IR 05000400/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010
ML22161A979
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 06/13/2022
From: James Baptist
Division of Reactor Safety II
To: Maza K
Duke Energy Carolinas
References
IR 2022010
Download: ML22161A979 (17)


Text

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000400/2022010

Dear Ms. Maza:

On April 29, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Shearon Harris Nuclear Power Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Shearon Harris Nuclear Power Plant.

June 13, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket No. 05000400 License No. NPF-63

Enclosure:

As stated

Inspection Report

Docket Number:

05000400

License Number:

NPF-63

Report Number:

05000400/2022010

Enterprise Identifier:

I-2022-010-0035

Licensee:

Duke Energy Carolinas, LLC

Facility:

Shearon Harris Nuclear Power Plant

Location:

New Hill, NC.

Inspection Dates:

April 03-April 29, 2022

Inspectors:

T. Fanelli, Senior Reactor Inspector

M. Schwieg, Senior Reactor Inspector

J. Zudans, Contractor

Approved By:

James B. Baptist, Chief

Engineering Br 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Shearon Harris Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Valves Anomalous Behavior Not Identified in Corrective Action Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-01 Open/Closed

[H.8] -

Procedure Adherence 71111.21N.02 The inspectors identified a GREEN finding and an associated NCV of 10 CFR 50 Appendix B Criterion XVI, Corrective Action, for the licensee's failure to identify potential degradation to a containment isolation valve in the corrective action program (CAP).

Not Addressing Containment Isolation Valve Closure Requirements in Design Documents Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-02 Open/Closed None (NPP)71111.21N.02 The NRC identified a GREEN finding and associated NCV of 10 CFR 50 Appendix B,

Criterion III for the licensees failure to address containment isolation valve closure requirements to prevent leakage.

Failure to correct nonconformance's with 10 CFR 50.55a(b)(3)(ii)

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-03 Open/Closed None (NPP)71111.21N.02 The inspectors identified a GREEN finding and an associated NCV of 10 CFR 50 Appendix B Criterion XVI, Corrective Action, for the licensee's failure to correct nonconformance with 10 CFR 50.55a(b)(3)(ii).

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from [enter dates].

(1) URI 05000400/2021010-01, Treatment of Class 1E interfaces and interlocks with the Turbine Trip System Design

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a determined whether the sampled POVs are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases Specific Guidance b.

determined whether the sampled POVs are capable of performing their design-basis functions c.

determined whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions d.

evaluate maintenance activities including a walkdown of the sampled POVs (if accessible)

(1)1CT-102 MOV Containment Sump to CS Pump "B" Isolation Valve (CIV)

(2)1MS-82 AOV Main Steam Isolation Valve (MSIV) for MS Header "B" (CIV)

(3)1AF-19 HOV AFWP "1A" Pressure Control Valve (4)1CC-167 MOV CCW From RHR Heat Exchanger "B" Outlet Isolation Valve (5)1CT-50 MOV Containment Spray Pump "A" Discharge to Nozzles Isolation Valve (CIV)

(6)1BD-30 AOV SG "B" Blowdown Isolation Valve (CIV)

(7)1SI-4 MOV Boron Injection Tank (BIT) Outlet Isolation Valve (CIV)

(8)1MS-62 HOV MS Line "C" PORV (CIV)

(9)1CS-11 AOV Letdown Isolation (CIV)

INSPECTION RESULTS

Valves Anomalous Behavior Not Identified in Corrective Action Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-01 Open/Closed

[H.8] -

Procedure Adherence 71111.21N.02 The inspectors identified a GREEN finding and an associated NCV of 10 CFR 50 Appendix B Criterion XVI, Corrective Action, for the licensee's failure to identify potential degradation to a containment isolation valve in the corrective action program (CAP).

Description:

On 5/3/2021, after a valve packing replacement, Work Order (WO) 20380548 performed a post maintenance diagnostic test for Air Operated Valve (AOV) 1BD-30, Steam Generator "B" Blowdown Containment Isolation Valve (CIV). The test showed high and uneven friction anomalies indicating an issue with the valve. In addition, the diagnostic test identified a potential binding anomaly at the beginning of the closing stroke (the CIV safety function). The binding anomaly prevented a continuous and smooth closure of the valve. A qualified AOV engineer evaluated the test on 5/13/2021 and noted that the margin had been reduced significantly due to the high friction but remained acceptable. No further investigations into these anomalies were performed. No Corrective Action or Work Request (WR) was initiated until WR 20223816 was issued 4/7/2022. Procedure TMM-134, "Post Test Evaluation of AOV Diagnostic Test Data," Rev. 3, requires initiation of WR as needed to correct anomalies.

