February 2002 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 & 2
ML020920573
Person / Time
Site: Cook  
Issue date: 03/15/2002
From: Greenlee S
Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
AEP:NRC:2691-08
Download: ML020920573 (8)


Text

Indiana Michigan Power Company 500 Circle Drive Buchanan, MI 49107 1395 INDIANA MICHIGAN POWER March 15, 2002 AEP:NRC:2691-08 Docket Nos.

50-315 50-316 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-P 1-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 MONTHLY OPERATING REPORT Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 and Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for February 2002 is submitted.

Sincerely, Scot A. Greenlee Director, Nuclear Technical Services IJ/pae Attachments

U. S. Nuclear Regulatory Commission Page 2 c: ANI Nuclear Engineering Department G. P Arent A. C. Bakken, III L. Brandon - Department of Health G. T. Gaffney - Canton S. A. Greenlee S. Hamming - Department of Labor RAF Harris INPO Records Center B. Lewis - McGraw-Hill Companies D. H. Malin B. A. McIntyre NRC Project Manager - NRR NRC Region III NRC Resident Inspector D. W. Paul - Columbus J. E. Pollock R. P. Powers M. W. Rencheck W. H. Schalk AEP:NRC:2691-08

N.R.C. OPERATING DATA REPORT DOCKET NO.

50-315 DATE 3/5/02 COMPLETED BY RAF Harris TELEPHONE 616-465-5901 OPERATING STATUS

1. Unit Name D. C. Cook Unit 1
2. Reporting Period Feb-02
3. Licensed Thermal Power (MWt) 3250
4. Name Plate Rating (Gross MWe) 1152
5. Design Electrical Rating (Net MWe) 1020
6. Maximum Dependable Capacity(GROSS MWe) 1056
7. Maximum Dependable Capacity (Net MWe) 1000
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7)

Notes:

Since Last Report Give Reasons

9. Power Level To Which Restricted. If Any (Net MWe)
10. Reasons For Restrictions.

This Mo.

Yr. to Date Cumm

11. Hours in Reporting Period 672.0 1416.0 238104.1
12. No. of Hrs. Reactor Was Critical 672.0 1416.0 160937.:
13. Reactor Reserve Shutdown Hours 0.0 0.0 463.(
14. Hours Generator on Line 672.0 1416.0 158321.,
15. Unit Reserve Shutdown Hours 0.0 0.0 321.(
16. Gross Therm. Energy Gen. (MWH) 2182252.8 4553304.6 470058611.1
17. Gross Elect. Energy Gen. (MWH) 714670.0 1490860.0 152723680.1
16. Net Elect. Energy Gen. (MWH) 692089.0 1443140.0 146977434.1
19. Unit Service Factor 100.0 100.0 67.(
20. Unit Availability Factor 100.0 100.0 67.(
21. Unit Capacity Factor (MDC Net) 103.0 101.9 63.,
22. Unit Capacity Factor (DER Net) 101.0 99.9 62.(
23. Unit Forced Outage Rate 0.0 0.0 19.ý
24. Shutdowns Scheduled over Next Six Months (Type, Date,and Duration):

Refuelina outaee 18 is scheduled to beain durina the second auarter of 2002. The prooosed lenath of the outaae is 35 days.

25. If Shut Down At End of Report Period, Est'd Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast Achieved 0

3 6

0 0

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-315 ONE 05-Mar-02 RAF Harris 616-465-5901 MONTH Feb-02 AVERAGE DAILY POWER LEVEL 1029 1029 1032 1032 1032 1038 1029 1030 1033 1033 1032 1033 1030 1034 1033 1037 DAY 2/17/02 2/18/02 2/19/02 2/20/02 2/21/02 2/22/02 2/23/02 2/24/02 2/25/02 2/26/02 2/27/02 2/28/02 AVERAGE DAILY POWER LEVEL 1029 1032 1031 1036 1023 1025 1020 1025 1025 1028 1016 1029 DAY 2/1/02 2/2/02 2/3/02 2/4/02 2/5/02 216/02 2/7102 2/8/02 2/9102 2/10/02 2/11/02 2/12/02 2/13/02 2/14/02 2/15/02 2/16/02

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50- 315 D.C. Cook Unit 1 March 11, 2002 N Jackiw 616-465-5901 1 of I UNIT SHUTDOWNS AND POWER REDUCTIONS - February 2002 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO.

