MONTHYEARML24185A1262024-07-10010 July 2024 Summary of Meeting with Florida Power and Light on License Amendment Requests Regarding the Spent Fuel Criticality Analysis in Support of Planned Transition to 24-Month Fuel Cycles for St. Lucie, Unit 2 ML24128A2102024-05-0707 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Regarding Saint Lucie ML23276A1852023-09-25025 September 2023 Subsequent License Renewal Draft EIS Public Meetings: Meeting Summary ML23221A3782023-08-16016 August 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23058A4262023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML23087A0692023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23108A2752023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23068A0712023-04-28028 April 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 (EPID L-2022-LLA-0105) - Nonproprietary ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23081A5022023-03-28028 March 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23048A0492023-03-0303 March 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22350A7082023-01-17017 January 2023 Summary of November 21, 2022, Presubmittal Meeting with Florida Power and Light on St. Lucie License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML22349A0012023-01-0505 January 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22276A2302022-10-0606 October 2022 Summary of September 13, 2022, Public Meeting with FPL Concerning Supplemental Information Needed for Acceptance of License Amendment Request to Replace Instrumentation with Digital Systems on Turkey Point, Units 3 and 4 ML22263A0122022-09-27027 September 2022 Summary of August 29, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests (EPID Nos. L-2021-LLI-0000 and L 2021 Lli 0002) ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22238A2762022-08-29029 August 2022 Summary of August 17, 2022, Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Extend the Completion Time for an Inoperable Reactor Trip Breaker ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22228A2352022-08-23023 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22228A2032022-08-22022 August 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22195A1752022-07-27027 July 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22186A0812022-07-15015 July 2022 Summary of June 22, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Fire Protection Program Changes ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22160A3792022-06-30030 June 2022 Summary of May 24, 2022, Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22054A0082022-03-0303 March 2022 Summary of February 17, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Intake Cooling Water Discharge Piping Proposed Alternative ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML22020A4052022-01-24024 January 2022 Summary of January 14, 2022, Teleconference with Florida Power & Light Co. Regarding Verbal Authorization of Request for Alternative to the Requirements of ASME Code for Examination of Closure Head CEDM Housing 27 Canopy Seal Weld ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21337A1962021-12-16016 December 2021 Public Scoping Meeting Summary for the Environmental Review of the Subsequent License Renewal Application for St. Lucie Plant, Units 1 and 2 ML21327A1802021-12-0707 December 2021 Summary of August 25, 2021 Observation Public Meeting with FPL to Discuss Proposed Alternative Report for the Intake Cooling Water System ML21246A0212021-11-23023 November 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 ML21337A2062021-11-0303 November 2021 Environmental Scoping Meeting Related to the St. Lucie Plant, Units 1 and 2, Subsequent License Renewal Application ML21279A0432021-10-15015 October 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 ML21285A0412021-10-13013 October 2021 Summary of September 29, 2021 Meeting with the U.S. Fish and Wildlife Service Regarding Crocodile Monitoring at Turkey Point 2024-07-10
[Table view] |
Text
April 13, 2021 LICENSEE: NextEra/Florida Power and Light FACILITIES: Turkey Point Nuclear Generating, Unit Nos. 3 and 4 St. Lucie Plant, Unit Nos. 1 and 2
SUBJECT:
SUMMARY
OF THE MARCH 22, 2021, PRE-APPLICATION MEETING TO DISCUSS PLANNED LICENSE AMENDMENTS REGARDING CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS FOR THE TURKEY POINT NUCLEAR GENERATING, UNIT NOS. 3 AND 4, AND ST. LUCIE PLANT, UNIT NOS. 1 AND 2 FACILITIES (EPID L-2021-LRM-0032)
On March 22, 2021, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra/Florida Power and Light (FPL, the licensee) via virtual platform and teleconference. The purpose of the meeting was to discuss FPLs plans and schedule related to the submittal of license amendment requests (LARs) for the Turkey Point Nuclear Generating, Unit Nos. 3 and 4 (Turkey Point), and St. Lucie Plant, Unit Nos. 1 and 2 (St. Lucie) facilities. The licensee specified that the proposed LARs would convert the current Technical Specifications (TS) for each site to Improved Technical Specifications (ITS). The meeting notice and presentation material are available in the Agencywide Documents Access and Management System (ADAMS) under Accession Nos.
ML21078A441 and ML21076A615, respectively. A list of attendees is enclosed.
During the meeting, FPL provided an overview of the proposed LARs and the timetable for implementation phases at Turkey Point and St. Lucie facilities in order to ensure a common understanding of the ITS Conversion process. The NRC staff asked clarifying questions regarding the overall methodology and whether the licensees LARs would include items that could be considered beyond scope. The NRC staff asked the licensee to clearly communicate any changes to the intended timeframe with respect to submittal of the LARs to ensure proper allocation of resources and to foster an efficient review. No regulatory decisions were made, no egulatory positions were communicated, and no actions were identified as a result of this meeting. No members of the public were in attendance for the meeting, thus no Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-7410 or Natreon.Jordan@nrc.gov.
/RA/
Natreon Jordan, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, and 50-389
Enclosure:
List of Attendees cc: Listserv
LIST OF ATTENDEES FOR THE MARCH 22, 2021, PRE-APPLICATION MEETING TO DISCUSS PLANNED LICENSE AMENDMENTS REGARDING CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS FOR THE TURKEY POINT NUCLEAR GENERATING, UNIT NOS. 3 AND 4 AND ST. LUCIE PLANT, UNIT NOS. 1 AND 2 FACILITIES (EPID L-2021-LRM-0032)
ATTENDEE ORGANIZATION Eva Brown U.S. Nuclear Regulatory Commission (NRC)
Natreon (Nate) Jordan NRC Victor Cusumano NRC Tarico Sweat NRC Khadijah West NRC Matthew Hamm NRC Steve Smith NRC Ashley Clinton NRC Ravi Grover NRC Craig Harbuck NRC Michelle Honcharik NRC Andrea Russell NRC Caroline Tilton NRC Michael Waters NRC Joshua Wilson NRC Kate Suh NRC Undine Shoop NRC David Wrona NRC William Maher NextEra/FPL Jarrett Mack NextEra/FPL Ken Frehafer NextEra/FPL Steve Franzone NextEra/FPL Charles DeDeaux Excel Services Greg Ellis Excel Services Enclosure
ML21092A102 *via e-mail OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC* DORL/LPL2-2/PM NAME NJordan RButler DWrona NJordan DATE 03/31/2021 04/06/2021 04/13/2021 04/13/2021