ML24025A137 | 31 January 2024 | Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 | |
ML24019A193 | 30 January 2024 | Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 | |
ML23356A028 | 27 December 2023 | December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam | |
ML23311A130 | 17 November 2023 | Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 | Exemption Request |
ML23313A095 | 16 November 2023 | Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 | Ultimate heat sink Mission time Chernobyl Power Uprate |
ML23303A203 | 1 November 2023 | October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 | |
ML23275A088 | 12 October 2023 | Summary of Meeting with Southern Nuclear Operating Company | Exemption Request |
ML23272A182 | 11 October 2023 | Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 | |
ML23230A021 | 30 August 2023 | LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting | Enforcement Discretion Probabilistic Risk Assessment |
ML23187A574 | 22 August 2023 | Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company | Large early release frequency |
ML23146A154 | 5 June 2023 | Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company | |
ML23132A041 | 18 May 2023 | Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company | |
ML23121A169 | 12 May 2023 | Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves | |
ML23115A328 | 10 May 2023 | Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 | |
ML23115A066 | 1 May 2023 | Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 | |
IR 05000424/2004025 | 28 April 2023 | Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 | |
ML23090A142 | 3 April 2023 | Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections | |
ML23065A073 | 17 March 2023 | March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 | |
ML23055A090 | 14 March 2023 | February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company | Exemption Request |
ML23048A068 | 1 March 2023 | Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 | |
ML23037A003 | 6 February 2023 | Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company | |
ML23012A051 | 17 January 2023 | January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment | |
ML22349A214 | 3 January 2023 | Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company | Exemption Request |
ML22336A081 | 5 December 2022 | Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 | |
ML22335A492 | 2 December 2022 | Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 | |
ML22319A013 | 30 November 2022 | Summary of a Public Meeting with Southern Nuclear Operating Company on November 10, 2022 | Probabilistic Risk Assessment |
ML22322A167 | 28 November 2022 | Summary of 11/15/2022 Public Meeting on Lessons Learned | Enforcement Discretion Significance Determination Process Low Safety Significance Issue Resolution |
ML22271A018 | 4 October 2022 | Summary of Public Meeting with SNC on Lessons Learned Final | |
ML22257A236 | 19 September 2022 | Summary of September 13, 2022, Partially Open and Partially Closed Pre-Submittal Meeting Held with SNC, Regarding a Proposed OLM License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 | |
ML22243A030 | 9 September 2022 | Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022 | |
ML22145A605 | 2 June 2022 | Summary of May 24, 2022, Public Meeting with SNC, Regarding a Proposed Alternative Request for Performance-Based Leakage Test Frequencies for the Refueling Water Tank Suction Check Valves for Vogtle, Units 1 & 2 | |
ML22145A449 | 27 May 2022 | Summary of May 23, 2022, Public Meeting with SNC, Regarding a Proposed License Amendment Request to Change Technical Specification 3.8.1 and Implement TSTF-163 for Vogtle Electric Generating Plant, Units 1 and 2 | |
ML22131A342 | 18 May 2022 | Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Requests to Implement Alternate Source Term, TSTF-51, TSTF-471, and TSTF-490 for Vogtle, Units 1 & 2 (EPID No. L-2022-LRM-0033 | |
ML22132A010 | 17 May 2022 | Meeting of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding Proposed Accident Tolerant Fuel License Amendment Request and Exceptions for Vogtle Electric Generating Plant, Units 1 and 2 | Probabilistic Risk Assessment Surveillance Frequency Control Program Severe Accident Management Guideline Exemption Request |
ML22123A065 | 2 May 2022 | Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 | Coronavirus |
ML22098A129 | 26 April 2022 | Summary of March 31, 2022 Public Meeting with Southern Nuclear Operating Company | Exemption Request |
ML22095A229 | 11 April 2022 | Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections | |
ML22077A543 | 4 April 2022 | Summary of Meeting with Southern Nuclear Operating Co | Incorporated by reference |
ML22028A046 | 1 February 2022 | MTS - Meeting Summary - Pre-Submittal Meeting on January 27, 2022 - Vogtle ATF LAR and Exemption | Probabilistic Risk Assessment Exemption Request |
ML21337A003 | 7 December 2021 | Summary of Vogtle Readiness Group Public Meeting on December 2, 2021 | |
ML21322A150 | 2 December 2021 | Summary of November 10, 2021 Public Meeting with Southern Nuclear Operating Company | Fitness for Duty Exemption Request |
ML21316A069 | 22 November 2021 | November 4, 2021 Summary of Public Meeting with Southern Nuclear Operating Company | Fitness for Duty Exemption Request |
ML21313A117 | 18 November 2021 | Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Technical Specification 5.5.16 for Joseph M. Farley Nuclear Plant | |
ML21238A162 | 10 September 2021 | Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Main Steam Isolation Valves for Vogtle Electric Generating Plant | Internal Flooding Probabilistic Risk Assessment Large early release frequency |
ML21225A553 | 31 August 2021 | August 13,2021, Public Meeting Summary with Southern Nuclear Operating Regarding Proposed LAR to Revise Technical Specifications Related to Reactor Trip System & Engineered Safety Feature Actuation System Instrumentation for Vogtle 1&2 (L-2 | Anticipated operational occurrence |
ML21230A010 | 24 August 2021 | Summary of Public Meeting with Southern Nuclear Operating Company on August 12, 2021 | |
ML21154A277 | 20 July 2021 | Summary of a Public Meeting with Southern Nuclear Operating Company on May 27, 2021 | |
ML21194A040 | 20 July 2021 | Summary of June 24, 2021 Public Meeting with SNC | Exemption Request |
ML21190A062 | 16 July 2021 | Summary of July 8 2021 Public Meeting to Discuss Late-Filed Allegation Process for Vogtle Electric Generating Plant Units 3 and 4 |