MONTHYEAR05000316/LER-2024-004, AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications2024-11-11011 November 2024 AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications IR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] Category:License-Monthly Operating Report
MONTHYEARML0602503852006-01-13013 January 2006 December 2005 Monthly Operating Report for Donald C. Cook Units 1 & 2 ML0536300452005-12-14014 December 2005 December 2005 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0532604202005-11-11011 November 2005 October 2005 Monthly Operating Report for Donald C. Cook Units 1 and 2 ML0529902812005-10-14014 October 2005 September 2005 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0527002382005-09-14014 September 2005 August 2005 Monthly Operating Report for Donald C. Cook Units 1 and 2 ML0523501752005-08-12012 August 2005 July 2005 Monthly Operating Report for Donald C Cook Nuclear Plant Units 1 and 2 ML0520706942005-07-15015 July 2005 June 2005 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 2 ML0517304332005-06-14014 June 2005 May 2005 Monthly Operating Report for Donald C Cook Nuclear Plant Units 1 and 2 ML0514403902005-05-13013 May 2005 April 2005 Monthly Operating Report for Donald C Cook Nuclear Plant Units 1 and 2 ML0511602202005-04-14014 April 2005 March 2005 Monthly Operating Report for D.C. Cook, Units 1 and 2 ML0508202372005-03-15015 March 2005 February 2005 Monthly Operating Report for Donald C. Cook Nuclear Plant, Units 1 and 2 ML0505406022005-02-15015 February 2005 January 2005 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0502601922005-01-12012 January 2005 December 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant, Units 1 and 2 ML0435200892004-12-15015 December 2004 November 2004 Monthly Operating Report for Donald C Cook Nuclear Plant Units 1 and 2 ML0432805992004-11-15015 November 2004 October 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant, Units 1 and 2 ML0429402642004-10-11011 October 2004 September 2004 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0426600752004-09-0909 September 2004 August 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 2 ML0424506062004-08-11011 August 2004 July 2004 Monthly Report for Donald C. Cook Nuclear Plant Units 1 and 2 AEP-NRC-2691-44, June 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 22004-07-12012 July 2004 June 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 2 ML0416901372004-06-10010 June 2004 May 2004 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 2 ML0414103092004-05-14014 May 2004 April 2004 Monthly Operating Report for Donald C. Cook, Unit Nos. 1 and 2 ML0411203622004-04-14014 April 2004 March 2004 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0407806212004-03-0909 March 2004 February 2004 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0404904732004-02-10010 February 2004 January 2004 Monthly Operating Report for D.C. Cook, Units 1 and 2 ML0402905472004-01-14014 January 2004 December 2003 Monthly Operating Report for Donald C Cook Units 1 and 2 ML0335301082003-12-0505 December 2003 November 2003 Monthly Operating Report for D.C. Cook, Units 1 and 2 ML0332800262003-11-14014 November 2003 October 2003 Monthly Operating Report for D C Cook Units 1 and 2 ML0329504582003-10-15015 October 2003 September 2003 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0326709912003-09-15015 September 2003 August 2003 Monthly Operating Report for D.C. Cook, Units 1 and 2 ML0323406442003-08-15015 August 2003 July 2003 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0320400552003-07-12012 July 2003 June 2003 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0316900252003-06-13013 June 2003 May 2003 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 & 2 ML0313900242003-05-15015 May 2003 April 2003 Monthly