Corrective Actions: The licensee entered the nonconformance into the CAP and identified a second corrective action deficiency with anomalies associated with valve 1CS-231 in Action Request (AR) 02423878

Corrective Action References: NCR 2423818 and AR 02423878

Performance Assessment:

Performance Deficiency: The failure to identify anomalous behavior that could degrade the safety function of containment isolation valve performance in the corrective action program was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, the anomalous behavior was on the beginning of the closure stoke and could worsen, thus degrading the valve effectiveness to perform its safety function to close and isolate containment.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the finding was determined to be of very low safety significance GREEN because the finding is a deficiency affecting the design or qualification of a mitigating SSC, but the SSC maintains its operability or PRA functionality Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures, and work instructions. The licensee failed to identify anomalous valve behavior completely and in a timely manner in accordance with evaluation procedure TMM-134.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, states, in part, that Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.

Contrary to the above, since 5/3/2021, deviant valve diagnostic anomalies were not promptly identified in CAP to be corrected.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Not Addressing Containment Isolation Valve Closure Requirements in Design Documents Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-02 Open/Closed None (NPP)71111.21N.02 The NRC identified a GREEN finding and associated NCV of 10 CFR 50 Appendix B, Criterion III for the licensees failure to address containment isolation valve closure requirements to prevent leakage.

Description:

FSAR, Section 6.2.4.2.3, Valve Operability, states, in part, that, The valve types utilized for containment isolation service are designs which provide rapid closure and near zero leakage. Therefore, essentially no leakage is anticipated through the containment isolation valves when in closed position. The licensing basis for the plant exempted approximately 36 CIV from 10 CFR 50, Appendix J, testing requirements, based on the application of a water seal for 30 days after a design basis event. However, these valves were not exempted from the rapid closure and near zero leakage requirement. The licensee program did not ensure that the valve seat stresses necessary for near zero leakage were determined and met. In addition, test control documents and subsequent corrective action documents that identified degradation on the disc and seat did not evaluate for leakage degradation. The documents specified that the valves did not need to meet any leak rate requirements because of their exemption from 10 CFR 50 Appendix J, testing requirements. The inspectors identified that the degradation could affect the valve leakage.

The valves evaluated in the inspection sample included the Boron Injection Tank (BIT) output containment isolation valves 1SI-3 and 1SI-4, Containment Sump valve 1CT-102, and Blowdown isolation valve 1BD-30. A site extent of condition is being performed to determine how many CIVs were affected by this issue. The inspectors noted that not ensuring that near zero leakage requirements were addressed in the valve program allowed degradation affecting leakage requirements to go unaddressed.

Corrective Actions: The licensee entered this issue into the CAP and is performing an extent of condition.

Corrective Action References: AR 2425558

Performance Assessment:

Performance Deficiency: The failure to ensure that the near zero leakage requirements for CIVs continued to be met was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because, if left uncorrected, it would have the potential to lead to a more significant safety concern. The containment isolation function of these valves was not ensured in design control and test control documents for their associated design basis events leading to the failure to address potential degradation affecting their safety functions.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the finding was determined to be of very low safety significance GREEN because the finding is a deficiency affecting the design or qualification of a mitigating SSC, but the SSC maintains its operability or PRA functionality Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion III, states, in part, that Measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in § 50.2 and as specified in the license application, for those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions.

Contrary to the above, since 4/28/2000, the site failed to assure that applicable regulatory requirements and design basis, as defined in § 50.2 and as specified in the license application, for containment isolation valves to which this appendix applies were correctly translated into specifications, drawings, procedures, and instructions. Specifically, design documents for valve capability did not address the containment isolation valve function.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to correct nonconformance's with 10 CFR 50.55a(b)(3)(ii)

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000400/2022010-03 Open/Closed None (NPP)71111.21N.02 The inspectors identified a GREEN finding and an associated NCV of 10 CFR 50 Appendix B Criterion XVI, Corrective Action, for the licensee's failure to correct nonconformance with 10 CFR 50.55a(b)(3)(ii).

