MONTHYEARML24025A1372024-01-31031 January 2024 Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23313A0952023-11-16016 November 2023 Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML23275A0882023-10-12012 October 2023 Summary of Meeting with Southern Nuclear Operating Company ML23272A1822023-10-11011 October 2023 Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML23121A1692023-05-12012 May 2023 Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves ML23115A3282023-05-10010 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML23090A1422023-04-0303 April 2023 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML23065A0732023-03-17017 March 2023 March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 ML23055A0902023-03-14014 March 2023 February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company ML23048A0682023-03-0101 March 2023 Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23037A0032023-02-0606 February 2023 Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company ML23012A0512023-01-17017 January 2023 January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company ML22336A0812022-12-0505 December 2022 Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22335A4922022-12-0202 December 2022 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22319A0132022-11-30030 November 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on November 10, 2022 ML22322A1672022-11-28028 November 2022 Summary of 11/15/2022 Public Meeting on Lessons Learned ML22271A0182022-10-0404 October 2022 Summary of Public Meeting with SNC on Lessons Learned Final ML22257A2362022-09-19019 September 2022 Summary of September 13, 2022, Partially Open and Partially Closed Pre-Submittal Meeting Held with SNC, Regarding a Proposed OLM License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22243A0302022-09-0909 September 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022 ML22145A6052022-06-0202 June 2022 Summary of May 24, 2022, Public Meeting with SNC, Regarding a Proposed Alternative Request for Performance-Based Leakage Test Frequencies for the Refueling Water Tank Suction Check Valves for Vogtle, Units 1 & 2 ML22145A4492022-05-27027 May 2022 Summary of May 23, 2022, Public Meeting with SNC, Regarding a Proposed License Amendment Request to Change Technical Specification 3.8.1 and Implement TSTF-163 for Vogtle Electric Generating Plant, Units 1 and 2 ML22131A3422022-05-18018 May 2022 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Requests to Implement Alternate Source Term, TSTF-51, TSTF-471, and TSTF-490 for Vogtle, Units 1 & 2 (EPID No. L-2022-LRM-0033 ML22132A0102022-05-17017 May 2022 Meeting of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding Proposed Accident Tolerant Fuel License Amendment Request and Exceptions for Vogtle Electric Generating Plant, Units 1 and 2 ML22123A0652022-05-0202 May 2022 Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 ML22098A1292022-04-26026 April 2022 Summary of March 31, 2022 Public Meeting with Southern Nuclear Operating Company ML22095A2292022-04-11011 April 2022 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML22077A5432022-04-0404 April 2022 Summary of Meeting with Southern Nuclear Operating Co ML22028A0462022-02-0101 February 2022 MTS - Meeting Summary - Pre-Submittal Meeting on January 27, 2022 - Vogtle ATF LAR and Exemption ML21337A0032021-12-0707 December 2021 Summary of Vogtle Readiness Group Public Meeting on December 2, 2021 ML21322A1502021-12-0202 December 2021 Summary of November 10, 2021 Public Meeting with Southern Nuclear Operating Company ML21316A0692021-11-22022 November 2021 November 4, 2021 Summary of Public Meeting with Southern Nuclear Operating Company ML21313A1172021-11-18018 November 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Technical Specification 5.5.16 for Joseph M. Farley Nuclear Plant ML21238A1622021-09-10010 September 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Main Steam Isolation Valves for Vogtle Electric Generating Plant ML21225A5532021-08-31031 August 2021 August 13,2021, Public Meeting Summary with Southern Nuclear Operating Regarding Proposed LAR to Revise Technical Specifications Related to Reactor Trip System & Engineered Safety Feature Actuation System Instrumentation for Vogtle 1&2 (L-2 ML21230A0102021-08-24024 August 2021 Summary of Public Meeting with Southern Nuclear Operating Company on August 12, 2021 ML21154A2772021-07-20020 July 2021 Summary of a Public Meeting with Southern Nuclear Operating Company on May 27, 2021 ML21194A0402021-07-20020 July 2021 Summary of June 24, 2021 Public Meeting with SNC ML21190A0622021-07-16016 July 2021 Summary of July 8 2021 Public Meeting to Discuss Late-Filed Allegation Process for Vogtle Electric Generating Plant Units 3 and 4 2024-01-31
