ML110890209

From kanterella
Jump to navigation Jump to search
Notice of Meeting with Shearon Harris Nuclear Plant to Discuss Human Improvement Plan and to Introduce New Site Management Team
ML110890209
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/30/2011
From: Randy Musser
NRC/RGN-II/DRP/RPB4
To: Burton C
Carolina Power & Light Co
References
Download: ML110890209 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 30, 2011 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

SUBJECT:

MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400

Dear Mr. Burton:

This letter confirms a Category 1 meeting which has been scheduled for May 9, 2011, at 10:00 a.m. The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting, scheduled at your request, is to discuss your Human Performance Improvement Plan and introduce new members of the Harris management staff.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4603.

Sincerely,

/RA/

Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 50-400 License No.: NPF-63

Enclosure:

As stated

March 30, 2011 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

SUBJECT:

MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400

Dear Mr. Burton:

This letter confirms a Category 1 meeting which has been scheduled for May 9, 2011, at 10:00 a.m. The meeting notice, which provides location and additional details, is enclosed. The purpose of the meeting, scheduled at your request, is to discuss your Human Performance Improvement Plan and introduce new members of the Harris management staff.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4603.

Sincerely,

/RA/

Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-400 License Nos.: NPF-63

Enclosure:

As stated X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:___ML110890209_____ X SUNSI REVIEW COMPLETE RAM 3/29/2011 OFFICE RII:DRP RII:DRP SIGNATURE JGW1 RAM NAME JWorosilo RMusser DATE 03/29/2011 03/29/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\DRPII\RPB4\PROGESS ENERGY MEETINGS\HARRIS MEETING NOTICE MAY 2011.DOCX

CP&L 2 cc w/encl: Chairman Brian C. McCabe North Carolina Utilities Commission Manager, Nuclear Oversight Electronic Mail Distribution Shearon Harris Nuclear Power Plant Electronic Mail Distribution Robert P. Gruber, Executive Director Public Staff - NCUC Donald L. Griffith, Training Manager 4326 Mail Service Center Shearon Harris Nuclear Power Plant Raleigh, NC 27699-4326 Progress Energy Electronic Mail Distribution Chair Board of County Commissioners of Wake LaQuisha M. Parks County Manager Support Services P.O. Box 550 Shearon Harris Nuclear Power Plant Raleigh, NC 27602 Progress Energy Electronic Mail Distribution Ernest J. Kapopoulos, Jr.

Plant General Manager David H. Corlett, Supervisor Carolina Power and Light Company Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution Electronic Mail Distribution Senior Resident Inspector David T. Conley, Senior Counsel U.S. Nuclear Regulatory Commission Legal Department Shearon Harris Nuclear Power Plant Progress Energy U.S. NRC Electronic Mail Distribution 5421 Shearon Harris Rd New Hill, NC 27562-9998 John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge Kelvin Henderson 2300 N. Street, NW General Manager-Nuclear Fleet Operations Washington, DC 20037-1128 Progress Energy Kelvin.henderson@pgnmail.com Joseph W. Donahue Vice President Nuclear Oversight Donna B. Alexander, Manager Progress Energy Nuclear Regulatory Affairs Electronic Mail Distribution Progress Energy Donna.alexander@pgnmail.com W. Lee Cox, III, Section Chief Radiation Protection Section Chair N.C. Department of Environmental Board of County Commissioners of Commerce & Natural Resources Chatham County Electronic Mail Distribution P. O. Box 1809 Pittsboro, NC 27312 Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211

CP&L 3 Letter to Christopher Burton from Randall A. Musser dated March 30, 2011

SUBJECT:

MEETING ANNOUNCEMENT - CATEGORY 1 PUBLIC MEETING WITH SHEARON HARRIS NUCLEAR PLANT REGARDING HUMAN IMPROVEMENT PLAN - DOCKET NO. 50-400 Distribution w/encl:

C. Evans, RII EICS L. Slack, RII EICS OE Mail RIDSNRRDIRS RIDSNRRDIRSIPAB PUBLIC RidsNrrPMHarris Resource Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS

SUBJECT:

PUBLIC MEETING WITH CAROLINA POWER AND LIGHT COMPANY FACILITY: Shearon Harris Nuclear Plant DOCKET: 50-400 DATE & TIME: Monday May 9, 2011 10:00 a.m. - 12:00 p.m.

LOCATION: 245 Peachtree Center Ave NE, Suite 1200 Room 1486 Atlanta, GA 30303 PURPOSE: The purpose of this meeting is to discuss the Shearon Harris Nuclear Plant Human Performance Improvement Plan and to introduce new site management team.

The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov and contains information regarding visitors and security.

CATEGORY: This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact, listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

NRC OFFICE Region II PARTICIPATING:

PARTICIPANTS: NRC V. McCree, Regional Administrator, Region II L. Wert, Deputy Regional Administrator, Region II R. Croteau, Director, Reactor Projects, Region II W. Jones, Deputy Director, Reactor Projects, Region II J. Munday, Director, Reactor Safety, Region II H. Christensen, Deputy Director, Reactor Safety, Region II R. Musser, Chief, Reactor Projects Branch 4, Region II G. Wilson, Sr. Project Engineer, Reactor Projects Branch 4, Region II J. Worosilo, Project Engineer, Reactor Projects Branch 4, Region II LICENSEE Chris Burton, Vice-President - Harris Plant Ernie Kapopoulos, Plant General Manager - Harris Plant Enclosure

MEETING Randall A. Musser CONTACT: 404-997-4603 Randy.Musser@nrc.gov Interested members of the public can participate in this meeting via a toll-free AUDIO TELE-audio teleconference. For details, please call the NRC meeting contact CONFERENCING listed above by May 8, 2011, or call the NRCs toll-free number, 1-800-368-5642, and ask the operator to be connected to Randy Musser.

VIDEO TELE- Not Available CONFERENCING Enclosure