- 'A f ouquesneumt Telephone (412) 393-6000 Nuclear Dnnsson P. O. Box 4 Shippmgport PA 15077-0004 April 22, 1986 NDISS1:2793 Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Special Report United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In accordance with Appendix A, Beaver Valley Technical Specification 3.3.3.1, " Radiation Monitoring Instrumentation," the following Special Report is submitted. This report is required when the conditions specified in Technical Specification 3.3.3.1.b are not satisfied.
On 4/10/86 at 1730 hours0.02 days <br />0.481 hours <br />0.00286 weeks <br />6.58265e-4 months <br /> RM-VS-109, one of the SPING Radiation Monitors, was declared out-of-service due to a complete unit failure.
This failure included channels 7 and 9, medium and high range noble gas channels, which monitor the ventilation system exhaust. This is nonconservative with respect to Technical Specification 3.3.3.1 and reportable per Technical Specification 3.3.3.1.b.
Investigations to determine the root cause have been performed and with the assistance of the vendor, Eberline Instruments, the problem was resolved on 4/21/86. A failure was identified on the memory board and corrective actions included the replacement of the unit software with an updated version. RM-VS-109 will be placed back in service after the successful completion of its Maintenance Surveillance Procedure. The software in the remaining SPING units will be updated as an additional corrective action. There were no safety implications to the public because alternate preplanned monitoring has been and will be available until these channels are returned to service.
Very truly yours,
)
kC(.?
11, i
km. S. Lacey Plant Manage j>
8604280406 860422 PDR ADOCK 05000334 Y,.
S PDR 1
, April 22, 1986 NDISS1:2793 Page two cc: Dr. Thomas E. Murley Regional Administrator United States Nuc1 car Regulatory Commission Region 1 King of Prussia, PA 19406 C. A. Roteck, Ohio Edison Mr. Peter Tam, BVPS Licensing Project Manager United States Nuclear Regulatory Commission Washington, DC 20555 W. Troskoski, Nuclear Regulatory Commision, BVPS Site Inspector Mr. Alex Timme, CAPCO Nuclear Projects Coordinator, Toledo Edison INPO Records Center Suite 1500 1100 Circle 75 Parkway Atlanta, GA 30339 G. E. Muckle, Factory Mutual Engineering, Pittsburgh Mr. J. A. Triggiani, Operating Plant Projects Manager Mid Atlantic Area Westinghouse Electric Corporation Nuclear Services Integration Division Box 2728 Pittsburgh, PA 15230 American Nuclear Insurers c/o Dottie Sherman, ANI Library The Exchange Suite 245 270 Farmington Avenue Farmington, CT 06032 e