MONTHYEARML21265A2842021-09-15015 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Request ML21265A2942021-09-15015 September 2021 Enclosure 2 - Volume 9 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.4 Reactor Coolant System (Rcs), Revision 0 Project stage: Request ML21265A2932021-09-15015 September 2021 Enclosure 2 - Volume 8 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.3 Instrumentation, Revision 0 Project stage: Request ML21265A2912021-09-15015 September 2021 Enclosure 2 - Volume 6 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.1 Reactivity Control Systems, Revision 0 Project stage: Request ML21265A2902021-09-15015 September 2021 Enclosure 2 - Volume 5 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.0 LCO and SR Applicability, Revision 0 Project stage: Request ML21265A2962021-09-15015 September 2021 Enclosure 2 - Volume 11 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.6 Containment Systems, Revision 0 Project stage: Request ML21265A2952021-09-15015 September 2021 Enclosure 2 - Volume 10 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.5 Emergency Core Cooling Systems (Eccs), Revision 0 Project stage: Request ML21265A2972021-09-15015 September 2021 Enclosure 2 - Volume 12 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.7 Plant Systems, Revision 0 Project stage: Request ML21265A2882021-09-15015 September 2021 Enclosure 2 - Volume 3 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Chapter 1.0 Use and Application, Revision 0 Project stage: Other ML21265A2852021-09-15015 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Request L-2021-159, Enclosures 1,3,4,5, and 6 - Contents of the St. Lucie Plant, Units 1 and 2, Improved Technical Specifications (ITS) Submittal2021-09-15015 September 2021 Enclosures 1,3,4,5, and 6 - Contents of the St. Lucie Plant, Units 1 and 2, Improved Technical Specifications (ITS) Submittal Project stage: Request ML21265A2982021-09-15015 September 2021 Enclosure 2 - Volume 13 - St. Lucie Plant, Units 1 and 2, Improved Technical Specifications Conversion ITS Section 3.8 Electrical Systems, Revision 0 Project stage: Request ML21265A3822021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 11, Revision 0, Section 3.6, Containment Systems Project stage: Request ML21265A3812021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 9, Revision 0, Section 3.5, Emergency Core Cooling Systems (ECCS) Project stage: Request ML21265A3852021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 14, Revision 0, Section 3.9, Refueling Operations Project stage: Request L-2021-158, Contents of the Turkey Point Nuclear Plant, Units 3 and 4 Improved Technical Specifications (Its) Submittal2021-09-22022 September 2021 Contents of the Turkey Point Nuclear Plant, Units 3 and 4 Improved Technical Specifications (Its) Submittal Project stage: Request ML21265A3842021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 13, Revision 0, Section 3.8, Electrical Power Systems Project stage: Request ML21265A3792021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 8, Revision 0, Section 3.3, Instrumentation Project stage: Request ML21265A3772021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 6, Revision 0, Section 3.1, Reactivity Control Systems Project stage: Request ML21265A3802021-09-22022 September 2021 Improved Technical Specifications Conversion, Volume 9, Revision 0, Section 3.4, Reactor Coolant Systems (RCS) Project stage: Request ML21265A3712021-09-22022 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1431 Revision 5 Project stage: Request ML21265A3702021-09-22022 September 2021, 23 September 2021 License Amendment Request for the Technical Specifications Conversion to NUREG-1431 Revision 5 Project stage: Request PMNS20211440, Notice of Forthcoming Meeting with Nextera/Florida Power and Light (FPL) Regarding the Conversion of Turkey Point Nuclear Generating Station, Units 3 and 4, and St. Lucie Plant, Units 1 and 2 to Improved Technical Specifications2021-11-0808 November 2021 Notice of Forthcoming Meeting with Nextera/Florida Power and Light (FPL) Regarding the Conversion of Turkey Point Nuclear Generating Station, Units 3 and 4, and St. Lucie Plant, Units 1 and 2 to Improved Technical Specifications Project stage: Request ML21350A4262021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Licensing Amendment Request Concerning Technical Specification Conversion to NUREG-1432, Revision 5 Project stage: Acceptance Review ML21342A2932021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Requested License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 Project stage: Acceptance Review L-2022-000, License Amendment Request for the Technical Specifications Conversion to NUREG- 1432 Revision 5 - Request for Supplemental Information (Rsi) Response2022-01-19019 January 2022 License Amendment Request for the Technical Specifications Conversion to NUREG- 1432 Revision 5 - Request for Supplemental Information (Rsi) Response Project stage: Supplement L-2022-010, License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 -Request for Supplemental Information Response2022-01-19019 January 2022 License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 -Request for Supplemental Information Response Project stage: Supplement NUREG-1431, Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 52022-02-0303 February 2022 Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 Project stage: Acceptance Review ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) Project stage: Meeting ML22054A1382022-02-16016 February 2022 February 24, 2022 ITS Public Meeting Material - Florida Power and Light Project stage: Meeting ML22054A1662022-02-23023 February 