DATE TYPE1 HOURS REASON2 REACTOR3 REPORT NO.

CODE4 CODE 5 TO PREVENT RECURRENCE I TYPE:

F: Forced S: Scheduled 2 REASON:

A: Equipment Failure (Explain)

B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain) 3 METHOD:

1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:

Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:

Exhibit I: Same Source

N.R.C. OPERATING DATA REPORT DOCKET NO.

50-316 DATE 3/5/02 COMPLETED BY RAF Harris TELEPHONE 616-465-5901 OPERATING STATUS

1. Unit Name D.C. Cook Unit 2 Notes:
2. Reporting Period Feb-02
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity(GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
9. Power Level To Which Restricted. If Any (Net MWe)
10. Reasons For Restrictions.

This Mo.

Yr. to Date

11. Hours in Reporting Period 672.0 1416.0
12. No. of Hrs. Reactor Was Critical 85.4 517.5
13. Reactor Reserve Shutdown Hours 0.0 0.0
14. Hours Generator on Line 18.5 450.6
15. Unit Reserve Shutdown Hours 0.0 0.0
16. Gross Therm. Energy Gen. (MWH) 27833.8 1343609.3
17. Gross Elect. Energy Gen. (MWH) 3520.0 434540.0
18. Net Elect. Energy Gen. (MWH) 2972.7 419209.7
19. Unit Service Factor 2.8 31.8
20. Unit Availability Factor 2.8 31.8
21. Unit Capacity Factor (MDC Net) 0.4 27.9
22. Unit Capacity Factor (DER Net) 0.4 27.2
23. Unit Forced Outage Rate 4.1 0.2
24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
25. If Shut Down At End of Report Period, Est'ed Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast Commenced power escalation on 2/28/02.

Achieved Cumm.

212250.0 134622.5 0.0 130852.5 0.0 408170958.6 132261050.0 127484263.6 62.3 62.3 57.8 56.3 24.6

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-316 TWO 5-Mar-02 RAF Harris 616-465-5901 MONTH Feb-02 AVERAGE DAILY POWER LEVEL 0

0 0

0 0

0 0

0 0

0 0

0 0

0 0

0 DAY 2/17/02 2/18/02 2/19/02 2/20/02 2/21/02 2/22/02 2/23/02 2/24/02 2/25/02 2/26/02 2/27/02 2/28/02 AVERAGE DAILY POWER LEVEL 0

0 0

0 0

0 0

0 0

0 0

124 DAY 2/1/02 2/2/02 2/3/02 2/4/02 2/5/02 2/6/02 2/7/02 2/8/02 2/9/02 2/10102 2/11/02 2/12/02 2/13/02 2/14/02 2/15/02 2/16102

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50-316 D.C. Cook Unit 2 March 11, 2002 IN Jackiw 616-465-5901 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - February 2002 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO.

DATE TYPE' HOURS REASON2 REACTOR3 REPORT NO.

CODE 4 CODE5 TO PREVENT RECURRENCE 340 020201 S

652.7 C

2 Continuation of Unit 2 scheduled Refueling Outage (U2C13),

341 020228 F

0.8 A

4 Power reduction from approximately 28% to 2.5 % to adjust steam generator stop valve 2-MRV-220. Reactor remained in Mode 2.

F: Forced S: Scheduled 2 REASON:

A: Equipment Failure (Explain)

B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain) 3 METHOD:

1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:

Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:

Exhibit I: Same Source