[Table view] |
Text
September 9, 2022 LICENSEE: SOUTHERN NUCLEAR OPERATING COMPANY FACILITY: VOGTLE ELECTRIC GENERATING PLANT, UNIT 4
SUBJECT:
SUMMARY
OF AUGUST 25, 2022, MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY On August 25, 2022, the U.S. Nuclear Regulatory Commission (NRC) held a virtual public meeting with representatives of Southern Nuclear Operating Company (SNC). The purpose of the meeting was to have a pre-submittal discussion about a potential license amendment to delete and consolidate several electrical inspections, tests, analyses, and acceptance criteria (ITAAC) in the Vogtle Electric Generating Plant (VEGP) Unit 4 combined license (COL)
(Agencywide Documents Access and Management System (ADAMS) Accession No. ML14100A135). The potential license amendment was provided to the NRC in the form of a draft license amendment request (LAR) and was based, in part, on lessons learned from the ITAAC process for VEGP Unit 3. In the draft LAR, SNC proposed two categories of changes to the VEGP Unit 4 COL, which would require an amendment and exemption: first, a deletion of certain redundant ITAAC, and second, a consolidation of certain electrical cable, raceway color coding, and separation ITAAC to improve efficiency of ITAAC completion. The draft LAR and presentation are available at ML22231A349. The meeting notice and agenda are available at ML22231B120. An attendee list is enclosed.
In its draft LAR, SNC proposed the deletion of 14 assigned division ITAAC that were said to be redundant with other Unit 4 ITAAC. The justification for this proposed deletion is that the inspection, test, and analysis (ITA) for these ITAAC are very similar, and the scope of these individual ITAAC fall within the scope of existing ITAAC for Class 1E cables for containment, and radiologically controlled and non-radiologically controlled areas of the auxiliary building, respectively.
The Unit 4 assigned division ITAAC proposed for deletion in the proposed LAR would be as follows:
- 1. ITAAC 2.1.02.07b (Index No. 26), Reactor Coolant System (RCS)
- 2. ITAAC 2.1.03.09b (Index No. 83), Reactor System (RXS)
- 3. ITAAC 2.2.01.06b (Index No. 103), Containment System (CNS)
- 4. ITAAC 2.2.03.07b (Index No. 172), Passive Core Cooling System (PXS)
- 5. ITAAC 2.2.04.07b (Index No. 233), Steam Generator System (SGS)
- 6. ITAAC 2.2.05.06a (Index No. 263), Main Control Room Emergency Habitability System (VES)
- 7. ITAAC 2.3.02.06b (Index No. 296), Chemical and Volume Control System (CVS)
- 8. ITAAC 2.3.06.07b (Index No. 368), Normal Residual Heat Removal System (RNS)
- 9. ITAAC 2.3.07.06a (Index No. 399), Spent Fuel Pool Cooling System (SFS)
- 10. ITAAC 2.3.10.11a (Index No. 878), Liquid Radwaste System (WLS)
- 11. ITAAC 2.3.13.06b (Index No. 467), Primary Sampling System (PSS)
- 12. ITAAC 2.5.02.05a (Index No. 527), Protection and Safety Monitoring System (PMS)
- 13. ITAAC 2.6.01.03a (Index No. 582), Main ac Power System (ECS)
- 14. ITAAC 2.7.01.06a (Index No. 687), Nuclear Island Nonradioactive Ventilation System (VBS)
The NRC staff commented that documentation explaining how the ITAAC proposed for deletion are redundant to the remaining ITAAC has not been identified in the proposed LAR. In addition, the justification proposed by SNC is partly based on similarities in uncompleted ITAAC notifications and associated work packages. The staff stated that this would typically be an insufficient basis for justifying the proposed changes. A readily reviewable LAR proposing deletions to ITAAC based on redundancy would specify the redundant ITAAC, explain why these ITAAC contain the same requirements or when completed accomplish the same purposes as the ITAAC proposed to be deleted, and provide adequate explanation or analysis supporting that statement.