Description:

Differential pressure testing results for 1SI-3 and1SI-4 showed signs of degradation and instability of valve factor performance, which could affect their safety injection function and their near zero leakage design requirement for CIVs. The tests demonstrated that the valves were not in conformance with 10 CFR 50.55a(b)(3)(ii) and this nonconformance was not recognized following these tests. The degradation was recognized and placed in the in the CAP as part of the Motor Operated Valve (MOV) testing program in 2006. It was identified that seat lapping has not been successful in achieving low VFC [Valve Factor Close] & VFO [Valve Factor Open]. Consideration needs to be given to replacing the valve. AR# 193559 is tracking the resolution of this issue. Instead of tracking the resolution of the issue, these valves were incorrectly classified as JOG Class A (based on these tests),not requiring further testing. This was contrary to the site MOV program given the identified degradation. The valves have not been retested under differential pressure since 2006. In this case, the licensee found MOVs that do not have a stable VF and are not consistent with the 95% approach used by the approved MOV program and Joint owners Group (JOG) data used for MOV program.

Corrective Actions: The licensee entered this into the CAP and is performing an extent of condition with other valves of the same type.

Corrective Action References: AR 2425557

Performance Assessment:

Performance Deficiency: The failure to correct nonconformance's with 10 CFR 50.55a(b)(3)(ii)was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. The identified degradation could lead to affect the effectiveness of the Safety Injection system to perform its safety functions as well as their CIV functions. These valves were identified to be used in approximately 39 procedures associated with the safe operation of the plant.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the finding was determined to be of very low safety significance GREEN because the finding is a deficiency affecting the design or qualification of a mitigating SSC, but the SSC maintains its operability or PRA functionality.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, states, in part, that Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformance's are promptly identified and corrected.

Contrary to the above, since 5/3/2006, the site failed to correct valve factor degradation in Safety Injection Valves that prevented them from meeting 10 CFR 50.55a(b)(3)(ii).

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 29, 2022, the inspectors presented the design basis assurance inspection (programs) inspection results to Kim Maza and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

14.SI-0017 DBR

Mechanical Analysis and Calculation for Gate Valve 1SI-4

Bit Outlet Isolation (CIV)

04/28/2021

CC-0009

Mechanical Analysis and Calculation for Gate Valve 1CC-

167 RHR Heat Exchanger B Isolation

CC-0009

JOG MOV EVALUATION REPORT 1CC-167 (HNP-1)

CT-0049

Mechanical Analysis and Calculation for Gate valve 1CT-50

Containment Spray Pump Discharge (CIV)

DC-129

Weak Link and Seismic Analysis Report for Velan Valve 12

Inch Class 150 Carbon Steel Bolted Bonnet Motor Operated

Gate Valve

EQDP-0311

Main Steam PORV Operator

HNP-15-0073

GL 89-10 MOVs 1CC-147 & 1CC-167 are Undersized

10/20/2015

HNP-APPJ

Containment Leakage Rate Testing Program

HNP-C-EQ-1196

Weak Link Analysis of Westinghouse Valves 1S1-3 and

1S1-4

2/14/2001

HNP-C/EO-1203

Weak Link Analysis of Velan Valves 1CC-147 and 1CC-167

HNP-IST-004

HNP IST Program Plan - 4th Interval

HNP-M/MECH-

23

Determination of MOV Rate of Loading Factors

HNP-M/MECH-

28

AOV System Level Calculations for Steam Generator

Blowdown Valves (1BD-1, 1BD-11, 1BD-20,1BD-30, 1BD-

39, 1BD-49)

