Meeting Announcement - Public Meeting - Shearon Harris Nuclear Power Plant
ML061040385
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 04/14/2006
From: Fredrickson P
NRC/RGN-II/DRP/RPB4
To: Gannon C
Carolina Power & Light Co
References
Download: ML061040385 (5)


Text

April 14, 2006 Carolina Power and Light Company ATTN: Mr. C. J. Gannon Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165

SUBJECT:

MEETING ANNOUNCEMENT - PUBLIC MEETING -

SHEARON HARRIS NUCLEAR POWER PLANT, DOCKET NO. 50-400

Dear Mr. Gannon:

This letter confirms the conversation between Mr. David Corlett of your staff and Mr. Randy Musser of this office on April 11, 2006, concerning a Category 1 meeting which has been scheduled for May 23 at 7:00 pm. The meeting notice, which provides additional details, is enclosed. The purpose of the meeting, scheduled at our request, is to discuss the NRC Reactor Oversight Process Annual Assessment of the Shearon Harris Nuclear Power Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact Mr. Son Ninh at (404) 562-4532.

Sincerely,

/RA/

Paul E. Fredrickson, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No. 50-400 Licensee No. NPF-63 cc w/encl: (See page 2)

CP&L 2 cc w/encl: Beverly Hall, Acting Director Chris L. Burton, Manager Division of Radiation Protection Performance Evaluation and N. C. Department of Environmental Regulatory Affairs CPB 9 Commerce & Natural Resources Carolina Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Peggy Force Robert J. Duncan II Assistant Attorney General Director of Site Operations State of North Carolina Carolina Power & Light Company Electronic Mail Distribution Shearon Harris Nuclear Power Plant Electronic Mail Distribution Public Service Commission State of South Carolina Eric McCartney P. O. Box 11649 Plant General Manager--Harris Plant Columbia, SC 29211 Progress Energy Carolinas, Inc.

Shearon Harris Nuclear Power Plant Chairman of the North Carolina Electronic Mail Distribution Utilities Commission c/o Sam Watson, Staff Attorney J. Wayne Gurganious Electronic Mail Distribution Training Manager-Harris Plant Progress Energy Carolinas, Inc. Robert P. Gruber Harris Energy & Environmental Center Executive Director Electronic Mail Distribution Public Staff NCUC 4326 Mail Service Center Christos Kamilaris, Manager Raleigh, NC 27699-4326 Support Services Carolina Power & Light Company Herb Council, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Wake County P. O. Box 550 David H. Corlett, Supervisor Raleigh, NC 27602 Licensing/Regulatory Programs Carolina Power & Light Company Tommy Emerson, Chair Shearon Harris Nuclear Power Plant Board of County Commissioners Electronic Mail Distribution of Chatham County Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Email Distribution: (See page 3)

Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128

OFFICE RII:DRP SIGNATURE PEF for NAME SNinh DATE 04/14/2006 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

SUBJECT:

PUBLIC MEETING WITH PROGRESS ENERGY CAROLINAS (CAROLINA POWER AND LIGHT COMPANY)

FACILITY: Shearon Harris Nuclear Power Plant DOCKET: 50-400 DATE & TIME: Tuesday, May 23, 2006, at 7:00 p.m.

LOCATION: New Horizons Fellowship Annex 820 E. Williams St. (Highway 55)

Apex, NC 27502 PURPOSE: Discuss the NRC Reactor Oversight Process Annual Assessment for the Shearon Harris Nuclear Power Plant. The Annual Assessment Letter is accessible from the Publicly Available Records (PARS) component of NRC's document system (ADAMS-- ML060610387) or from the NRC Web site at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/har_2005q4.

pdf. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov ,

and contains information regarding conduct of NRC meetings.

CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have an opportunity to communicate with the NRC at the conclusion of the meeting.

NRC OFFICE Region II PARTICIPATING:

OTHER None ORGANIZATIONS PARTICIPATING:

PARTICIPANTS: NRC-Region II P. Fredrickson, Chief, Reactor Projects Branch 4, Division of Reactor Projects R. Musser, Senior Resident Inspector, Shearon Harris Nuclear Power Plant P. OBryan, Resident Inspector, Shearon Harris Nuclear Power Plant V. McCree, Director, Division of Reactor Safety LICENSEE--Shearon Harris Nuclear Power Plant C. Gannon, Site Vice President R. Duncan, Director of Site Operations E. McCartney, Plant General Manager

2 MEETING Son Ninh, NRC, RII CONTACT: (404) 562-4532 son@nrc.gov AUDIO TELE- Not available CONFERENCING VIDEO TELE - Not available CONFERENCE