Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002)
ML22020A403
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 02/07/2022
From: Michael Mahoney
Plant Licensing Branch II
To:
Florida Power & Light Co
Mahoney M
References
EPID L-2021-LLI-0000, EPID L-2021-LLI-0002
Download: ML22020A403 (4)


Text

February 7, 2022 LICENSEE:

Florida Power and Light/NextEra FACILITIES: Saint Lucie Plant, Units 1 and 2; Turkey Point Nuclear Plant, Units 3 and 4

SUBJECT:

SUMMARY

OF NOVEMBER 17, 2021, MEETING WITH FLORIDA POWER AND LIGHT/NEXTERA ON IMPROVED TECHNICAL SPECIFICATION CONVERSION LICENSE AMENDMENT REQUESTS (EPID NOS. L-2021-LLI-0000 AND L-2021-LLI-0002)

On November 17, 2021, a virtual Observation public meeting was held between the U.S.

Nuclear Regulatory Commission (NRC) and representatives of Florida Power and Light/NextEra (FPL, the licensee). The purpose of the meeting was to discuss the license amendment requests (LARs) for Saint Lucie Plant, Units 1 and 2 (STL) and Turkey Point Nuclear Plant Units 3 and 4 (TPN) to convert to improved standard technical specifications in accordance with NUREG-1431, Westinghouse Plants, and NUREG-1432, Combustion Engineering Plants, Rev. 5 (improved technical specification (ITS) Rev. 5). The meeting notice and agenda, dated November 5, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML21312A082. A list of attendees is provided in the Enclosure. The NRC staff presented draft information which is available at ADAMS Accession No. ML21320A261.

The NRC staff presented a list of questions developed, to the date of the meeting, during the acceptance review. The NRC staff went over each question to discuss with the licensee to ensure there is a common understanding of the information being sought. These items being discussed were included in letters to the licensee, requesting supplemental information in order to complete the NRCs acceptance review of the ITS LARs. These letters also included editorial items, for the consideration of the licensee to address in future supplements. On December 21, 2021, the NRC issued a letter requesting supplemental information for St. Lucie, which can be found in ADAMS at Accession No. ML21342A293 and the letter for Turkey Point, also dated December 21, 2021 can be found in ADAMS at Accession No. ML21350A426.

Members of the public were not in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-3867, or Michael.Mahoney@nrc.gov.

/RA/

Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335, 50-389, 50-250 and 50-251

Enclosure:

List of Attendees cc: Listserv

Enclosure LIST OF ATTENDEES NOVEMBER 17, 2021, MEETING WITH FPL/NEXTERA IMPROVED STANDARD TECHNICAL SPECIFICATION CONVERSION NRC Clinton Ashley Ravi Grover Matt Hamm Craig Harbuck Natreon Jordan Andrea Russell Steve Smith Tarico Sweat Khadijah West Joshua Wilson David Wrona Michael Mahoney FPL/NextEra Excel Services William Maher Gregg Ellis David Stoia Jerry Riste Jarrett Mack Bob Pell Richard Orthen Charles DeDeaux Steve Catron Randy Newton Fred Pollak Jarrett Mack Richard Sciscente Steve Franzone Susan Baughn Michael Friedman

Meeting Notice, ML21312A082 Meeting Summary, ML22020A403 Handouts, ML21320A261 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NAME MMahoney RButler DWrona DATE 02/04/2022 01/27/2022 02/07/2022