UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 30, 2011 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
SUBJECT:
MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400
Dear Mr. Burton:
This letter confirms a Category 1 meeting which has been scheduled for May 9, 2011, at 10:00 a.m. The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting, scheduled at your request, is to discuss your Human Performance Improvement Plan and introduce new members of the Harris management staff.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4603.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.:
50-400 License No.: NPF-63
Enclosure:
As stated
March 30, 2011 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
SUBJECT:
MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400
Dear Mr. Burton:
This letter confirms a Category 1 meeting which has been scheduled for May 9, 2011, at 10:00 a.m. The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting, scheduled at your request, is to discuss your Human Performance Improvement Plan and introduce new members of the Harris management staff.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4603.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-400 License Nos.: NPF-63
Enclosure:
As stated X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:___ML110890209_____
X SUNSI REVIEW COMPLETE RAM 3/29/2011 OFFICE RII:DRP RII:DRP SIGNATURE JGW1 RAM NAME JWorosilo RMusser DATE 03/29/2011 03/29/2011 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME:
G:\\DRPII\\RPB4\\PROGESS ENERGY MEETINGS\\HARRIS MEETING NOTICE MAY 2011.DOCX
CP&L 2
cc w/encl:
Brian C. McCabe Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Electronic Mail Distribution Donald L. Griffith, Training Manager Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution LaQuisha M. Parks Manager Support Services Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution David H. Corlett, Supervisor Licensing/Regulatory Programs Progress Energy Electronic Mail Distribution David T. Conley, Senior Counsel Legal Department Progress Energy Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Joseph W. Donahue Vice President Nuclear Oversight Progress Energy Electronic Mail Distribution W. Lee Cox, III, Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 Chairman North Carolina Utilities Commission Electronic Mail Distribution Robert P. Gruber, Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 Ernest J. Kapopoulos, Jr.
Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998 Kelvin Henderson General Manager-Nuclear Fleet Operations Progress Energy Kelvin.henderson@pgnmail.com Donna B. Alexander, Manager Nuclear Regulatory Affairs Progress Energy Donna.alexander@pgnmail.com Chair Board of County Commissioners of Chatham County P. O. Box 1809 Pittsboro, NC 27312
CP&L 3
Letter to Christopher Burton from Randall A. Musser dated March 30, 2011
SUBJECT:
MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400 Distribution w/encl:
C. Evans, RII EICS L. Slack, RII EICS OE Mail RIDSNRRDIRS RIDSNRRDIRSIPAB PUBLIC RidsNrrPMHarris Resource Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS
Enclosure
SUBJECT:
PUBLIC MEETING WITH CAROLINA POWER AND LIGHT COMPANY FACILITY:
Shearon Harris Nuclear Plant DOCKET:
50-400 DATE & TIME:
Monday May 9, 2011 10:00 a.m. - 12:00 p.m.
LOCATION:
245 Peachtree Center Ave NE, Suite 1200 Room 1486 Atlanta, GA 30303 PURPOSE:
The purpose of this meeting is to discuss the Shearon Harris Nuclear Plant Human Performance Improvement Plan and to introduce new site management team.
The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov and contains information regarding visitors and security.
CATEGORY:
This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact, listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
NRC OFFICE PARTICIPATING:
Region II PARTICIPANTS:
NRC V. McCree, Regional Administrator, Region II L. Wert, Deputy Regional Administrator, Region II R. Croteau, Director, Reactor Projects, Region II W. Jones, Deputy Director, Reactor Projects, Region II J. Munday, Director, Reactor Safety, Region II H. Christensen, Deputy Director, Reactor Safety, Region II R. Musser, Chief, Reactor Projects Branch 4, Region II G. Wilson, Sr. Project Engineer, Reactor Projects Branch 4, Region II J. Worosilo, Project Engineer, Reactor Projects Branch 4, Region II LICENSEE Chris Burton, Vice-President - Harris Plant Ernie Kapopoulos, Plant General Manager - Harris Plant
Enclosure MEETING CONTACT:
Randall A. Musser 404-997-4603 Randy.Musser@nrc.gov AUDIO TELE-CONFERENCING Interested members of the public can participate in this meeting via a toll-free audio teleconference. For details, please call the NRC meeting contact listed above by May 8, 2011, or call the NRCs toll-free number, 1-800-368-5642, and ask the operator to be connected to Randy Musser.
VIDEO TELE-CONFERENCING Not Available