Operating Report for Donald C. Cook Units 1 & 2 ML0310704352003-04-11011 April 2003 March 2003 Monthly Operating Report for Donald C. Cook Nuclear Plant, Units 1 & 2 ML0307705772003-03-14014 March 2003 February 2003 Monthly Operating Report for Donald C. Cook Units 1 & 2 ML0305804672003-02-14014 February 2003 January 2003 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 & 2 ML0301701792003-01-15015 January 2003 December 2002 Monthly Operating Report for Donald C. Cook ML0235200332002-12-13013 December 2002 November 2002 Monthly Operating Report for Donald C. Cook Units 1 & 2 ML0232201872002-11-15015 November 2002 October 2002 Monthly Operating Report for Donald C Cook ML0228901292002-10-15015 October 2002 September 2002 Monthly Operating Report for Donald C. Cook, Units 1 and 2 ML0226101762002-09-13013 September 2002 August 2002 Monthly Operating Report for Donald C. Cook ML0223102782002-08-15015 August 2002 July 2002 Monthly Operating Report for Donald C. Cook Nuclear Plant, Units 1 and 2 ML0213501872002-05-13013 May 2002 April 2002 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0210600872002-04-12012 April 2002 March 2002 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 and 2 ML0209205732002-03-15015 March 2002 February 2002 Monthly Operating Report for Donald C. Cook Nuclear Plant Units 1 & 2 ML0205100262002-02-14014 February 2002 January 2002 Monthly Operating Report for Donald C. Cook, Units 1 & 2 ML0201800082002-01-11011 January 2002 December 2001 Monthly Operating Report for Donald C. Cook Units 1 and 2 2006-01-13
[Table view] |
Text
Indiana Michigan Power Company 500 Circle Drive Buchanan, Ml 49107 1373 INDIANA MICHIGAN POWER April 11, 2003 AEP:NRC:2691-29 Docket Nos. 50-315 50-316 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-P1-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units I and 2 MONTHLY OPERATING REPORT Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 and Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for March 2003 is submitted.
Sincerely, Director Design Engineering and Regulatory Affairs BWO/rdw Attachment 2*4AC
U. S. Nuclear Regulatory Commission AEP:NRC:2691-29 Page 2 c: ANI Nuclear Engineering Department A. C. Bakken, III L. Brandon - Department of Health M. J. Finissi G. T. Gaffney - Canton J. B. Giessner S. Hamming - Department of Labor RAF Harris INPO Records Center B. Lewis - McGraw-Hill Companies D. H. Malin K. L. Matheny B. A. McIntyre NRC Project Manager - NRR NRC Region III NRC Resident Inspector D. W. Paul - Columbus J. E. Pollock W. H. Schalk
N.R.C. OPERATING DATA REPORT DOCKET NO. 50-315 DATE 4/2103 COMPLETED BY T Pham TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D.C. Cook Unit I Notes:
- 2. Reporting Period Mar-03
- 3. Licensed Thermal Power (MWt) 3304
- 4. Name Plate Rating (Gross MWe) 1152
- 5. Design Electrical Rating (Net MWe) 1020
- 6. Maximum Dependable Capacity(GROSS MWe) 1056
- 7. Maximum Dependable Capacity (Net MWe) 1000
- 8. If Changes Occur InCapacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo. Yr. to Date Cumm.
- 11. Hours in Reporting Period 744.0 2160.0 247608.0
- 12. No. of Hrs. Reactor Was Critical 744.0 1695.2 169043.8
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 463.0
- 14. Hours Generator on Une 744.0 1673.6 166362.5
- 15. Unit Reserve Shutdown Hours 0.0 0.0 321.0
- 16. Gross Therm. Energy Gen. (MWH) 2456661.4 5474006.0 495743080.6
- 17. Gross Elect. Energy Gen. (MWH) 798010.0 1777460.0 161019890.0
- 18. Net Elect. Energy Gen. (MWH) 771765.0 1718515.5 154993712.0
- 19. Unit Service Factor 100.0 77.5 67.7
- 20. Unit Availability Factor 100.0 77.5 67.7
- 21. Unit Capacity Factor (MDC Net) 103.7 79.6 64.0
- 22. Unit Capacity Factor (DER Net) 101.7 78.0 62.8
- 23. Unit Forced Outage Rate 0.0 22.5 19.2
- 24. Shutdowns Scheduled over Next Six Months (TypeDate,and Duration):