Calculations

TMM-134

Analysis of Category 1(2) AOV Diagnostic Data, Sliding

Stem Valve with Spring/Diaphragm Actuator Spring to

Close Configuration, 1BD-30

05/03/2021

Corrective Action

Documents

AR 193559-05

1SI-2 and 1SI-4 Increase Valve Factor /Margin after Seat

lap

08/31/2006

1364-003059

IN CS 150 lb MO Gate Valve ASME CL 3 12-GM32SB

1364-099223 SHT

1-2

PORV EHO Assembly Drawing

1364-4383 SO1

Main Steam Power Operated Relief Valves Details

71111.21N.02

Drawings

1364-4384

Main Steam Power Operated Relief Valves Details

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5-S-0542

SIMPLIFIED FLOW DIAGRAM MAIN STEAM SYSTEM

UNIT 1

5-S-0550

SFD CONT SPRAY SYSTEM UNIT 1

CAR 2166 B-401

Unit No.1 Control Wiring Diagram

CAR 2166-B-060

Miscellaneous Electrical Details & Notes Sheet 42

CAR-2165 G-

0050

Flow Diagram Containment Spray System Unit 1

CF1L-2165

Simplified Flow Diagram Component Cooling Water

System, Sheet 2

CPL-2165-S-1324

Simplified Flow Diagram RHR System Unit 1

EC 0000298557

Wedge, Valve, Gate, 12 inch, Velan, MH/FS

EC 295206

Obsolete MS PORV EHO Replacement

EC 295206

Mod Test Plan, AD-EG-ALL-1155, Attachment 3

Engineering

Changes

ESR 99-00009

RF-09, MOV Modifications for HHSI, Cont. Spray and HHSI

2/02/1999

1CS-11

AOV Setup Datasheet

2/15/2022

1CS-11

Analysis of Category 2 & 3 AOV Diagnostic Data

04/19/2015

1SI-4 DP Test 4-

2-06

Rising Stem Dynamic Test Analysis

04/12/2006

1SI-4 DP Test 5-

4-06

Rising Stem Dynamic Test Analysis

05/04/2006

1SI-4

PTE_2015_04_05

MOV POST-TEST DATA REVIEW WORKSHEET

04/05/2015

1SI-4

PTE_2021_04_15

MOV POST-TEST DATA REVIEW WORKSHEET

04/25/2021

9500335

Document Review of Pressure-Locking Scenario for

Containment

04/04/1995

9600054

Valve Press Lock/Thermal Bind Evaluations Reqd by 95-07

2/11/1996

CT-0054

MECHANICAL ANALYSIS AND CALCULATION FOR

GATE VALVE 1CT-102 CONTAINMENT SUMP TO

CONTAINMENT SPRAY PUMP

E5-0001

ANALYSIS OF MOTOR OUTPUT TORQUE FOR AC

MOTOR OPERATED VALVES

Engineering

Evaluations

HNP-M-Mech-

21

DETERMINATION OF MOV VALVE FACTORS

R6

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HNP-M/MECH-

21

AOV COMPONENT LEVEL CALCULATION FOR MAIN

STEAM ISOLATION VALVES (MSIVS)

