Special Rept:On 880122,electrical motor-driven Fire Pump Declared Out of Svc for Corrective Maint Due to Packing Leak.Repair Activities Will Not Be Completed within 7 Days. Temporary Diesel Fire Pump Added to Supply Suppression Sys
ML20147D723
Person / Time
Site: Beaver Valley
Issue date: 02/29/1988
From: Lacey W
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
ND3SPM:0169, ND3SPM:169, NUDOCS 8803040111
Download: ML20147D723 (3)


Text

_ _ _ _ _ _ _ _ _ - _

'Af Telephone (41r> 393-e00o

. $7s'e'[4 February 29,1988 Shippingport, PA 15077-0004 ND3SPM:0169 Beaver Valley Power Station, Unit 1 Docket No. 50-334, License No. DPR-66 Special Report United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen, In accordance with Technical Specification 3.7.14.1, the following Special Report is submitted:

On January 22,1988, at 0200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br />, the Electrical Motor Driven Fire Pump (FP-P-1) was declared out of service for corrective maintenance. During operation of the fire pump on January 21,1988, a packing leak was detected. The pump was shutdown and a maintenance word request was generated to repair the fire pump.

Repair activities began on January 22,1988, to replace the packing. The packing is in the discharge diffuser area of the pump casing. This necessitates disassembly of the entire pump shaft casing to replace the spring loaded packing seal assembly. Since repair requires sending the pump assembly offsite to a vendor facility, it was anticipated that repair activities would not be completed within the seven (7) day period allowed by ACTION Statement "a" of Technical Specification 3.7.14.1. Therefore this Special Report is being generated in accordance with the requirements of the Technical Specification 3.7.14.1.

The fire pump (Peerless Pump, Model 16 HXB) has been removed from the system and was sent offsite on February 12,1988, for overhaul by a vendor service representative. The cause for the failed packing is believed to be normal wear.

Interim corrective action being taken until the fire pump is returned to service involves the addition of a temporary diesel-engine driven fire pump (Joy Model 7063-7000) to supply the fire suppression system. ,

bbk $50hh;54 'c fh

- *s$cbruary 29, 1988 ND3SPMt0169 Pa'ge 2 There were no safety implications to the public due to this incident.. The diesel-engine driven fire pump-(FP-P-2) remained operable during the entire period, and the temporary fire pump was available if required.

r F . S. Lac y Site Plant 3ager JGT/tlu t

a ' . - 'Fcbruary 29, 1988 Np3SPM:0169 _

Page 3 cc: Mr. William T. Russell Regional Administrato' ,

United States Nuclear 2 Commission Region-1 King of Prussia, PA C. A. Roteck, Ohio Edison Mr. Peter. Tam, BVPS Licensing Project Manager United States Nuclear Regulatory Commission Washir.gton, DC -20555 J. Beall, Nuclear Regulatory Commission, BVPS Senior Resident Inspector t Mr. Alex Timme, CAPCO Nuclear Projects Coordinator Toledo Edison INPO Records Center Suite 1500 1100 circle 75 Parkway Atlanta, GA 30339 G. E. Muckle, Factory Mutual Engineering, Pittsburgh Mr. J. N. Steinmetz, Operating Plant Projects Manager Mid Atlantic Area Westinghouse Electric Corporation Energy Systems Service Division Box 355 Pittsburgh, PA 15230 ,

American Nuclear Insurers c/o Dottie Sherman, ANI Library The Exchange Suite 245 270 Farmington Avenue Farmington, CT 06032 Mr. Richard Janati Department of Environmental Resources P. O. Box 2063 16th Floor, Fulton Building Harrisburg, PA 17120

_ _ _ . . . _ . _ _ _ . _ _ _ . . _ . . _ _ _