The presentation proceeded to the second category of changes proposed in the draft LAR, which is the proposal to consolidate 18 electrical cable, raceway color coding, and separation ITAAC into the three Containment, Auxiliary Building Non-Radiation, and Auxiliary Building Radiation, ITAAC for VEGP Unit 4 as show below:
Containment ITAAC - Unconsolidated Containment ITAAC - Consolidated ITAAC 3.3.00.07aa (Index No. 789)
ITAAC 3.3.00.07ba (Index No. 792)
ITAAC 3.3.00.07d.ii.a (Index No. 800)
ITAAC 3.3.00.07d.ii.a (Index No. 800)
ITAAC 3.3.00.07d.iii.a (Index No. 803)
ITAAC 3.3.00.07d.iv.a (Index No. 806)
ITAAC 3.3.00.07d.v.a (Index No. 809)
Auxiliary Building Non-Radiation ITAAC - Auxiliary Building Non-Radiation ITAAC -
Unconsolidated Consolidated ITAAC 3.3.00.07ab (Index No. 790)
ITAAC 3.3.00.07bb (Index No. 793)
ITAAC 3.3.00.07d.ii.b (Index No. 801)
ITAAC 3.3.00.07d.ii.b (Index No. 801)
ITAAC 3.3.00.07d.iii.b (Index No. 804)
ITAAC 3.3.00.07d.iv.b (Index No. 807)
ITAAC 3.3.00.07d.v.b (Index No. 810)
Auxiliary Building Radiation ITAAC - Auxiliary Building Radiation ITAAC -
Unconsolidated Consolidated ITAAC 3.3.00.07ac (Index No. 791)
ITAAC 3.3.00.07bc (Index No. 794)
ITAAC 3.3.00.07d.ii.c (Index No. 802)
ITAAC 3.3.00.07d.ii.c (Index No. 802)
ITAAC 3.3.00.07d.iii.c (Index No. 805)
ITAAC 3.3.00.07d.iv.c (Index No. 808)
ITAAC 3.3.00.07d.v.c (Index No. 811)
The staff summarized its understanding of the consolidation changes as follows: for each case of the consolidation, the unconsolidated design commitments; inspections, tests, and analyses (ITAs); and acceptance criteria would be moved in their entirety with no changes to the consolidated ITAAC. SNC confirmed this understanding was correct. The draft LAR does note, however, that for ITAAC Index No. 805, there is one apparent error in the acceptance criterion number ii.c). The proposed revision to consolidated ITAAC Index No. 802 corrects this number to iii.c). SNC estimated the current submittal date would be August 31, 2022, with the current proposed approval date of January 7, 2023, but the submittal date might change due to feedback received at this meeting.
Following completion of the presentation by SNC and comments by NRC staff, members of the public were asked for comment. The members of the public who were in attendance offered no comments or questions. The staff did not receive any verbal meeting feedback or completed Public Meeting Feedback forms.
Please direct any inquiries to me at 301-415-7270 or Cayetano.Santos@nrc.gov.
Sincerely, Signed by Santos, Cayetano on 09/09/22 Cayetano Santos Jr., Senior Project Manager Vogtle Project Office Office of Nuclear Reactor Regulation Docket No.52-026
Enclosure:
As stated cc: Listserv
LIST OF ATTENDEES AUGUST 25, 2022, PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY Name Organization Cayetano (Tanny) Santos William (Billy) Gleaves Christopher Welch Michael Webb Victor Hall Phil OBryan James Gaslevic Garry Armstrong NRC/Office of Nuclear Reactor Regulation Tom Fredette Bill Roggenbrodt Sheila Ray Thomas Scarbrough Stewart Bailey Morton Wendell Mike Waters NRC/Office of Nuclear Security and Incident Ken Mott
Response
George Khouri Bradley Davis Robert Mathis NRC/Region II Omar Lopez-Santiago Nicole Coovert Julie Ezell NRC/Office of General Counsel Amy Chamberlain Kelli Roberts Neil Haggarty Eddie Grant Southern Nuclear Operating Company Peter LeJeune Keith Dorsey Keith Drudy Ray Fu Kevin Little Members of the Public Wade McKenzie Michael Hiller Enclosure
ML22243A030 OFFICE NRR/VPO/VPOB NRR/VPO/VPOB NRR/DEX/ELTB NRR/DEX/EEOB NAME WGleaves WG RButler RB WMorton WM MWaters MW DATE Aug 31, 2022 Aug 31, 2022 Sep 8, 2022 Sep 8, 2022 OFFICE R-II/DRP/RPB4 NRR/VPO/VPOB NRR/VPO/VPOB SBailey NAME VHall VH CSantos CS YLi for YL DATE Sep 9, 2022 Sep 9, 2022 Sep 9, 2022