ML22054A008

From kanterella
Jump to navigation Jump to search

Summary of February 17, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Intake Cooling Water Discharge Piping Proposed Alternative
ML22054A008
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/03/2022
From: Michael Mahoney
Plant Licensing Branch II
To: Moul D
Florida Power & Light Co
M Mahoney, NRR/DORL
References
EPID L-2021-LLR-0078
Download: ML22054A008 (3)


Text

March 3, 2022 LICENSEE: Florida Power and Light Company/NextEra FACILITY: Turkey Point Nuclear Generating Unit No. 3

SUBJECT:

SUMMARY

OF FEBRUARY 17, 2022, PARTIALLY CLOSED MEETING WITH FLORIDA POWER AND LIGHT TO DISCUSS INTAKE COOLING WATER DISCHARGE PIPING PLANNED ALTERNATIVE (EPID L-2021-LLR-0078)

On February 17, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a partially closed meeting with representatives of Florida Power and Light Company (FPL or the licensee) to discuss a planned alternative request for the Intake Cooling Water (ICW) discharge piping line for the Turkey Point Nuclear Generating Unit No. 3. The meeting notice and agenda for this meeting, dated February 4, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22035A022. A list of attendees is enclosed. No regulatory decisions were made at this meeting.

During licensees public presentation (ADAMS Accession No. ML22046A046), it described the leak discovery and leak location, pipe characteristics and flaw size, flaw evaluation, American Society of Mechanical Engineers (ASME) Code repair hardship, risks and planned alternative request, ASME Code Case N-513, Revision 4 (N-513-4), Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 extension, flaw size non-destructive examination (NDE) results and status update, and restoration hardware assembly proposed alternative.

Details of the restoration hardware assembly were discussed in detail during the closed portion of the meeting.

No members of public were in attendance.

Please direct any inquiries to me at 301-415-3867 or Michael.Mahoney@nrc.gov.

/RA/

Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-250

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES FEBRUARY 17, 2022, PUBLIC PORTION OF PARTIALLY CLOSED MEETING WITH FLORIDA POWER AND LIGHT REGARDING INTAKE COOLING WATER DISCHAGE PIPING PROPOSED ALTERNATIVE Name Organization Mike Mahoney U.S. Nuclear Regulatory Commission (NRC)

Matt Mitchell NRC John Honcharik NRC Stavroula Mihalakea Florida Power and Light Company (FPL)

Tom Ruiz FPL Robert Hess FPL Michael Koberling FPL Chuck Zyne FPL Chris Webb FPL Gary Priolo FPL Steve Catron FPL Swadesh Ramdeen FPL Donna Slivon FPL Ken Hudson PMC Engineering Solutions, Inc. (FPL Vendor)

Paul Manzon PMC Engineering Solutions, Inc. (FPL Vendor)

Stephen Parker Structural Integrity Associates, Inc. (third party reviewer)

Enclosure

ML22054A008 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NRR/DORL/LPL2-2/PM NAME MMahoney RButler DWrona MMahoney DATE 02/22/2022 02/25/2022 03/02/2022 03/03/2022