Summary of Vogtle Readiness Group Public Meeting on December 2, 2021
ML21337A003
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/07/2021
From: Cayetano Santos
NRC/NRR/VPOB
To: Victor Hall
Office of Nuclear Reactor Regulation
Tanny Santos, VPO
References
Download: ML21337A003 (5)


Text

December 7, 2021 MEMORANDUM TO: Victor Hall, Chief Vogtle Project Office Office of Nuclear Reactor Regulation FROM: Cayetano Santos Jr., Senior Project Manager /RA/

Vogtle Project Office Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF VOGTLE READINESS GROUP PUBLIC MEETING ON DECEMBER 2, 2021 The U.S. Nuclear Regulatory Commission (NRC) staff held an information meeting with a question-and-answer session on December 2, 2021. The purpose of this meeting was to discuss Vogtle Readiness Group (VRG) activities that support construction at Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

The meeting notice can be found in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML21333A243. The meeting notice was also posted on the NRC public website. Enclosures 1 and 2 are the meeting agenda and attendance list for the meeting, respectively. The documents referenced during the discussion can be found at the ADAMS Accession No. given below:

Vogtle Readiness Group Presentation ML21333A217 CONTACT: C. Santos, NRR/VPO (301) 415-7270

V. Hall Meeting Summary:

On December 2, 2021, NRC staff held an information meeting with a question-and-answer session to discuss VRG activities to support construction at VEGP, Units 3 and 4. The NRC staff described the licensing actions; inspection activities; and inspections, tests, analyses, and acceptance criteria (ITAAC) closure reviews associated with VEGP, Units 3 and 4. The NRC staff also discussed two white findings associated with cable separation issues (ADAMS Accession No. ML21312A412) and the transition of VEGP, Unit 3 from the construction reactor oversight process to the reactor oversight process. The NRC staffs presentation can be found at ADAMS Accession No. ML21333A217. There were no comments or questions from the public.

Docket No.: 52-025 52-026

Enclosures:

As stated cc w/encls: Listserv

ML21337A003 *via e-mail NRR-106 OFFICE PM: NRR/VPO LA: NRR/VPO BC: RII/DCO/CIB2 BC: NRR/VPO NAME CSantos RButler BDavis VHall DATE 12/2/2021 12/06/2021 12/06/2021 12/07/2021 OFFICE BC:NRR/DRO/IRIB PM: NRR/VPO NAME THipschman CSantos DATE 12/07/2021 12/07/2021 AGENDA FOR PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION Thursday, December 2, 2021 Teleconference 3:00 p.m. - 4:00 p.m.

PURPOSE: To hold an open forum to discuss the Vogtle Readiness Groups activities to support Vogtle Electric Generating Plant (VEGP) Units 3 and 4.

Time Topic Led By Introductions and Opening 3:00 p.m. NRC Remarks Vogtle Readiness Group 3:05 p.m. - 3:30 p.m. NRC Presentation 3:30 p.m. - 4:00 p.m. Question-and-Answer Session NRC/Public 4:00 p.m. Adjourn NRC Enclosure 1

PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION Thursday, December 2, 2021 List of Attendees Name Organization Cayetano (Tanny) Santos Victor Hall Dave Gasperson Bradley Davis James Gaslevic Greg Bowman Omar Lopez-Santiago Michael Spencer Shani Seaton Garry Armstrong Marissa Bailey Nicole Coovert US Nuclear Regulatory Commission Philip McKenna William (Billy) Gleaves Michael Webb Christopher Regan Thomas Hipschman Valerie Gray Robert Mathis Andrea Johnson Robert Krsek Caty Nolan Shakur Walker Steven Leighty Stephanie Agee Southern Nuclear Operating Company Michael Yox Jana Bergman Members of the Public Note: All participated via teleconference.

Enclosure 2