Indiana Michigan Power Company 500 Circle Drive Buchanan, Ml 49107 1395 INDIANA MICHIGAN POWER December 13, 2002 Docket Nos.
AEP:NRC:2691-25 50-315 50-316 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-P1-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 MONTHLY OPERATING REPORT Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 and Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for November 2002 is submitted.
Sincerely, Scot A. Greenlee Director, Nuclear Technical Services BWO/jen Attachments
U. S. Nuclear Regulatory Commission Page 2 c: ANI Nuclear Engineering Department A. C. Bakken, III L. Brandon - Department of Health G. T. Gaffney - Canton S. A. Greenlee S. Hamming - Department of Labor RAF Harris INPO Records Center B. Lewis - McGraw-Hill Companies D. H. Malin B. A. McIntyre NRC Project Manager - NRR NRC Region III NRC Resident Inspector D. W. Paul - Columbus J. E. Pollock W. H. Schalk AEP:NRC:2691-25
N.R.C. OPERATING DATA REPORT DOCKET NO.
50-315 DATE 12/10/02 COMPLETED BY RAF Harris TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D.C. Cook Unit 1 Notes:
- 2. Reporting Period Nov-02
- 3. Licensed Thermal Power (MWt) 3250
- 4. Name Plate Rating (Gross MWe) 1152
- 5. Design Electrical Rating (Net MWe) 1020
- 6. Maximum Dependable Capacity(GROSS MWe) 1056
- 7. Maximum Dependable Capacity (Net MWe) 1000
- 8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo.
Yr. to Date
- 11. Hours in Reporting Period 720.0 8016.0
- 12. No. of Hrs. Reactor Was Critical 720.0 7083.3
- 13. Reactor Reserve Shutdown Hours 0.0 0.0
- 14. Hours Generator on Line 720.0 7039.5
- 15. Unit Reserve Shutdown Hours 0.0 0.0
- 16. Gross Therm. Energy Gen. (MWH) 2304291.6 22419735.0
- 17. Gross Elect. Energy Gen. (MWH) 751750.0 7241800.0
- 18. Net Elect. Energy Gen. (MWH) 726636.0 6999120.6
- 19. Unit Service Factor 100.0 87.8
- 20. Unit Availability Factor 100.0 87.8
- 21. Unit Capacity Factor (MDC Net) 100.9 87.3
- 22. Unit Capacity Factor (DER Net) 98.9 85.6
- 23. Unit Forced Outage Rate 0.0 1.4
- 24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
- 25. If Shut Down At End of Report Period, Est'd Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Cumm.
244704.0 166604.6 463.0 163944.9 321.0 487925042.0 158474620.0 152533414.5 67.5 67.5 63.8 62.5 19.2
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-315 ONE 02-Dec-02 RAF Harris 269-465-5901 MONTH Nov-02 AVERAGE DAILY POWER LEVEL 1031 1031 1033 1032 1030 1032 1027 1031 1034 1036 466 934 1030 1038 1027 1041 DAY 11/17/02 11/18/02 11/19/02 11/20/02 11/21/02 11/22/02 11/23/02 11/24/02 11/25/02 11/26/02 11/27/02 11/28/02 11/29/02 11/30/02 AVERAGE DAILY POWER LEVEL 1021 1030 1037 1027 1032 1033 1031 1026 1028 1031 1029 1032 1033 1033 DAY
.11/1/02 11/2/02 11/3/02 11/4/02 11/5102 11/6/02 11/7/02 11/8/02 11/9/02 11110/02 11/11/02 11/12/02 11/13/02 11/14/02 11/15/02 11/16/02
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50-315 D.C. Cook Unit 1 December 3, 2002 B. O'Rourke 269-465-5901 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - November 2002 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO.
'DATE TYPE1 HOURS REASON 2 REACTOR3 REPORT NO.
CODE4 CODE5 TO PREVENT RECURRENCE 344 021110 S
0 B
4 n/a AB P
Unit 1 power reduced to 30% to allow containment entry to add oil to the #14 Reactor Coolant Pump.
1 TYPE:
F: Forced S: Scheduled 2 REASON:
A: Equipment Failure (Explain)
B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain) 3 METHOD:
1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:
Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:
Exhibit I: Same Source
N.R.C. OPERATING DATA REPORT DOCKET NO.
50-316 DATE 1212/02 COMPLETED BY RAF Harris TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D. C. Cook Unit 2 Notes:
- 2. Reporting Period Nov-02
- 3. Licensed Thermal Power (MWt) 3411
- 4. Name Plate Rating (Gross MWe) 1133
- 5. Design Electrical Rating (Net MWe) 1090
- 6. Maximum Dependable Capacity(GROSS MWe) 1100
- 7. Maximum Dependable Capacity (Net MWe) 1060
- 8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo.
Yi
- 11. Hours in Reporting Period 720.0
- 12. No. of Hrs. Reactor Was Critical 720.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator on Line 720.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Therm. Energy Gen. (MWH) 2454561.1 21
- 17. Gross Elect. Energy Gen. (MWH) 816920.0
- 18. Net Elect. Energy Gen. (MWH) 791251.0
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (MDC Net) 103.7
- 22. Unit Capacity Factor (DER Net) 100.8
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
Refuelina Outaoe scheduled for Aoril 2003
- r. to Date 8016.0 6719.1 0.0 6594.6 0.0 860422.3 7100040.0 3867170.4 82.3 82.3 80.8 78.6 6.5
- 25. If Shut Down At End of Report Period, Est'ed Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Cumm.
218850.0 140824.1 0.0 136996.5 0.0 428687771.6 138926550.0 133932224.3 63.3 63.3 58.9 57.3 23.9 Refuelino Outaae scheduled for ADril 2003
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-316 TWO 2-Dec-02 RAF Harris 269-465-5901 MONTH Nov-02 AVERAGE DAILY POWER LEVEL 1090 1106 1096 1090 1096 1093 1095 1098 1101 1097 1098 1093 1100 1098 1098 1098 DAY 11/17/02 11118/02 11/19102 11/20/02 11/21/02 11/22/02 11/23/02 11/24/02 11/25/02 11/26/02 11/27/02 11/28/02 11/29/02 11/30/02 AVERAGE DAILY POWER LEVEL 1098 1095 1098 1100 1104 1099 1107 1100 1099 1097 1103 1109 1103 1110 DAY 11/1/02 11/2/02 11/3/02 11/4/02 11/5/02 11/6/02 11/7/02 11/8/02 11/9/02 11/10/02 11/11/02 11/12/02 11/13/02 11/14/02 11/15/02 11/16/02
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50-316 D.C. Cook Unit 2 December 3, 2002 B. O'Rourke 269-465-5901 lofl UNIT SHUTDOWNS AND POWER REDUCTIONS - November 2002 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO.
DATE TYPE1 HOURS REASON2 REACTOR 3 REPORT NO.
CODE4 CODE5 TO PREVENT RECURRENCE None 1 TYPE:
F: Forced S: Scheduled 2 REASON:
A: Equipment Failure (Explain)
B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain) 3 METHOD:
1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:
Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:
Exhibit I: Same Source