April 25, 2023

Title:

Shearon Harris Nuclear Power Plant Annual Assessment Meeting Date(s) and Time(s): May 17, 2023, 06:00 PM to 07:00 PM ET Location: Other, New Hill Community Center 3101 New Holleman Rd.

New Hill, NC Category: This is an Information Meeting with a Question and Answer Session. The purpose of this meeting is for the NRC staff to meet directly with individuals to discuss regulatory and technical issues. Attendees will have an opportunity to ask questions of the NRC staff or make comments about the issues discussed throughout the meeting; however, the NRC is not actively soliciting comments towards regulatory decisions at this meeting.

Purpose:

The U.S. Nuclear Regulatory Commission (NRC) will hold an open forum to discuss the NRCs assessment of safety performance for 2022 at the Shearon Harris Nuclear Power Plant.

Contact:

Matt Fannon 404-997-4547 matthew.fannon@nrc.gov

Participants:

NRC External Matt Fannon, Branch Chief, Region II Duke Energy Peter Boguszewski, Senior Resident Inspector , Region II Casey Smith, Resident Inspector, Region II Docket No: 05000400 Comments: The Harris annual assessment letter is accessible from the publicly available records (PARS) component of the NRCs document system (ADAMS) (Accession No. ML23055A033).

The NRC provides reasonable accommodations to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting or need a meeting notice or the transcript or other information from a meeting in another format (e.g. braille, large print), please contact Anne Silk, NRC Reasonable Accommodations Coordinator, at Anne.Silk@nrc.gov or call directly at 301-287-0745.

Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Ten (10) days advance notice is requested to try to ensure availability; however, every effort will be made to address a request for reasonable accommodations with less notice.

PUBLIC MEETING AGENDA

Shearon Harris Nuclear Power Plant Annual Assessment Meeting May 17, 2023, 06:00 PM to 07:00 PM ET Other, New Hill Community Center 3101 New Holleman Rd.

New Hill, NC

ADAMS Accession Number: ML23116A318 Office NRC/DRP matthew.fannon@nrc.

Name gov Date 04/25/2023 OFFICIAL RECORD COPY Link to meeting details: https://www.nrc.gov/pmns/mtg?do=details&Code=20230561 Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" 86 FR 14964, March 19, 2021 ADAMS No. ML21050A046 https://www.nrc.gov/reading-rm/doc-collections/commission/policy/index.html