Notice of Meeting with Carolina Power & Light Company to Discuss NRC Reactor Oversight Process Annual Assessment of Shearon Harris Nuclear Plant, Unit 1
ML13094A260
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 04/04/2013
From: Randy Musser
NRC/RGN-II/DRP/RPB4
To: Hamrick G
Carolina Power & Light Co
References
Download: ML13094A260 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 4, 2013 Mr. George Hamrick, Vice President Carolina Power and Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO.

50-400

Dear Mr. Hamrick:

This letter confirms a Category 1 public meeting which has been scheduled for May 20, 2013, at 5:00 p.m. (EDT). The enclosed meeting notice provides additional details. The purpose of the meeting is to discuss the NRC Reactor Oversight Process Annual Assessment of your Shearon Harris Nuclear Plant.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4603.

Sincerely,

/RA/

Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 50-400 License No.: NPF-63

Enclosure:

Meeting Notice cc w/encl.: (See page 2)

__ML13094A260_______________ XSUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP SIGNATURE RXM:/RA/

NAME RMusser DATE 4/4/2013 E-MAIL COPY? YES NO YES NO G. Hamrick 2 cc w/encl:

Brian Bernard David H. Corlett Manager, Nuclear Services and EP Supervisor Nuclear Protective Services Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution Electronic Mail Distribution Brian C. McCabe David T. Conley Manager, Nuclear Oversight Senior Counsel Shearon Harris Nuclear Power Plant Legal Department Progress Energy Progress Energy Electronic Mail Distribution Electronic Mail Distribution George T. Hamrick Donna B. Alexander Vice President Manager, Nuclear Regulatory Affairs (interim)

Carolina Power and Light Company Progress Energy Shearon Harris Nuclear Power Plant Electronic Mail Distribution Electronic Mail Distribution John H. O'Neill, Jr.

Lara S. Nichols Shaw, Pittman, Potts & Trowbridge Deputy General Counsel 2300 N. Street, NW Duke Energy Corporation Washington, DC 20037-1128 Electronic Mail Distribution Joseph W. Donahue M. Christopher Nolan Vice President Director - Regulatory Affairs Nuclear Oversight General Office Progress Energy Duke Energy Corporation Electronic Mail Distribution Electronic Mail Distribution W. Lee Cox, III Robert J. Duncan II Section Chief Senior Vice President Radiation Protection Section Progress Energy N.C. Department of Environmental Commerce &

Electronic Mail Distribution Natural Resources Electronic Mail Distribution Sean T. O'Connor Manager, Support Services Public Service Commission Shearon Harris Nuclear Power Plant State of South Carolina Electronic Mail Distribution P.O. Box 11649 Columbia, SC 29211 Donald L. Griffith Training Manager Chairman Shearon Harris Nuclear Power Plant North Carolina Utilities Commission Progress Energy Electronic Mail Distribution Electronic Mail Distribution R. Keith Holbrook (cc:w/encl continued next page)

Manager, Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution

G. Hamrick 3 cc:w/encl continued Terrence E. Slake Manager Nuclear Plant Security Shearon Harris Nuclear Power Plant Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 Ernest J. Kapopoulos Jr.

Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Chair Board of County Commissioners of Chatham County P.O. Box 1809 Pittsboro, NC 27312 Senior Resident Inspector U.S. Nuclear Regulatory Commission Shearon Harris Nuclear Power Plant 5421 Shearon Harris Rd New Hill, NC 27562-9998

G. Hamrick 4 Letter to G. Hamrick from Randall A. Musser dated April 4, 2013

SUBJECT:

MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO.

50-400 Distribution w/encl:

C. Evans, RII EICS (Part 72 Only)

L. Douglas, RII EICS (Linda Douglas)

OE Mail (email address if applicable)

RIDSNRRDIRS PUBLIC RidsNrrPMShearonHarris Resource Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS

SUBJECT:

PUBLIC MEETING WITH CAROLINA POWER AND LIGHT COMPANY FACILITY: Shearon Harris Nuclear Plant DOCKET: 50-400 DATE & TIME: Monday, May 20, 2013 Open House and Poster Session 5:00p.m. - 6:30p.m.

Public Meeting Presentation, followed by a question and answer session 6:30p.m. - 7:30p.m.

LOCATION: Holly Springs Cultural Center 300 West Ballentine Street Holly Springs, NC 27540 PURPOSE: The purpose of the meeting is to discuss the NRC Reactor Oversight Process Annual Assessment of Shearon Harris Nuclear Plant, Unit 1.

The Annual assessment Letter is accessible from the Publicly Available Records (PARS) component of NRCs document system (ADAMS)

(ML13063A223) or http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/rob_2012q4.pdf The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC web site, www.nrc.gov and contains information regarding visitors and security.

CATEGORY: This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, ore need this meeting notice or other information from the meeting in another format (e.g., Braille, large print) please notify the NRCs meeting contact listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

NRC OFFICE PARTICIPATING: Region II PARTICIPANTS: NRC W. Jones, Deputy Director, Division of Reactor Projects R. Musser, Chief, Construction Inspection Branch 3 J. Austin, Sr. Resident Inspector, Harris P. Lessard, Resident Inspector, Harris Enclosure

2 MEETING Randall A. Musser CONTACT: 404-997-4603 randy.musser@nrc.gov AUDIO TELE-CONFERENCING: Not available VIDEO TELE-CONFERENCING: Not available Enclosure