) NRC Inspection 86-05 Enforcement Conference, April 15, 1986
2) SECY-85-306, " Staff Recommandations Regarding the Implementation of Appendix R to 10CFo.50", dated September 17, 1985
3) Letter, G02-85-310, GC Sorensen (SS) to EG Adensam (NRC), " Submittal of Advanced Copy of Appendix R -

Fire Protection Evaluation", dated April 4,1986

4) Letter, EG Adensam (NRC) to GC Sorensen (SS), "WNP-2 Fire Protection Program - Request for Additional Information", dated May 23, 1986 During the Enforcement Conference (Ref.1), the Supply System committed to submit a proposed amendment to the subject License Condition using the recommendations provided in Enclosure 6 to Reference 2 (see attached) as a model . The license amendment process has been initiated in that we are working with NRR Division of Licensing to obtain a Safety Evaluation Report (SER) on our WNP-2 Fire Protection Program (Ref. 3). The earliest a SER can be issued appears to be September 1986. Since the SER is a prerequisite for final submittal of the license amendment, the target submittal date discussed at the Enforcement Conference in April is unattainable.

The Supply System submitted their initial response (Ref. 3), subsequent to which the Staff requested additional information (Ref. 4). The additional information was submitted in draft form with a formal meeting having been held June 11, 1986, to allow the Supply System and NRR Staff to discuss the information contained in our submittal. The Supply System hopes to be able to incorporate the Staff's comments and to submit a final response to their questions the week of June 30, 1986. If additional questions are asked by the Staff, however, this could impact our ability to submit the final response by the above schedule, 8607160054 860701 g lI gN PDR ADOCK 05000397 p PDR 4 y I~

Mr. J. B. Martin Page Two July 1, 1986 LICENSE CONDITION (14), FIRE PROTECTION PROGRAM The Staff expects to take at least four (4) weeks from their receipt of our final response to prepare their SER on this matter. A meeting between NRR and the Supply System to review our total submittal has tentatively been scheduled for mid-July.

Since our submittal is tied to the Staff's final SER, we will plan to submit the subject license amendment within 30 days of our receipt of the Staff's SER. In the meantime, we will keep you informally advised as the review progresses.

Very truly yours, k  %:4-C. M. Powers (927M)

WNP-2 Plant Manager CMP:1p Attachment cc: JO Bradfute - NRC RT Dodds - NRC Site RC Barr - NRC Site C-_______-__________-_-___________

! ATTACHMENT

\

[

ENCLOSURE 6 FIRE PROTECTION LICENSE CONDITION

1. The licensee shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report for the facility. (or as described in-submittals dated--------) and asapprovedintheSERdated--------(andSupplementsdated--------) subject to provisions 2 and 3 below.
2. The licensee may make no change to the approved fire protection program which would significantly decrease the level of fire protection in the plant without prior approval of the Ccanission. To make such a change the licensee must submit an application for license amendment pursuant to 10 CFR 50.90,
3. The licensee may make changes to features of the approved fire pro-tection program which do not significantly decrease the level c? fire protection without prior Comission approval provided (a) such changes do not otherwise involve a change in a ifrcense condition or technical specification or result in an unreviewed safety question (see 10 CFR 50.59), and (b) such changes do not result in failure to complete the fire protection program approved by the Cemission prior to license issu-ance. The licensee shall maintain, in an auditable form, a current record of all such changes, including an analysis of the effects of the change en the fire protection program, and shall make such records avail-able to NRC inspectors upon request. All changes to the approved program .

shall be reported annually to the Director of the Office of Nuclear Reactor Regulation, along with the FSAR revisions required by 10 CFR -

50.71(e). . .