Letter Sequence Other |
|---|
EPID:L-2021-LLI-0000, TSTF-500, TSTF-505, TSTF-425, TSTF-360, TSTF-422, TSTF-500, TSTF-360, TSTF-500 (Approved, Closed) EPID:L-2021-LLI-0002, (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML21265A2842021-09-15015 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Request ML21265A2942021-09-15015 September 2021 Enclosure 2 - Volume 9 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.4 Reactor Coolant System (Rcs), Revision 0 Project stage: Request ML21265A2932021-09-15015 September 2021 Enclosure 2 - Volume 8 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.3 Instrumentation, Revision 0 Project stage: Request ML21265A2912021-09-15015 September 2021 Enclosure 2 - Volume 6 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.1 Reactivity Control Systems, Revision 0 Project stage: Request ML21265A2902021-09-15015 September 2021 Enclosure 2 - Volume 5 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.0 LCO and SR Applicability, Revision 0 Project stage: Request ML21265A2962021-09-15015 September 2021 Enclosure 2 - Volume 11 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.6 Containment Systems, Revision 0 Project stage: Request ML21265A2952021-09-15015 September 2021 Enclosure 2 - Volume 10 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.5 Emergency Core Cooling Systems (Eccs), Revision 0 Project stage: Request ML21265A2972021-09-15015 September 2021 Enclosure 2 - Volume 12 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.7 Plant Systems, Revision 0 Project stage: Request ML21265A2882021-09-15015 September 2021 Enclosure 2 - Volume 3 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Chapter 1.0 Use and Application, Revision 0 Project stage: Other ML21265A2852021-09-15015 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Request L-2021-159, Enclosures 1,3,4,5, and 6 - Contents of the St. Lucie Plant, Units 1 and 2, Improved Technical Specifications (ITS) Submittal2021-09-15015 September 2021 Enclosures 1,3,4,5, and 6 - Contents of the St. Lucie Plant, Units 1 and 2, Improved Technical Specifications (ITS) Submittal Project stage: Request ML21265A2982021-09-15015 September 2021 Enclosure 2 - Volume 13 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.8 Electrical Systems, Revision 0 Project stage: Request ML21265A3822021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 11, Revision 0, Section 3.6, Containment Systems Project stage: Request ML21265A3812021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 9, Revision 0, Section 3.5, Emergency Core Cooling Systems (ECCS) Project stage: Request ML21265A3852021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 14, Revision 0, Section 3.9, Refueling Operations Project stage: Request L-2021-158, Contents of the Turkey Point Nuclear Plant, Units 3 and 4 Improved Technical Specifications (Its) Submittal2021-09-22022 September 2021 Contents of the Turkey Point Nuclear Plant, Units 3 and 4 Improved Technical Specifications (Its) Submittal Project stage: Request ML21265A3842021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 13, Revision 0, Section 3.8, Electrical Power Systems Project stage: Request ML21265A3792021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 8, Revision 0, Section 3.3, Instrumentation Project stage: Request ML21265A3772021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 6, Revision 0, Section 3.1, Reactivity Control Systems Project stage: Request ML21265A3802021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 9, Revision 0, Section 3.4, Reactor Coolant Systems (RCS) Project stage: Request ML21265A3712021-09-22022 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1431 Revision 5 Project stage: Request ML21265A3702021-09-22022 September 2021, 23 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1431 Revision 5 Project stage: Request PMNS20211440, Notice of Forthcoming Meeting with Nextera/Florida Power and Light (FPL) Regarding the Conversion of Turkey Point Nuclear Generating Station, Units 3 and 4, and St. Lucie Plant, Units 1 and 2 to Improved Technical Specifications2021-11-0808 November 2021 Notice of Forthcoming Meeting with Nextera/Florida Power and Light (FPL) Regarding the Conversion of Turkey Point Nuclear Generating Station, Units 3 and 4, and St. Lucie Plant, Units 1 and 2 to Improved Technical Specifications Project stage: Request ML21350A4262021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Licensing Amendment Request Concerning Technical Specification Conversion to NUREG-1432, Revision 5 Project stage: Acceptance Review ML21342A2932021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Requested License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 Project stage: Acceptance Review L-2022-000, License Amendment Request for the Technical Specifications Conversion to NUREG- 1432 Revision 5 - Request for Supplemental Information (Rsi) Response2022-01-19019 January 2022 License Amendment Request for the Technical Specifications Conversion to NUREG- 1432 Revision 5 - Request for Supplemental Information (Rsi) Response Project stage: Supplement L-2022-010, License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 -Request for Supplemental Information Response2022-01-19019 January 2022 License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 -Request for Supplemental Information Response Project stage: Supplement NUREG-1431, Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 52022-02-0303 February 2022 Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 Project stage: Acceptance Review ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) Project stage: Meeting ML22054A1382022-02-16016 February 2022 February 24, 2022 ITS Public Meeting Material - Florida Power and Light Project stage: Meeting ML22054A1662022-02-23023 February 2022 ITS Public Meeting Material - NRC - Expectations for Licensees Responses to ITS Conversion LAR and RAIs Project stage: Meeting NUREG-1432, Acceptance of License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 52022-02-23023 February 2022 Acceptance of License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Acceptance Review PMNS20220112, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-02-23023 February 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting PMNS20220139, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-02-23023 February 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting PMNS20220236, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-03-11011 March 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220321, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-04-0505 April 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220427, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-04-27027 April 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22154A4992022-04-27027 April 2022, 7 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220454, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-05-17017 May 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22154A5182022-06-0909 June 2022 Summary of June 2, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request PMNS20220609, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-06-14014 June 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22228A1982022-06-28028 June 2022, 22 August 2022 Summary of July 14, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request PMNS20220683, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-06-28028 June 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22228A2432022-07-14014 July 2022, 23 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request 2022-03-21
[Table View] |
Text
August 24, 2022 LICENSEE:
Florida Power and Light/NextEra FACILITIES: St. Lucie Plant, Unit Nos. 1 and 2 Turkey Point Nuclear Generating, Unit Nos. 3 and 4
SUBJECT:
SUMMARY
OF AUGUST 11, 2022, MEETING WITH FLORIDA POWER AND LIGHT/NEXTERA ON ST. LUCIE AND TURKEY POINT IMPROVED TECHNICAL SPECIFICATION CONVERSION LICENSE AMENDMENT REQUEST (EPID NOS. L-2021-LLI-0000 AND L-2021-LLI-0002)
On August 11, 2022, a virtual observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power and Light/NextEra (FPL, the licensee). The purpose of the meeting was to discuss the license amendment request (LAR) for St. Lucie Plant (St. Lucie), Unit Nos. 1 and 2 to convert to improved standard technical specifications in accordance with NUREG-1432, Standard Technical Specifications -
Combustion Engineering Plants, Revision 5 (improved standard technical specifications (ISTS))
and Turkey Point Nuclear Generating, Unit Nos. 3 and 4 (Turkey Point) to convert to improved standard technical specifications in accordance with NUREG-1431. The meeting notice and agenda, dated August 2, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML22215A007. A list of attendees is enclosed.
There were no specific items related to the St. Lucie review discussed other than the NRC staff stated that in a few weeks they will start posting questions in the online St. Lucie Improved Technical Specification (ITS) Conversion Database Question and Answer Portal.
The following items for the Turkey Point review were discussed during the meeting:
o Open item questions related to setpoint methodologies. Specifically, the NRC technical staff is reviewing the responses these questions and staff relayed to the licensee that review of the move of the setpoints to a licensee-controlled Technical Requirements Manual (TRM) may impact the overall review schedule as additional review is required.
Staff will likely have multiple additional requests for additional information (RAIs) regarding the removal of setpoints from technical specifications to TRM.
The licensee stated that they will discuss internally whether they want to keep this proposed change (moving the setpoint to TRM).
o The licensee discussed numerous planned changes in an upcoming supplement which were not directly as a result of an NRC question, the items were the following:
ITS 5.6.3 - the licensee is planning to add a note before the list of analytical methods to distinguish which methods are applicable to which units operating cycle.
ITS 3.4.6 - the licensee is planning to replace DOC A02 with DOC M03 to address the new ITS 3.4.6 ACTION requirement for two loops inoperable.
ITS 3.7.10 - the licensee is planning for Insert 3 to add in MODES 1, 2, 3, or 4 to the 2nd part of new Condition J, this is an oversight from a response to another question from the NRC staff.
ITS 5.5.10 - the licensee is planning to move the specific American Society for Testing and Materials (ASTM) standards to the Bases of ITS 3.8.3. Additionally, the licensee will add a new LA DOC. In the ISTS, the specific ASTM standards are in the ISTS 3.8.3 Bases. The specific ASTM standards in CTS 6.0 are already in the ITS Bases 3.8.3. As such, this change to the program would just remove the redundant information from the Diesel Fuel Oil Testing Program.
ITS 5.5.8 - the licensee is planning to delete reference to the Backup Control Room Filtration System from ITS 5.5.8 and mark the CTS page to point to ITS 3.7.10. ITS 3.7.10 already has this information relocated to the TRM with an LA DOC. No additional DOC is necessary.
ITS 5.2 - the license is planning to add specific no significant hazard considerations (NSHCs) for ITS 5.2 DOCs L01 and L02 since these did not appear to fit a generic L DOC category.
Generic NSHCs - the licensee is planning to delete the current L DOC Category 9 - Deletion of Reporting Requirements. This category was not used by the licensee and the licensee is planning to delete reference to it.
There were no members of the public in attendance.
Please direct any inquiries to me at 301-415-3867, or Michael.Mahoney@nrc.gov.
/RA/
Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, and 50-389
Enclosure:
List of Attendees cc: Listserv
Enclosure LIST OF ATTENDEES AUGUST 11, PUBLIC MEETING WITH FLORIDA POWER AND LIGHT/NEXTERA ST. LUCIE PLANT, UNIT NOS. 1 AND 2 TURKEY POINT NUCLEAR GENERATING, UNIT NOS. 3 AND 4 IMPROVED STANDARD TECHNICAL SPECIFICATION CONVERSION Name Organization Michael Mahoney U.S. Nuclear Regulatory Commission (NRC)
Clinton Ashley NRC Craig Harbuck NRC Ravi Grover NRC Khadijah West NRC Matthew Hamm NRC Vic Cusumano NRC Josh Wilson NRC Andrea Russell NRC Steve Smith NRC William Maher Florida Power and Light Company (FPL)
Bruce Crabbs FPL Steven Kane FPL Jarrett Mack FPL Gregg Ellis Excel Services Corporation (Excel)
Jerry Riste Excel Charles DeDeaux Excel Christina Long Excel
Package: ML22229A544 Meeting Notice: ML22215A007 Meeting Summary: ML22229A525 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NAME MMahoney RButler DWrona DATE 8/23/2022 08/18/2022 08/24/2022