| {{#Wiki_filter:April 14, 2006Carolina Power and Light CompanyATTN:Mr. C. J. GannonVice President - Harris PlantShearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165 | | {{#Wiki_filter:April 14, 2006 Carolina Power and Light Company ATTN: Mr. C. J. Gannon Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| MEETING ANNOUNCEMENT - PUBLIC MEETING -SHEARON HARRIS NUCLEAR POWER PLANT, DOCKET NO. 50-400 | | MEETING ANNOUNCEMENT - PUBLIC MEETING - |
| | SHEARON HARRIS NUCLEAR POWER PLANT, DOCKET NO. 50-400 |
|
| |
|
| ==Dear Mr. Gannon:== | | ==Dear Mr. Gannon:== |
|
| |
|
| This letter confirms the conversation between Mr. David Corlett of your staff and Mr. RandyMusser of this office on April 11, 2006, concerning a Category 1 meeting which has been scheduled for May 23 at 7:00 pm. The meeting notice, which provides additional details, is enclosed. The purpose of the meeting, scheduled at our request, is to discuss the NRC Reactor Oversight Process Annual Assessment of the Shearon Harris Nuclear Power Plant.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC'sdocument system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this meeting, please contact Mr. Son Ninh at (404)562-4532.Sincerely,/RA/Paul E. Fredrickson, ChiefReactor Projects Branch 4 Division of Reactor ProjectsDocket No. 50-400Licensee No. NPF-63cc w/encl: (See page 2) | | This letter confirms the conversation between Mr. David Corlett of your staff and Mr. Randy Musser of this office on April 11, 2006, concerning a Category 1 meeting which has been scheduled for May 23 at 7:00 pm. The meeting notice, which provides additional details, is enclosed. The purpose of the meeting, scheduled at our request, is to discuss the NRC Reactor Oversight Process Annual Assessment of the Shearon Harris Nuclear Power Plant. |
| CP&L2cc w/encl:Chris L. Burton, Manager Performance Evaluation and Regulatory Affairs CPB 9 Carolina Power & Light Company Electronic Mail DistributionRobert J. Duncan IIDirector of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail DistributionEric McCartneyPlant General Manager--Harris PlantProgress Energy Carolinas, Inc.
| | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| Shearon Harris Nuclear Power Plant Electronic Mail DistributionJ. Wayne GurganiousTraining Manager-Harris Plant Progress Energy Carolinas, Inc.
| | Should you have any questions concerning this meeting, please contact Mr. Son Ninh at (404) 562-4532. |
| Harris Energy & Environmental Center Electronic Mail DistributionChristos Kamilaris, ManagerSupport Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail DistributionDavid H. Corlett, SupervisorLicensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail DistributionDavid T. ConleyAssociate General Counsel - Legal Department Progress Energy Service Company, LLC Electronic Mail DistributionJohn H. O'Neill, Jr.Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128Beverly Hall, Acting DirectorDivision of Radiation Protection N. C. Department of Environmental Commerce & Natural Resources Electronic Mail DistributionPeggy ForceAssistant Attorney General State of North Carolina Electronic Mail DistributionPublic Service CommissionState of South Carolina P. O. Box 11649 Columbia, SC 29211Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail DistributionRobert P. GruberExecutive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326Herb Council, ChairBoard of County Commissioners of Wake County
| | Sincerely, |
| | /RA/ |
| | Paul E. Fredrickson, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No. 50-400 Licensee No. NPF-63 cc w/encl: (See page 2) |
|
| |
|
| P. O. Box 550 Raleigh, NC 27602Tommy Emerson, ChairBoard of County Commissioners of Chatham County Electronic Mail DistributionEmail Distribution: (See page 3) | | CP&L 2 cc w/encl: Beverly Hall, Acting Director Chris L. Burton, Manager Division of Radiation Protection Performance Evaluation and N. C. Department of Environmental Regulatory Affairs CPB 9 Commerce & Natural Resources Carolina Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Peggy Force Robert J. Duncan II Assistant Attorney General Director of Site Operations State of North Carolina Carolina Power & Light Company Electronic Mail Distribution Shearon Harris Nuclear Power Plant Electronic Mail Distribution Public Service Commission State of South Carolina Eric McCartney P. O. Box 11649 Plant General Manager--Harris Plant Columbia, SC 29211 Progress Energy Carolinas, Inc. |
| | Shearon Harris Nuclear Power Plant Chairman of the North Carolina Electronic Mail Distribution Utilities Commission c/o Sam Watson, Staff Attorney J. Wayne Gurganious Electronic Mail Distribution Training Manager-Harris Plant Progress Energy Carolinas, Inc. Robert P. Gruber Harris Energy & Environmental Center Executive Director Electronic Mail Distribution Public Staff NCUC 4326 Mail Service Center Christos Kamilaris, Manager Raleigh, NC 27699-4326 Support Services Carolina Power & Light Company Herb Council, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Wake County P. O. Box 550 David H. Corlett, Supervisor Raleigh, NC 27602 Licensing/Regulatory Programs Carolina Power & Light Company Tommy Emerson, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Chatham County Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Email Distribution: (See page 3) |
| | Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr. |
| | Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 |
|
| |
|
| _________________________OFFICERII:DRPSIGNATUREPEF forNAMESNinhDATE04/14/2006 E-MAIL COPY? YESNO YESNO YESNO YESNO YESNO YESNO YESNO
| | _________________________ |
| | OFFICE RII:DRP SIGNATURE PEF for NAME SNinh DATE 04/14/2006 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| PUBLIC MEETING WITH PROGRESS ENERGY CAROLINAS(CAROLINA POWER AND LIGHT COMPANY)FACILITY:Shearon Harris Nuclear Power Plant DOCKET:50-400 DATE & TIME:Tuesday, May 23, 2006, at 7:00 p.m. | | PUBLIC MEETING WITH PROGRESS ENERGY CAROLINAS (CAROLINA POWER AND LIGHT COMPANY) |
| LOCATION:New Horizons Fellowship Annex820 E. Williams St. (Highway 55)Apex, NC 27502PURPOSE:Discuss the NRC Reactor Oversight Process Annual Assessment forthe Shearon Harris Nuclear Power Plant. The Annual Assessment Letter is accessible from the Publicly Available Records (PARS) component of NRC's document system (ADAMS-- ML060610387) orfrom the NRC Web site at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/har_2005q4. | | FACILITY: Shearon Harris Nuclear Power Plant DOCKET: 50-400 DATE & TIME: Tuesday, May 23, 2006, at 7:00 p.m. |
| pdf. The NRC's Policy Statement, "Enhancing Public Participation inNRC Meetings," effective May 28, 2002, applies to this meeting. Thepolicy statement may be found on the NRC Web site, www.nrc.gov | | LOCATION: New Horizons Fellowship Annex 820 E. Williams St. (Highway 55) |
| ,and contains information regarding conduct of NRC meetings.CATEGORY:This is a Category 1 meeting: The public is invited to observe thismeeting and will have an opportunity to communicate with the NRC atthe conclusion of the meeting.NRC OFFICEPARTICIPATING:Region IIOTHERORGANIZATIONS PARTICIPATING:NonePARTICIPANTS:NRC-Region IIP. Fredrickson, Chief, Reactor Projects Branch 4, Division of ReactorProjects R. Musser, Senior Resident Inspector, Shearon Harris Nuclear Power Plant P. O'Bryan, Resident Inspector, Shearon Harris Nuclear Power Plant V. McCree, Director, Division of Reactor SafetyLICENSEE--Shearon Harris Nuclear Power PlantC. Gannon, Site Vice PresidentR. Duncan, Director of Site Operations E. McCartney, Plant General Manager 2MEETINGCONTACT:Son Ninh, NRC, RII(404) 562-4532 son@nrc.gov AUDIO TELE- Not available CONFERENCING VIDEO TELE - Not available CONFERENCE}}
| | Apex, NC 27502 PURPOSE: Discuss the NRC Reactor Oversight Process Annual Assessment for the Shearon Harris Nuclear Power Plant. The Annual Assessment Letter is accessible from the Publicly Available Records (PARS) component of NRC's document system (ADAMS-- ML060610387) or from the NRC Web site at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/har_2005q4. |
| | pdf. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov , |
| | and contains information regarding conduct of NRC meetings. |
| | CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have an opportunity to communicate with the NRC at the conclusion of the meeting. |
| | NRC OFFICE Region II PARTICIPATING: |
| | OTHER None ORGANIZATIONS PARTICIPATING: |
| | PARTICIPANTS: NRC-Region II P. Fredrickson, Chief, Reactor Projects Branch 4, Division of Reactor Projects R. Musser, Senior Resident Inspector, Shearon Harris Nuclear Power Plant P. OBryan, Resident Inspector, Shearon Harris Nuclear Power Plant V. McCree, Director, Division of Reactor Safety LICENSEE--Shearon Harris Nuclear Power Plant C. Gannon, Site Vice President R. Duncan, Director of Site Operations E. McCartney, Plant General Manager |
| | |
| | 2 MEETING Son Ninh, NRC, RII CONTACT: (404) 562-4532 son@nrc.gov AUDIO TELE- Not available CONFERENCING VIDEO TELE - Not available CONFERENCE}} |
|
---|
Category:Letter
MONTHYEARIR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20243012023-05-15015 May 2023 Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22227A0682022-09-0202 September 2022 Alternative to Certain Inservice Testing Requirements in the American Society of Mechanical Engineers Code for Operation and Maintenance for Certain Target Rock Solenoid Valves IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) IR 05000400/20224032022-08-23023 August 2022 Security Baseline Inspection Report 05000400/2022403 ML22126A0082022-08-0909 August 2022 Issuance of Amendment No. 194 Revise Technical Specifications Related to Reactor Protection System Instrumentation P7 IR 05000400/20220022022-08-0505 August 2022 Integrated Inspection Report 05000400/2022002 ML22161B0332022-07-28028 July 2022 Issuance of Amendment No. 193 Regarding Revision of Surveillance Requirements to Remove Shutdown Limitation IR 05000400/20220112022-07-20020 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000400 2022011 IR 05000400/20224022022-06-30030 June 2022 Material Control and Accounting Program Inspection Report 05000400/2022402 (OUO Removed) IR 05000400/20220102022-06-13013 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010 ML22138A4012022-05-26026 May 2022 Project Manager Reassignment ML22101A2822022-05-0606 May 2022 Regulatory Audit Summary Related to the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme IR 05000400/20220012022-05-0404 May 2022 Integrated Inspection Report 05000400/2022001 IR 05000400/20224012022-03-24024 March 2022 Security Baseline Inspection Report 05000400/2022401 ML22020A0072022-03-10010 March 2022 Issuance of Amendment No. 192 Regarding Removal of Extraneous Content and Requirements from the Renewed Facility Operating License and Technical Specifications ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML21351A4722022-02-10010 February 2022 Issuance of Amendment No. 190 Regarding Revision to Containment Spray Nozzle Test Frequency IR 05000400/20210042022-02-0404 February 2022 Integrated Inspection Report 05000400/2021004 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 2024-01-30
[Table view] Category:Meeting Notice
MONTHYEARPMNS20231317, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE)2023-11-21021 November 2023 Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE) PMNS20230561, Annual Assessment Meeting2023-04-26026 April 2023 Annual Assessment Meeting PMNS20230395, Meeting with Duke Energy to Discuss a Planned License Amendment Request (LAR) to Be Submitted Under Risk-Informed Process for Evaluations (RIPE)2023-04-13013 April 2023 Meeting with Duke Energy to Discuss a Planned License Amendment Request (LAR) to Be Submitted Under Risk-Informed Process for Evaluations (RIPE) PMNS20220537, Meeting with Duke Energy to Discuss the Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI)-1912022-06-0202 June 2022 Meeting with Duke Energy to Discuss the Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI)-191 PMNS20220375, Pre-submittal Public Meeting with Duke Energy to Discuss the Proposed License Amendment Request to Revise Surveillance Frequency for Reactor Cooling System Pressurized Isolation Valve2022-04-19019 April 2022 Pre-submittal Public Meeting with Duke Energy to Discuss the Proposed License Amendment Request to Revise Surveillance Frequency for Reactor Cooling System Pressurized Isolation Valve PMNS20220350, Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting2022-04-0404 April 2022 Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting PMNS20210385, and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting2021-04-12012 April 2021 and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting ML16103A2552016-04-14014 April 2016 05/02/2016 Notice of Forthcoming Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson and Shearon Harris Plants (CAC Nos. MF7443 and MF7444) ML15107A4252015-04-17017 April 2015 4/20/2015, Forthcoming Closed Meeting with Duke Energy Progress, Inc. to Discuss Shearon Harris Nuclear Power Plant, Unit 1, Relief Request I3R-15 Revision and Supplement, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspe ML14106A2902014-04-16016 April 2014 Notice of Category 1 Public Meeting Regarding Shearon Harris Nuclear Plant to Discuss NRC Reactor Oversight Process Annual Assessment of 2013 Performance ML14087A0802014-03-28028 March 2014 Notice of Forthcoming Meeting with Duke Energy ML13295A3062013-10-22022 October 2013 Meeting Notice with Duke Energy Carolinas, LLC Discuss the Planned Modifications Related to the Fukushima Flood Hazard Reevaluations for the Sites Operated by Duke Energy Carolinas, LLC ML13162A2962013-06-11011 June 2013 7/9/2013 - Notice of Forthcoming Meeting with Duke Energy, Inc. Re. a Nonconservative Technical Specification Loss of Offsite Power Voltage Setpoint License Amendment Request ML13151A0622013-05-31031 May 2013 Notice of Category 3 Public Meeting to Discuss the NRC Special Inspection on the Reactor Vessel Head Nozzle Repair of Shearon Harris Nuclear Plant, Unit 1 ML13136A0562013-05-16016 May 2013 7/23-24/2013 Notice of Public Meeting Announcement with All Region II Licensees, Initial Examination Writers' Workshop ML13120A1372013-05-0202 May 2013 Notice of Forthcoming Meeting with Duke Energy, Inc. Regarding a Non-Conservative Technical Specification Loss-of-Offsite Power Voltage Setpoint License Amendment Request for Shearon Harris, Unit 1 ML13106A3372013-04-17017 April 2013 Notice of Forthcoming Meeting with Duke Energy, Inc. Concerning the Relocation of the Emergency Operating Facilities ML13094A2602013-04-0404 April 2013 Notice of Meeting with Carolina Power & Light Company to Discuss NRC Reactor Oversight Process Annual Assessment of Shearon Harris Nuclear Plant, Unit 1 ML12300A4032012-10-26026 October 2012 11/8/2012 Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-design-Basis External Events ML12284A4612012-10-12012 October 2012 Forthcoming Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-Design-Basis External Events ML12261A0992012-09-17017 September 2012 10/2/12 - Notice of Forthcoming Public Conference Call with Duke Energy Carolinas Regarding Shearon Harris Nuclear Plant, Unit 1 ML12249A1702012-09-0606 September 2012 Notice of Forthcoming Conference Call Public Meeting with Duke Energy Regarding the Non Conservative Technical Specifications License Amendment Requests for Shearon Harris Nuclear Plant Unit 1 ML12221A2612012-08-0707 August 2012 09/25-26/2012 Noticeo of Meeting Announcement - 2012 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Writers' Workshop ML12213A5172012-07-31031 July 2012 8/24/2012 Harris Meeting Announcement - Category 1 Public Meeting - Regulatory Conference and Predecisional Enforcement Conference ML1207201932012-03-12012 March 2012 Meeting Announcement - Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML11336A1592011-12-0202 December 2011 Notice of Closed Meeting with Carolina Power & Light Company Regarding Shearon Harris Nuclear Plant, Unit 1 (TAC ME6999), the Purpose of the Meeting Is to Discuss the August 22, 2011, Large Break Loss of Coolant Accident Submittal ML1115403882011-06-0202 June 2011 08/02-03/2011 Meeting Announcement - 2011 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Writers Workshop ML1108902092011-03-30030 March 2011 Notice of Meeting with Shearon Harris Nuclear Plant to Discuss Human Improvement Plan and to Introduce New Site Management Team ML1108004872011-03-21021 March 2011 Notice of Meeting with Carolina Power & Light Co. to Discuss NRC Reactor Oversight Process Annual Assessment of the Shearon Harris Nuclear Plant ML1103804972011-02-0808 February 2011 Notice of Forthcoming Preapplication Meeting with Carolina Power & Light Company and Representatives Regarding Shearon Harris Nuclear Plant, Unit 1 ML1015501432010-06-0404 June 2010 08/17-18/2010 Meeting Announcement - 2010 NRC Initial Exam Writers Workshop ML1012305352010-05-0303 May 2010 Notice of Category 1 Public Meeting with Carolina Power & Light Company to Discuss NRC Reactor Oversight Process Annual Assessment of Shearon Harris Nuclear Plant Unit 1 ML1005702002010-02-26026 February 2010 Notice of Closed Meeting with Progress Energy to Observe a Live Test Fire of Mackenzie River Partner'S Remotely Operated Weapon System at the Shearon Harris Nuclear Plant ML0936406952010-01-0707 January 2010 Notice of Meeting with Carolina Power & Light Company to Discuss Requests for Additional Information Associated with Generic Letter 2004-02 ML0918004532009-06-29029 June 2009 Meeting Announcement - Category 2 Public Meeting, 2009 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Development Workshop ML0912708872009-05-0707 May 2009 Notice of Category 1 Public Meeting with Carolina Power & Light Co., to Discuss the NRC Reactor Oversight Process Annual Assessment of Harris Nuclear Plant ML0912708612009-05-0707 May 2009 Notice of Category 1 Public Meeting with Carolina Power & Light and Florida Power Corp., Regarding Brunswick Performance and Organizational Alignment within the Company ML0909900182009-04-10010 April 2009 04/21-22/2009, Notice of Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition the Shearon, Unit 1 and the Oconee, Units 1, 2 and 3 ML0825209362008-09-0808 September 2008 Notice of Public Category 1 Meeting with Carolina Power & Light and Florida Power Corporation Organizational Alignment within the Company ML0819605262008-07-14014 July 2008 Notice of Public Meeting for Shearon Harris on Openness and Transparency of NRC Security Inspection Findings and NRC Assessment of Licensee Security Performance ML0819600282008-07-11011 July 2008 08/05-06/2008-Notice of Meeting - 2008 Us Nuclear Regulatory Commission Initial Examination Development Workshop ML0818406962008-07-0707 July 2008 Meeting with Progress Energy Carolinas, Inc. and Duke Energy Carolinas, LLC, to Discuss the 05/29&30/2008, License Amendment Requests to Transition Shearon Harris, Unit 1, and Oconee, Units 1, 2, & 3 to NFPA Standard 805 ML0816901212008-06-17017 June 2008 Forthcoming Closed Meeting with Progress Energy Carolinas, Inc., to Discuss the May 29, 2008, License Amendment Request (LAR) to Transition the Shearon Harris Nuclear Plant, Unit 1 (Harris) to National Fire Protection Association (Nfpa).. ML0812004952008-04-29029 April 2008 Notice of Public Meeting with Carolina Power and Light to Discuss the NRC Reactor Oversight Process Annual Assessment of Your Shearon Harris Nuclear Plant ML0809303182008-04-0202 April 2008 04/14-16/2007 - Notice of Meeting with Duke Energy and Progress Energy to Discuss Pilot Plant Implementation of National Fire Protection Association Standard 805 ML0806701932008-03-0707 March 2008 Revised Notice of Public Meeting - Shearon Harris Nuclear Power Plant, to Introduce the Site'S New Management Team, and to Present the Plant'S Status and Any New Initiatives ML0805801382008-02-27027 February 2008 Notice of Meeting with Carolina Power and Light Company to Introduce Harris'S New Management Team and to Present the Plant'S Status and Any New Initiatives ML0736010052008-01-14014 January 2008 01/30/2008-Notice of Meeting to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Shearon Harris Nuclear Power Plant Unit 1 ML0735205132007-12-19019 December 2007 01/07-08/2008 Pilot Observation Visit with Duke Energy and Progress Energy Regarding Oconee and Harris Transition to National Fire Protection Association Standard 805 ML0733711662007-12-0303 December 2007 Notice of Meeting with Progress Energy & Duke Energy Regarding Fire Probabilistic Risk Assessment for the Pilot Plants Transitioning to the National Fire Protection Association Standard NFPA 805 2023-04-26
[Table view] |
Text
April 14, 2006 Carolina Power and Light Company ATTN: Mr. C. J. Gannon Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING -
SHEARON HARRIS NUCLEAR POWER PLANT, DOCKET NO. 50-400
Dear Mr. Gannon:
This letter confirms the conversation between Mr. David Corlett of your staff and Mr. Randy Musser of this office on April 11, 2006, concerning a Category 1 meeting which has been scheduled for May 23 at 7:00 pm. The meeting notice, which provides additional details, is enclosed. The purpose of the meeting, scheduled at our request, is to discuss the NRC Reactor Oversight Process Annual Assessment of the Shearon Harris Nuclear Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact Mr. Son Ninh at (404) 562-4532.
Sincerely,
/RA/
Paul E. Fredrickson, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No. 50-400 Licensee No. NPF-63 cc w/encl: (See page 2)
CP&L 2 cc w/encl: Beverly Hall, Acting Director Chris L. Burton, Manager Division of Radiation Protection Performance Evaluation and N. C. Department of Environmental Regulatory Affairs CPB 9 Commerce & Natural Resources Carolina Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Peggy Force Robert J. Duncan II Assistant Attorney General Director of Site Operations State of North Carolina Carolina Power & Light Company Electronic Mail Distribution Shearon Harris Nuclear Power Plant Electronic Mail Distribution Public Service Commission State of South Carolina Eric McCartney P. O. Box 11649 Plant General Manager--Harris Plant Columbia, SC 29211 Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant Chairman of the North Carolina Electronic Mail Distribution Utilities Commission c/o Sam Watson, Staff Attorney J. Wayne Gurganious Electronic Mail Distribution Training Manager-Harris Plant Progress Energy Carolinas, Inc. Robert P. Gruber Harris Energy & Environmental Center Executive Director Electronic Mail Distribution Public Staff NCUC 4326 Mail Service Center Christos Kamilaris, Manager Raleigh, NC 27699-4326 Support Services Carolina Power & Light Company Herb Council, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Wake County P. O. Box 550 David H. Corlett, Supervisor Raleigh, NC 27602 Licensing/Regulatory Programs Carolina Power & Light Company Tommy Emerson, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Chatham County Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Email Distribution: (See page 3)
Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128
_________________________
OFFICE RII:DRP SIGNATURE PEF for NAME SNinh DATE 04/14/2006 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
SUBJECT:
PUBLIC MEETING WITH PROGRESS ENERGY CAROLINAS (CAROLINA POWER AND LIGHT COMPANY)
FACILITY: Shearon Harris Nuclear Power Plant DOCKET: 50-400 DATE & TIME: Tuesday, May 23, 2006, at 7:00 p.m.
LOCATION: New Horizons Fellowship Annex 820 E. Williams St. (Highway 55)
Apex, NC 27502 PURPOSE: Discuss the NRC Reactor Oversight Process Annual Assessment for the Shearon Harris Nuclear Power Plant. The Annual Assessment Letter is accessible from the Publicly Available Records (PARS) component of NRC's document system (ADAMS-- ML060610387) or from the NRC Web site at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/har_2005q4.
pdf. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov ,
and contains information regarding conduct of NRC meetings.
CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have an opportunity to communicate with the NRC at the conclusion of the meeting.
NRC OFFICE Region II PARTICIPATING:
OTHER None ORGANIZATIONS PARTICIPATING:
PARTICIPANTS: NRC-Region II P. Fredrickson, Chief, Reactor Projects Branch 4, Division of Reactor Projects R. Musser, Senior Resident Inspector, Shearon Harris Nuclear Power Plant P. OBryan, Resident Inspector, Shearon Harris Nuclear Power Plant V. McCree, Director, Division of Reactor Safety LICENSEE--Shearon Harris Nuclear Power Plant C. Gannon, Site Vice President R. Duncan, Director of Site Operations E. McCartney, Plant General Manager
2 MEETING Son Ninh, NRC, RII CONTACT: (404) 562-4532 son@nrc.gov AUDIO TELE- Not available CONFERENCING VIDEO TELE - Not available CONFERENCE