June 30, 2022 LICENSEE:
Florida Power and Light Company/NextEra FACILITY:
Turkey Point Nuclear Generating Unit Nos. 3 and 4
SUBJECT:
SUMMARY
OF MAY 24, 2022, CLOSED MEETING WITH FLORIDA POWER AND LIGHT TO DISCUSS PLANNED LICENSE AMENDMENT REQUEST RELATED TO REACTOR COOLANT PUMP SEAL REPLACEMENTS (EPID L-2021-LRM-0009)
On May 24, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives of Florida Power and Light Company (FPL or the licensee) to discuss a planned license amendment request (LAR) related to reactor coolant pump seals for the Turkey Point Nuclear Generating Unit Nos. 3 and 4. The meeting was closed to the public due to discussion of proprietary information. The meeting notice and agenda for this meeting, dated May 11, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22131A254. A list of attendees is enclosed. No regulatory decisions were made at this meeting.
The following topics were discussed:
Purpose and background Approach to address fire risk increase PRA risk increase between the current and new replacement RCP seals Data supporting RCP seal failure model Proposed schedule Note, a non-proprietary version of the meeting slides can be found in ADAMS at Accession No. ML22144A390.
No members of the public were in attendance.
Please direct any inquiries to me at 301-415-3867 or Michael.Mahoney@nrc.gov.
/RA/
Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251
Enclosure:
List of Attendees cc: Listserv
ML22160A379 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NRR/DORL/LPL2-2/PM NAME MMahoney RButler DWrona MMahoney DATE 06/14/2022 06/14/2022 06/16/2022 06/30/2022
Enclosure LIST OF ATTENDEES MAY 24, 2022, PUBLIC PORTION OF PARTIALLY CLOSED MEETING WITH FLORIDA POWER AND LIGHT REGARDING PLANNED LICENSE AMENDMENT REQUEST RELATED TO REACTOR COOLANT PUMP SEAL REPLACEMENT Name Organization Mike Mahoney U.S. Nuclear Regulatory Commission (NRC)
Ching Ng NRC Jeff Circle NRC Charles Moulton NRC Robert Pascarelli NRC Jay Robinson NRC Jarrett Mack Florida Power and Light Company (FPL)
Keith Vincent FPL Phil Barnes FPL Stetson Hindes FPL Anil Julka FPL Brian Dunn FPL Mark Averett FPL Joshua Goad FPL Phil Opsal Framatome, Inc. (Framatome)
Stuart Brown Framatome Jerry Tabat Framatome Gerald Cleveland Framatome Ricky Paugh Framatome Mary Beth Baker Framatome