July 2003 Monthly Operating Report for Donald C. Cook, Units 1 & 2
ML032340644
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/15/2003
From: Zwolinski J
Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
-RFPFR, AEP:NRC:2691-33
Download: ML032340644 (8)


Text

Indiana Michigan Power Company i-1 500 Circle Drive Buchanan, MI 49107 1395 INDIANA MICHIGAN POWER August 15, 2003 AEP:NRC:2691-33 Docket Nos. 50-315 50-316 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-P1-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 MONTHLY OPERATING REPORT Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 and Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for July 2003 is submitted.

There are no new commitments associated with this submittal.

Should you have any questions, please contact Mr. Brian A. McIntyre, Manager of Regulatory Affairs, at (269) 697-5806.

Design Engineering and Regulatory Affairs JEN/jen Attachment

$6'eq

4 U. S. Nuclear Regulatory Commission AEP:NRC:2691-33 Page 2 c: ANI Nuclear Engineering Department L. Brandon - Department of Health M. J. Finissi G. T. Gaffney - Canton J. B. Giessner S. Hamming - Department of Labor INPO Records Center B. Lewis - McGraw-Hill Companies D. H. Malin K. L. Matheny B. A. McIntyre T. C. Pham NRC Project Manager - NRR NRC Region III NRC Resident Inspector D. W. Paul - Columbus W. H. Schalk J. A. Zwolinski

NRC OPERATING DATA REPORT DOCKET NO. 50-315 DATE 814/2003 COMPLETED BY T. Pham TELEPHONE 269-485-5901 OPERATING STATUS

1. Unit Name D. C. Cook Unit I Notes:
2. Reporting Period Jul-03
3. Licensed Thermal Power (MWt) 3304
4. Name Plate Rating (Gross MWe) 1152
5. Design Electrical Rating (Net MWe) 1020
6. Maximum Dependable Capacity(Gross MWe) 1056
7. Maximum Dependable Capacity (Net MWe) 1000
8. If Changes Occur InCapacity Ratings (Items no. 3 through 7)Since Last Report Give Reasons
9. Power Level To Which Restricted. If Any (Net MWe)
10. Reasons For Restrictions.

This Mo. Yr. to Date Cumm.

11. Hours InReporting Period 744.0 5087.0 250535.0
12. No. of Hrs. Reactor Was Critical 744.0 3809.9 171158.5
13. Reactor Reserve Shutdown Hours 0.0 0.0 463.0
14. Hours Generator on Line 744.0 3774.5 168463.4
15. Unit Reserve Shutdown Hours 0.0 0.0 321.0
16. Gross Therm. Energy Gen. (MWH) 2456948.9 12349742.0 502818816.6
17. Gross Elect. Energy Gen. (MWH) 783220.0 3988183.0 163230613.0
18. Net Elect. Energy Gen. (MWH) 756792.0 3855243.7 157130440.2
19. Unit Service Factor 100.0 74.2 67.7
20. Unit Availability Factor 100.0 74.2 67.7
21. Unit Capacity Factor (MDC Net) 101.7 75.8 64.2
22. Unit Capacity Factor (DER Net) 99.7 74.3 62.9
23. Unit Forced Outage Rate 0.0 25.8 19.3
24. Shutdowns Scheduled over Next Six Months Type,Date,and Duration):  :

Refueling outage currently scheduled for October 2003 with aplanned duration of 33 days.

25. If Shut Down At End of Report Period, Est'd Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO. 50-315 i::

UNIT ONE DATE 04-Aug-03 COMPLETED BY T. Pham TELEPHONE 269-465-5901 MONTH Jul-03 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 7/1/2003 983 7/17/2003 1011 7/2/2003 1027 7/1812003 1019 7/3/2003 1028 7/19/2003 1023 7/412003 1011 7/202003 1020 7/5/2003 1014 7/21/2003 1017 7/6/2003 1015 7/2212003 1024 7//2003 1016 7/23/2003 1028 7/8/2003 1017 7/24/2003 1032 7/9/2003 1025 7/25/2003 1004 7/10/2003 1023 7/26/2003 1019 7/11/2003 1018 7/27/2003 1015 7/12/2003 1020 7/28/2003 1011 7/13/2003 1010 7/29/2003 1020 7/14/2003 1023 7/30/2003 1016 7/15/2003 1017 7/31/2003 1008 7/16/2003 1021

