Forwards Insp Repts 50-327/85-35 & 50-328/85-35 on 851006-1105 & Notice of Violation
ML20138N150
Person / Time
Site: Sequoyah, 05000308
Issue date: 12/10/1985
From: Walker R, Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML20138N155 List:
References
NUDOCS 8512230390
Download: ML20138N150 (2)


See also: IR 05000327/1985035

Text

_. -

'

'UM h t

,'

..

34..

-

DEC 101985

Tennessee Valley Authority

/TN: Mr.ManagerH. G. ofParris

Power and

t

Engineering-(Nuclear)

6N11 B Missionary Ridge Place

1101 Market Street-

Chattanooga, TN 37402-2801

Gentlemen:

SUBJECT: REPORT NOS. 50-327/85-35 AND 50-328/85-35

On - 0ctober 6 - November 5, 1985, NRC inspected activities authorized by NRC

Operating License Nos. DPR-77 and. DPR-79 for your Sequoyah facility. At the

conclusion of the inspection, the findings were discussed with those members of

your staff identified in.the enclosed inspection report.

Areas examined during the inspection are identified in the report. Within these

areas, the inspection consisted of selective examinations of procedures and

representative records, interviews with personnel, and observation of activities

in progress.

The inspection findings indicate that certain activities violated NRC require-

ments. The violations, references to pertinent requirements, and elements to be

included in your response are presented in the enclosed Notice of Violation.

- The responses directed by this letter and the enclosures are not subject to the

~

clearance procedures of the Office of Management and Budget issued under the

-

iPaperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this letter, please contact us.

Sincerely,

Original signed by

Virgil L. Brownlee for

Roger D. Walker, Director

Division of Reactor Projects

' Enclosures:

1. Notice'of Violation

2. Inspection Report Nos. 50-327/85-35

and 50-328/85-35

cc w/encls: (See page 2)

v

hk P

O.

".LEolkl-

.

m

.

f_ W ,

,

"3 Tennessee-Valley Authority 2

DEC 101985

cc/wneles:

tM L. Abercrombie, Sequoyah Nuclear Plant

Site Director-

  1. -R.'Wallace,-Plant Manager-
g. W. Whitt, Chief, Nuclear

.

Safety' Review Staff

g L. Williams, Jr., Supervisor

Licensing Section .

  1. B. Kirk, Compliance-Staff Supervisor

.

p V E. Wills,' Project Engineer

bp'w/encls: -

W RC~ Resident Inspector

Document Control Desk-

State of Tennessee

i

. ,

RII.' RII RII'

(Qcf L]

AIgnatonis:dr. SWeise DV rrelli

M/cy851 -H/6 /85 4t/4 /85

/d /A 42

.