Public Meeting Summary - 2023 Annual Assessment Meeting Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 Docket Nos.. 50-424, 50-424,52-025, and 52-026 Meeting Number 20240471
ML24122C620
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/01/2024
From: Alejandro Alen
Division Reactor Projects II
To: Alan Blamey, Bradley Davis
Division Reactor Projects II
References
20240471
Download: ML24122C620 (4)


Text

MEMORANDUM TO: Alan J. Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects Bradley Davis, Chief Inspection Branch 2 Division of Construction Oversight FROM: Alejandro Alen Arias, Senior Project Engineer Reactor Projects Branch 2 Division of Reactor Projects

SUBJECT:

PUBLIC MEETING

SUMMARY

- 2023 ANNUAL ASSESSMENT MEETING VOGTLE ELECTRIC GENERATING PLANT, UNITS 1, 2, 3, AND 4 DOCKET NOS. 50-424, 50-424,52-025, AND 52-026 MEETING NUMBER 20240471 On April 30, 2024, the Nuclear Regulatory Commission (NRC) conducted a virtual Information Meeting (slide presentation) with Question-and-Answer Session to provide the public with information on the annual performance assessment of the Vogtle Electric Generating Plant, Units 1, 2, 3, and 4, for the period of January 1, 2023 to December 31, 2023.

To allow the NRC to effectively engage and maximize public stakeholders the meeting was held remotely through the Microsoft Teams application. Additionally, a telephone bridge line was available. The following documents related to the meeting are available in ADAMS: Meeting Notice (ML24095A022), Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 (ML24047A129) and Units 3 and 4 (ML24053A356), and the Annual Assessment Meeting Presentation Slides (ML24120A220).

The meeting was conducted from 6:00 PM to 6:30 PM eastern time. There were 18 attendees. In summary, the attendees consisted of representatives from the NRC (11),

Southern Nuclear Company (4), and members of the public (3) that did not indicate affiliation with any organization. At the conclusion of the discussion, there was an opportunity for the public to provide comments and ask questions to the NRC staff. There was minimal interaction with the public, which was consistent with the typical annual assessment meetings conducted both in-person (near the station) and virtual settings.

CONTACT: Alejandro Alen Arias, RII/DRP 404-997-4728May 1, 2024 Signed by Alen, Alejandro on 05/01/24

A. Blamey & B. Davis 2

The meeting was listed in the Public Meeting Feedback System (PMFS) under Meeting Code (20240471) and as of the date of this memo, no feedback responses were submitted.

Docket No.: 50-424, 50-424,52-025, and 52-026 License No.: NPF-68, NPF-81, NPF-91, and NPF-92

Enclosure:

List of Participants.

cc w/ encl: Distribution via LISTSERV

ML24122C620 X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DRP

NAME A. Alen DATE 5/1/2024

List of Participants 2023 Annual Assessment Meeting For Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 April, 30, 2024 Name Organization Alan Blamey NRC Alejandro Alen Arias NRC Bill Truss NRC Bradley Davis NRC Brian Griman NRC Christian Scott NRC Dave Gasperson NRC Jason Parent NRC Joylynn Quinones NRC Nicole Coovert NRC Thomas Morrissey NRC Kourosh Moayyed-Mohseni SNC Michael W. McCracken SNC Steven Leighty SNC William Garrett SNC Four (3) Public Members Affiliation not Identified (via Microsoft Teams)

Enclosure