2022 ITS Public Meeting Material - NRC - Expectations for Licensees Responses to ITS Conversion LAR and RAIs Project stage: Meeting NUREG-1432, Acceptance of License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 52022-02-23023 February 2022 Acceptance of License Amendment Request for the Technical Specifications Conversion to NUREG-1432, Revision 5 Project stage: Acceptance Review PMNS20220112, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-02-23023 February 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting PMNS20220139, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-02-23023 February 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting PMNS20220236, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-03-11011 March 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220321, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-04-0505 April 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220427, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-04-27027 April 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22154A4992022-04-27027 April 2022, 7 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting PMNS20220454, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-05-17017 May 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Meeting ML22154A5182022-06-0909 June 2022 Summary of June 2, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request PMNS20220609, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-06-14014 June 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22228A1982022-06-28028 June 2022, 22 August 2022 Summary of July 14, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request PMNS20220683, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request2022-06-28028 June 2022 Meeting with NextEra Energy/Florida Power & Light Company to Discuss the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Improved Technical Specifications (ITS) License Amendment Request Project stage: Meeting ML22228A2432022-07-14014 July 2022, 23 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request Project stage: Request 2022-03-21
[Table View] |
Text
December 8, 2022 LICENSEE:
Florida Power and Light FACILITIES: St. Lucie Plant, Unit Nos. 1 and 2 Turkey Point Nuclear Generating Unit Nos. 3 and 4
SUBJECT:
SUMMARY
OF OCTOBER 27, 2022, MEETING WITH FLORIDA POWER AND LIGHT ON ST. LUCIE AND TURKEY POINT IMPROVED TECHNICAL SPECIFICATION CONVERSION LICENSE AMENDMENT REQUESTS (EPID NOS. L-2021-LLI-0000 AND L-2021-LLI-0002)
On October 27, 2022, a virtual observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power and Light (FPL, the licensee). The purpose of the meeting was to discuss the license amendment requests (LARs) for St. Lucie Plant, Unit Nos. 1 and 2 to convert to improved standard technical specifications in accordance with NUREG-1432, Standard Technical Specifications - Combustion Engineering Plants, Revision 5 (improved standard Technical Specifications (ISTS)) and Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point) to convert to improved standard technical specifications in accordance with NUREG-1431, Standard Technical Specifications -
Westinghouse Plants, Revision 5. The meeting notice and agenda, dated October 17, 2022, are available in the Agencywide Documents Access and Management System (ADAMS)
Accession No. ML22290A161. A list of attendees is provided in the Enclosure.
The following items for the St. Lucie review were discussed during the meeting:
NRC and licensee staff engaged in discussion regarding the overall status of the review effort and use of the database.
o Staff and licensee discussed changes made to format and layout of Q&A database.
o Staff provided suggestions to make it easier to use.
o Licensee specified that they will work with vendor to make necessary changes.
Regarding review of the St. Lucie ITS review, staff asked questions concerning the proposed ITS 3.1 and ITS 3.5.
o Staff asked the licensee to Clarify aspects pertaining to ITS 3.1.2 bases.
o Staff asked the licensee to provide an explanation for the removal of a Note in the proposed ITS 3.5.1 related to the pressurizer pressure.
o NRC and licensee staff discussed other formatting issues regarding ITS 3.5.1.
o NRC and licensee staff engaged in discussion regarding formatting preferences for questions related to Section 3.8 editorial changes. Preferences were discussed regarding how NRC questions would be submitted. It was determined that NRC staff will break up questions, when needed, and keep editorial questioning by section.
There were no members of the public in attendance for this meeting.
For questions or comments, please contact me at 301-415-7410, or Natreon.Jordan@nrc.gov.
/RA/
Natreon (Nate) Jordan, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, and 50-389
Enclosure:
List of Attendees cc: Listserv
Enclosure LIST OF ATTENDEES OCTOBER 27, PUBLIC MEETING WITH FPL/NEXTERA ST. LUCIE PLANT, UNIT NOS. 1 AND 2 TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 IMPROVED STANDARD TECHNICAL SPECIFICATION CONVERSION Name Organization Natreon (Nate) Jordan U.S. Nuclear Regulatory Commission (NRC)
Clinton Ashley NRC Craig Harbuck NRC Ravi Grover NRC Khadijah West NRC Matthew Hamm NRC Vic Cusumano NRC Josh Wilson NRC Andrea Russell NRC Steve Smith NRC William Maher Florida Power and Light Company (FPL)
Michael Coen FPL Michael Davis FPL Jarrett Mack FPL Gregg Ellis Excel Services Corporation (Excel)
Jerry Riste Excel Charles DeDeaux Excel Christina Long Excel
Package: ML22329A036 Meeting Notice: ML22290A161 Meeting Summary: ML22327A240 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NAME NJordan RButler DWrona DATE 11/22/2022 11/30/2022 12/8/2022