HNP-M/MECH-

250

DESIGN BASIS DIFFERENTIAL PRESSURE REPORT

FOR MOV'S IN THE CONTAINMENT SPRAY SYSTEM

HNP-M/MECH-

252

DESIGN BASIS DIFFERENTIAL PRESSURE REPORT

FOR MOV'S IN THE LOW HEAD SAFETY INJECTION &

RHR SYSTEM

OST-1072

1CS-11 Last IST RPI

05/13/2021

OST-1865

CVCS/SI System Operability Cold Shutdown/Refueling

Interval Mode 4-5-6 Or Defueled

08/13/2021

RH-0017

JOG MOV EVALUATION REPORT 1RH-063

741918

50.59 Screening for EC 95206

99-1264

50.59 Screening for ESR 99-00009

AOQG OUT-TUR

Harris Nuclear Plant (HNP) Auxiliary Operator Outside and

Turbine Building Qualification Guide

CAR-SH-M-056

Main Steam Power Operated Relief Valve

DBD-002

Piping Stress Analysis

DBD-1000-V01

Harris Nuclear Plant Environmental Qualification Design

Basis Document

DBD-103

Chemical & Volume Control System Boron Thermal

Regeneration System Boron Recycle System

DBD-104

Safety Injection System

DBD-106

Containment Spray System

DBD-108

Containment Isolation System

DBD-125

Steam Generator, Main Steam, Extraction Steam, Steam

Dump and Auxiliary Steam System

DBD-126

Steam Generator Blowdown System Steam Generator

Blowdown System Steam Generator Chemical Addition

System

DBD-131

Component Cooling Water System

EPRI TR-103237

- R1 - T1

EPRI MOV Performance Prediction Program

Miscellaneous

MA26430

Detailed Complete Functional Acceptance Test Procedure,

PORV Modulating Actuator MD26420, EC 95206

F

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VM-FBG

ACTUATORS, HYDRAMOTOR

AD-EG-ALL-1415

Motor Operated Valve Performance Prediction, Actuator

Settings and Diagnostic Test Data

AD-EG-ALL-1431

Operated Valve Scope and Characterization

AD-EG-ALL-1432

Air Operated Valve Design Basis Review

AD-EG-ALL-1433

Air Operated Valve Testing Requirements

CM-M0186

Main Steam Power Operated Relief Valve (PORV) Operator

Fill and Bleed

EOP-ECA-0.0

LOSS OF ALL AC POWER

ISI-801

Inservice Testing of Valves

ISI-802

Inservice Testing of Pressure Relief Devices

OP-126

Main Steam, Extraction Steam and Steam Dump Systems

OP-137

AUXILIARY FEEDWATER SYSTEM

OST-1046

Main Steam Isolation Valve with Remote Position Indication

Operability Test Quarterly Interval Mode 3 to 5

OST-1068

Containment Isolation Valve Remote Position Indication

Test Two Year Interval Modes 5, 6

OST-1077

Auxiliary Feedwater Valves Operability Test Quarterly

Interval Mode 4-5-6

OST-1087

MOTOR DRIVEN AUXILIARY FEEDWATER PUMPS FULL

FLOW TEST QUARTERLY INTERVAL

MODE 1

OST-1104

Containment Isolation Inservice Inspection Valve Test

Quarterly Interval Modes 1-6

OST-1118

Containment Spray Operability Train A Quarterly Interval

Modes 1-4

OST-1129

CONTAINMENT SPRAY SYSTEM ISI VALVE TEST

QUARTERLY INTERVAL MODES 5 AND 6

OST-1191

Steam Generator PORV and Block Valve Operability Test

Quarterly Interval Modes 1-4

OST-1316

Component Cooling Water System Operability (Pump 1C-

SAB In Service) Quarterly Interval Modes1-4

Procedures

OST-1803

CONTAINMENT SUMP VISUAL INSPECTION 18 MONTH

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

INTERVAL MODE 5

OST-1839

Component Cooling Water Valve Remote Position

Indication Test Two Year Interval Modes 1-6

PD-EG-ALL-1430

Air Operated Valve Program

PLP-112

MOTOR OPERATED VALVE PROGRAM

PLP-400

Post Maintenance Testing

PM-I0054

Air Operated Valve Diagnostic Testing

TE-EG-ALL-1413

MOV Design Database Control, Calculation and Diagnostic

Test Instruction Development and Data Evaluation/Trending

2038486-05

MOV 1CT-50 Post Test Data Review Worksheet

05/16/2012

13321262-01

MOV 1CT-50 Post Test Data Review Worksheet

04/24/2015

13321262-06

Perform MOV PVT and PM -M0014 for 1CT-50

04/10/2015

13352259

M, 1AF-19:002, Hydromotor Actuator Long Term Reliability

04/03/2014

13352259

I, PIC-I058, Replace Hydromotor Actuator 1AF-19

04/04/2014

13366092-07

lCS-11, As Left Diagnostic Testing

04/23/2015

13484301-03

DUKE Nuclear MOV Program MOV Post-Test Data Review

Worksheet, 1CC-167

01/30/2017

13484301-03

MNT-NGGC-00 10,1CC-167, As Left Diagnostic Test

01/30/2017

20374172-01

1MS-62, Steam Leak Through Leakoff Line

2/31/2019

20380548

I, FT, PM-I0054, 1BD-30:006, As-Left AOV Diagnostic Test

05/20/2021

20394523-01

I, 1SI-4:002, MOV PVT AND PM-M0014

4/25/2021

Work Orders

2197059-03

DUKE Nuclear MOV Program MOV Post-Test Data Review

Worksheet, 1CC-167

06/17/2014