Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request
ML22195A175
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/27/2022
From: Michael Mahoney
Plant Licensing Branch II
To: Moul D
Florida Power & Light Co
Mahoney M
References
EPID L-2021-LLI-0002
Download: ML22195A175 (5)


Text

July 27, 2022 LICENSEE: Florida Power and Light/NextEra FACILITIES: Turkey Point Nuclear Generating Unit Nos. 3 and 4

SUBJECT:

SUMMARY

OF JUNE 30, 2022, MEETING WITH FLORIDA POWER AND LIGHT/NEXTERA ON TURKEY POINT IMPROVED TECHNICAL SPECIFICATION CONVERSION LICENSE AMENDMENT REQUEST (EPID NO. L-2021-LLI-0002)

On June 30, 2022, a virtual Observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power and Light/NextEra (FPL, the licensee). The purpose of the meeting was to discuss the license amendment request (LAR) for Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point) to convert to improved standard technical specifications in accordance with NUREG-1431, Standard Technical Specifications - Westinghouse Plants, Revision 5 (improved standard Technical Specifications (ISTS)). The meeting notice and agenda, dated June 14, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML22165A156. A list of attendees is provided in the Enclosure.

The following items were discussed during the meeting:

Status of all open questions in Question and Answer (QA) Portal.

Questions on the following ITS Sections:

o [JMW011, JMW050] - in a current Surveillance Requirement which was converted from current TS to ITS, the licensee identified that Turbine Pressure Valves are not installed, and licensee is planning to revise the application to remove reference to the Turbine Pressure Valves in the SR.

o [MEH008] Discussion on whether deletion of ITS ACTIONS 2.2.1.b.1 and 3.3.2.b.1 is a more restrictive change.

o [MEH009] Discussion of an apparent missing logical connector (AND) and order/arrangement of frequencies consistent with the ITS writers guide.

o [JWM026] NRC staff is waiting for a response for another question [JWM056]

before NRC closure, as the questions are related.

o Discussion on ITS Section 3.4.5, specifically a discussion of ITS LCO 3.4.5b and an apparent inconsistency with the Updated Final Safety Analysis Report, Section 14.2.6.

There was one member of the public in attendance.

Questions from public: None Please direct any inquiries to me at 301-415-3867, or Michael.Mahoney@nrc.gov.

/RA/

Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES JUNE 30, 2022, PUBLIC MEETING WITH FPL/NEXTERA IMPROVED STANDARD TECHNICAL SPECIFICATION CONVERSION Name Organization Michael Mahoney U.S. Nuclear Regulatory Commission (NRC)

Caroline Tilton NRC Clinton Ashley NRC Craig Harbuck NRC Ravi Grover NRC Khadijah West NRC Edmund Kleeh NRC Robert Elliott NRC Matthew Hamm NRC Vic Cusumano NRC Adakou Foli NRC Robert Beaton NRC Josh Wilson NRC Steve Smith NRC Diana Woodyatt NRC Andrea Russell NRC William Maher Florida Power and Light Company (FPL)

Jarrett Mack FPL Frederick Pollack FPL Richard Orthen FPL Michael Coen FPL Gregg Ellis Excel Services Corporation (Excel)

Jerry Riste Excel Charles DeDeaux Excel Christina Long Excel Clayon Crouch Dominion Energy Enclosure

Package: ML22195A178 Meeting Notice: ML122165A156 Meeting Summary: ML22195A175 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NAME MMahoney RButler DWrona DATE 07/14/2022 07/18/2022 07/27/2022