DOCKET NO. 50- 315 UNIT NAME D.C. Cook Unit 1 DATE August 8, 2003 COMPLETED BY J. Newmiller TELEPHONE 269-465-5901 PAGE 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - July 2003 METHOD OF SHUTTiNG UCENSEE DURATiON DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE1 HOURS REASON 2 REACTOR 3 REPORT NO. CODE CODE 5 TO PREVENT RECURRENCE None 4I TVD-IUVn. *) OFAWNfM- Q n!LJf%% A QVQCIOAffN F: Forced A: Equipment Fallure (Explain) 1: Manual Exhibit G - Instructions Exhibiti: Same Source S: Scheuled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Ucensee D: Regulatory Restricton 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161) icense Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

p.

a NRC OPERATING DATA REPORT DOCKET NO.60-316 DATE 814/2003 COMPLETED BY T. Pharn TELEPHONE 269-45-6901 OPERATING STATUS

1. Unit Name D.C.Cook Unit 2
2. Reporting Period Jul-03
3. Licensed Thermal Power (MWt) 3468
4. Name Plate Rating (Gross MWe) 1133
6. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (Gross MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. Changes Occur InCapacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
9. Power Level To Which Restricted. If Any (Net MWe)
10. Reasons For Restrictions.

This Mo. Yr. to Date Cumm

11. Hours In Reporting Period 744.0 6087.0 224681.0
12. No. of Hrs. Reactor Was Critical 744.0 3452.6 145020.7
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Une 744.0 3390.3 141130.8
16. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Therm Energy Gen. (MWH) 2574773.6 11349471.2 442573168.6
17. Gross Elect. Energy Gen. (MWH) 824730.0 3716850.0 143490550.0
18. Net Elect. Energy Gen. (MWH) 7982780 3600070.6 138352810.0
19. Unit Service Factor 100.0 66.6 63.5
20. Unit Availabflity Factor 100.0 66.6 63.5
21. Unit Capacity Factor (MDC Net) 1012 66.8 59.2
22. Unit Capacity Factor (DER Net) 98.4 64.9 57.6
23. Unit Forced Outage Rate 0.0 14.4 23.6
24. Shutdowns Scheduled over Next Six Months (Type,Dateand Duration):
25. If Shut Down At End of Report Period, Est'd Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

4 1%

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO. 50-316 UNIT TWO DATE 4-Aug-03 COMPLETED BY T. Pham TELEPHONE 269-465-5901 MONTH Jul AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 7/1/2003 1029 7/17/2003 1061 7/2/2003 1078 7/18/2003 1072 7/312003 1078 7/19/2003 1092 714/2003 1063 7/20/2003 1084 715/2003 1076 7/21/2003 1018 7/6/2003 1070 7/22/2003 1073 7/7/2003 1067 7/23/2003 1073 7/8/2003 1073 7/24/2003 1099 7/9/2003 1080 7/25/2003 1071 7/10/2003 1082 7/26/2003 1077 7/1112003 1077 7/27/2003 1070 7/1212003 1072 7/28/2003 1072 7/13/2003 1074 7/29/2003 1073 7/14/2003 1074 7/30/2003 1093 7115/2003 1070 7/31/2003 1094 7/16/2003 1077

..

DOCKET NO. 50-316 Eh UNIT NAME D.C. Cook Unit 2 DATE August 8, 2003 COMPLETED BY J. Newmiller TELEPHONE 269465-5901 PAGE 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - July 2003 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE' HOURS REASON 2 REACTOR3 REPORT NO. CODE' CODE 5 TO PREVENT RECURRENCE None 1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Fanure (Explain) 1: Manual Exhibit G - Instructions Exhibit : Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

Ucense Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)