It is requested that the Temporary Relief from Technical Specification LCO 4.3.10 be extended from the expected date of June 10, 1979 to June 14, 1979.
It is requested that the Temporary Relief from Technical Specification LCO 4.3.10 be extended from the expected date of June 10, 1979 to June 14, 1979.
If you require any additional fnformation, please let me know.
If you require any additional fnformation, please let me know.
Very truly yours,
Very truly yours, A  ,
* A  ,
f % ti n '
f % ti n '
Don W. Warembourg Manager, Nuclear P duction
Don W. Warembourg Manager, Nuclear P duction
                       'M oCo t So So l DWW/vt poob JS    / 47  .}}
                       'M oCo t So So l DWW/vt poob JS    / 47  .}}

Latest revision as of 20:46, 1 February 2020

Requests Extension to 790614 for Temporary Relief from Tech Spec LCO.3.10 Due to Delays in NRC Operator Examinations & Receipt of Snubber Parts
ML19261D561
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 06/11/1979
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Kuzmycz G
Office of Nuclear Reactor Regulation
References
P-79126, NUDOCS 7906190501
Download: ML19261D561 (1)


Text

public service company =e c4-+

P. O. Box 361, Platteville, CO 80651 June 11, 1979 Fort St. Vrain Unit No. 1 P-79126 Mr. George Kuzmycz, Project Manager Division of Project Management-Special Projects U.S. Nuclear Regulatory Commission Washington, DC. 20555

Subject:

Temporary Relief LC0 4.3.10

Reference:

May 25, 1979 Letter Speis to Fuller

Dear Mr. Kuzmycz:

In your letter of >by 25th, you granted Temporary Relief from Technical Speci-fication LCO 4.3.10 to permit pre-critical checkout and operating tests at power levels less than 2% with inoperable snubbers. It was also stated that we expected to be complete with the snubbers and/or the requirement for Temporary Relief by June 10, 1979.

Several events have occurred, which have delayed us beyond the June 10, 1979, expected date.

1. We were unable to schedule the operator tests as originally planned. Due to the Three-Mile Island incident, the NRC examiner could not conduct the examinations as scheduled, and the operator examinations had to be delayed until June 11 and 12th.
2. The snubber program was also delayed beyond the anticipated date due to delays experienced in receiving replacement parts. At the present time, all but 43 of the 430 snubbers have been tested and reinstalled. These 43 snubbers are presently being rebuilt, and should be in service by June 14th.

It is requested that the Temporary Relief from Technical Specification LCO 4.3.10 be extended from the expected date of June 10, 1979 to June 14, 1979.

If you require any additional fnformation, please let me know.

Very truly yours, A ,

f % ti n '

Don W. Warembourg Manager, Nuclear P duction

'M oCo t So So l DWW/vt poob JS / 47 .