- 25. If Shut Down At End of Report Period, Est'd Date of Startup: -
- 26. Units In Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO. 50-315 UNIT ONE DATE 02-Apr-03 COMPLETED BY T Pham TELEPHONE 269-465-5901 MONTH Mar-03 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 3/11/03 1040 3/17/03 1037 3/2103 1042 3/18/03 1040 3/3/03 1035 3/19103 1036 3/4/03 1036 3/20/03 1030 3/5/03 1044 3/21/03 1039 3/6/03 1041 3/22/03 1039 317/03 1037 3/23/03 1033 3/8/03 1042 3124/03 1035 3/9/03 1038 3125/03 1037 3/10/03 1042 3/26/03 1035 3/11/03 1035 3/27/03 1031 3/12/03 1036 3/28/03 1034 3113103 1038 3/29/03 1040 3/14/03 1035 3/30/03 1031 3115/03 1036 3/31/03 1046 3/16/03 1038
DOCKET NO. 50-315 UNIT NAME D.C. Cook Unit I DATE April 2, 2003 COMPLETED BY B. O'Rourke TELEPHONE 269-465-5901 PAGE 1of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - March 2003 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE1 HOURS REASON 2 REACTOR 3 REPORT NO. CODE 4 CODE 5 TO PREVENT RECURRENCE None 1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:
F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit l: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)
License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain)
N.R.C. OPERATING DATA REPORT DOCKET NO. 50-316 DATE 4/2/03 COMPLETED BY T Pham TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D.C. Cook Unit 2 Notes:
- 2. Reporting Period Mar-03
- 3. Licensed Thermal Power (MWt) 3411
- 4. Name Plate Rating (Gross MWe) 1133
- 5. Design Electrical Rating (Net MWe) 1090
- 6. Maximum Dependable Capacity(GROSS MWe) 1100
- 7. Maximum Dependable Capacity (Net MWe) 1060
- 8. If Changes Occur InCapacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo. Y'r.to Date Cumm.
- 11. Hours in Reporting Period 744.0 2160.0 221754.0
- 12. No. of Hrs. Reactor Was Critical 744.0 1884.6 143452.7
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 14. Hours Generator on Line 744.0 -1849.1 139589.6
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Therm. Energy Gen. (MWH) 2536498.7 45215442.3 437439139.6
- 17. Gross Elect. Energy Gen. (MWH) 843740.0 2060580.0 141834280.0
- 18. Net Elect. Energy Gen. (MWH) 818582.0 1997487.8 136750227.1
- 19. Unit Service Factor 100.0 85.6 63.6
- 20. Unit Availability Factor 100.0 85.6 63.6
- 21. Unit Capacity Factor (MDC Net) 103.8 87.2 59.3
- 22. Unit Capacity Factor (DER Net) 100.9 84.8 57.7
- 23. Unit Forced Outage Rate 0.0 14.4 23.7
- 24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
Rpfeplinn tiAenp achpduiedd fnr Mavn 2003.
- 25. If Shut Down At End of Report Period, Est'ed Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
v AVERAGE DAILY POWER LEVEL (MWeNet)
DOCKET NO. 50-316 UNIT TWO DATE 2-Apr-03 COMPLETED BY T Pham TELEPHONE 269-465-5901 MONTH Mar-03 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 311/03 1102 3/17/03 1102 312/03 1101 3118/03 1095 3/3/03 1101 3119/03 1101 314/03 1104 3/20/03 1102 3/5/03 1102 3/21/03 1102 3/6103 1111 3/22/03 1098 317/03 1103 3/23/03 1094 3/8/03 1097 3/24/03 1102 3/9103 1100 3/25/03 1097 3/10/03 1093 3/26/03 1106 3111/03 1095 3/27/03 1101 3112103 1101 3/28/03 1094 3113103 1102 3/29/03 1097 3114/03 1097 3/30/03 1099 3115103 1101 3/31/03 1103 3116/03 1106
DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit 2 DATE April 2, 2003 COMPLETED BY B. O'Rourke TELEPHONE 269-465-5901 PAGE 1 of I UNIT SHUTDOWNS AND POWER REDUCTIONS - March 2003 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE 1 HOURS REASON 2 REACTOR 3 REPORT NO. CODE 4 CODE 5 TO PREVENT RECURRENCE None 1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:
A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit l: Same Source F: Forced S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)
License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain)