ML080670193

From kanterella
Jump to navigation Jump to search
Revised Notice of Public Meeting - Shearon Harris Nuclear Power Plant, to Introduce the Site'S New Management Team, and to Present the Plant'S Status and Any New Initiatives
ML080670193
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/07/2008
From: Randy Musser
NRC/RGN-II/DRP/RPB4
To: Duncan R
Carolina Power & Light Co
References
Download: ML080670193 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 March 7, 2008 Carolina Power and Light Company ATTN: Mr. Robert J. Duncan, II Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165

SUBJECT:

REVISED MEETING ANNOUNCEMENT - PUBLIC MEETING SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50 - 400

Dear Mr. Duncan:

This letter confirms the telephone conversation between Mr. Dave Corlett of your staff and myself of this office on March 5, 2008, concerning a Category 1 meeting which has been scheduled for March 27, 2008 at 1:00 p.m. (EDT). The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting, scheduled at your request, is for Harris Nuclear Power Plant to introduce the sites new management team, and to present the plants status and any new initiatives. This letter supersedes the letter that was sent on February 27, 2008.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 562-4603.

Sincerely,

/RA/

Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 50-400 License No.: NPF-63

Enclosure:

As stated cc w/encl.: (See page 2)

OFFICE RII:DRP RII:DRP SIGNATURE GJW /RA/ RAM /RA/

NAME GWilson RMusser DATE 03/06/2008 03/07/2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO DPC 2 cc w/encl: Public Serivce Commission Paul Fulford State of South Carolina Manager P.O. Box 11649 Performance Evaluation and Regulatory Columbia, SC 29211 Affairs PEB5 Carolina Power & Light Company Herb Council Electronic Mail Distribution Chair Board of County Commissioners of Wake Chris L. Burton County Director Site Operations P.O. Box 550 Carolina Power & Light Company Raleigh, NC 27602 Shearon Harris Nuclear Power Plant Electronic Mail Distribution Tommy Emerson Chair J. Wayne Guganious Board of County Commissioners of Training Manager Chatham County Harris Electronic Mail Distribution Progress Energy Carolinas, Inc.

Electronic Mail Distribution Thomas J. Natale Manager Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett Supervisor Licensing/Regualtory Programs Carolina Power & Light Company Electronic Mail Distribution David T. Conley Associate General Counsel Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washingtion, DC 20037-1128 Beverly Hall Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution

DPC 3 Letter to Robert J. Duncan from Randall A. Musser dated March 7, 2008

SUBJECT:

REVISED MEETING ANNOUNCEMENT - PUBLIC MEETING SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50 - 400 Distribution w/encl:

Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS L. Regner, NRR L. Slack, RII RIDSNRRDIRS OE Mail PUBLIC

SUBJECT:

PUBLIC MEETING WITH PROGRESS ENERGY FACILITY: Shearon Harris Nuclear Plant DOCKETS: 50-400 DATE & TIME: Thursday, March 27, 2008, 1:00 p.m. (EDT)

LOCATION: Sam Nunn Atlanta Federal Center, 23T85 61 Forsyth Street, SW Room 24T20 Atlanta, GA 30303 PURPOSE: The purpose of this meeting is to allow Harris Nuclear Power Plant to introduce the sites new management team and to present the plants status and any new initiatives. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov and contains information regarding visitors and security.

CATEGORY: This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

NRC OFFICE Region II (RII)

PARTICIPATING:

OTHER None ORGANIZATIONS PARTICIPATING:

PARTICIPANTS: NRC V. McCree, Acting Regional Administrator, Region II (RII)

J. Shea, Division Director, Division of Reactor Projects (DRP), RII R. Musser, Chief, Reactor Projects Branch 4, DRP, RII LICENSEE Chris Burton, Director - Site Operations, Harris Nuclear Power Plant (HNP)

Kelvin Henderson, Plant General Manager, (HNP)

John Warner, Operations Manager, (HNP)

John Dufner, Maintenance Manager, (HNP)

John Dills, Outage and Scheduling Manager, (HNP)

Sean O'Connor, Engineering Manager, (HNP)

Dave Corlett, Licensing Supervisor, (HNP)

MEETING Randall A. Musser CONTACT: (404) 562-4603 rxm1@nrc.gov AUDIO TELE- Not Available CONFERENCING VIDEO TELE- Not Available CONFERENCING Enclosure