ML20134J439

From kanterella
Jump to navigation Jump to search
Insp Repts 50-348/96-09 & 50-364/96-09 on 960901-1012. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
ML20134J439
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 11/08/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20134J413 List:
References
50-348-96-09, 50-348-96-9, 50-364-96-09, 50-364-96-9, NUDOCS 9611150212
Download: ML20134J439 (44)


See also: IR 05000348/1996009

Text

. _ . . _ . . . _ _ - - - _ .- _ -

.

,

.

~'

. t

!

'

.

! 1

l

U.S. NUCLEAR REGULATORY COMMISSION (NRC)

F

REGION II l

l

!

'

!

Docket Nos: 50-348 and 50-364-

License Nos: NPF-2 and NPF-8

Report No: 50-348/96-09 and 50-364/96-09 ,

,

Licensee: Southern Nuclear Operating Company (SNC), Inc. f

Facility: Farley Nuclear Plant (FNP), Units 1 and 2 i

Location: 7388 North State Highway 95  !

Columbia, AL 36319 i

!

Dates: September 1 - October-12, 1996

i

1

Inspectors: T. Ross, Senior Resident Inspector

J. Bartley, Resident Inspector

J. Blake, Reactor _ Inspector (Sections M2, M3.

'

,

t

M6, and M8) l

R. Caldwell, Resident Inspector (In training) i

R. Chou.. Reactor Inspector (Section E1.1 thru 3)

M. Ernstes Operator Licensing Examiner (Section )

05.1)  !

W. Kleinsorge, Reactor Inspector (Sections R1.2, 1

R2. R3, R7)  !

l J. Lenahan, Reactor Inspector (Section E7.1 and  ;

2)  !

l

l Approved by: P. Skinner, Chief. Projects Branch 2

l Division of Reactor Projects

f

f

$

l

i Enclosure 2

,

9611150212 961108

PDR ADOCK 05000348

G PDR ,, l

)

. --. - - -.- - - - - . - ~ ~ - . ~ - - - - -

.

i

-

l .

. I

Farley Nuclear rP Units 1 And 2

NRC Inspection Report 50-348/96-09. 50-364/96-09 i

This integrated inspection included aspects of licensee operations.  !

engineering, maintenance, and plant support. The report covers a 6-week I

period of resident and regional inspections.

.

Ooerations

e Overall, both units operated well at steady state full power. The

l

conduct of operations by Operations personnel and management was l

consistently in compliance with procedures and regulatory requirements.

l and reflected conservative operation (Section 01).

e Shiit operators remained very attentive to plant conditions, and were

quite knowledgeable of plant status and ongoing activities (Section

01.1).

e The transfer of Unit 2 new fuel to the spent fuel pool was very well

controlled (Section 01.2). ]

e Operator performance in response to the Unit 2 main feedwater transient

and shutdown of Unit 2 for the upcoming refueling outage was~ exemplary

l '(Sections 01.3 and 01.4).

I e A violation was identified for two instances of mispositioned v71ves due ,

to personnel errors by non-licensed operators that caused two letdown

system transients on Unit 2 and inoperability of the 18 emergency diesel

'

generator (Section 01.5).

e .Overall. housekeeping and-physical conditions of the plants remained

adequate (Sections 02.1 - 02.3).

e A noncited violation was identified for failing to incorporate a newly

approved license amendment into plant procedures (Section 03.1).

,

e -The requalification program complied with the requirements and standards

of plant procedures as well as the requirements of 10 CFR 55.59 for the

, areas inspected. There continued to be some problems in ensuring the

operators are properly retrained on identified weaknesses (Section

05.1).

e Operator overtime was well controlled (Section 06.1).

Maintenance

e Maintenance and surveillance testing activities were routinely conducted

,

in a thorough and competent manner by well qualified individuals in

, accordance with plant procedures and work instructions (Section M1.1).

Enclosure 2

l

_ _ _. _ _ _ - . ~ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . _ _ . _ . _ _

.

. i

'

!

l 2 l

e. Major work activities (i.e., epoxy coating of component cooling water

heat.exchangers and control room air conditioning modification) were

well coordinated, exhibited good craftsmanship, and accomplished

.according to approved work instructions and procedures (Sections M1.2 -

and M1.3).

! e Current status and history of the FNP steam generators indicate that the

licensee has been doing a conscientious job of managing steam generator 3

degradation (Section M2.1).

'

e Licensee and contractor procedures 'for the evaluation and management of

steam generator eddy current data appear to be adequate for the

circumstances (Section M3).

l e . Steam generator degradation has been properly managed even though the i

!

integrated program for management has not been documented (Section M6).  !

'

Enaineerino i

e. Design change control process procedures comply with regulatory l

l requirements (Section E1.1).

  • Design change packages were generally of good quality. However, several l

'

minor discrepancies with the associated installation drawings were

identified (Section E1.2).

l e Additional examples of recent and pre-existing as-built design '

! discrepancies associated with cable tray and pipe supports were

identi fied. The number of welding discrepancies identified indicates

that the licensee's welding inspection program may be deficient (Section

'

E1.2). ,

e Program for control and handling of heavy loads was adequate (Section .

E1.3).

e Engineering and technical support and oversight of major maintenance,

modification and inspection activities were evident and effective

(Section E1.4).

e Quality assurance audits of engineering activities provided useful i

insights (Section E7.1).

l

e Safety system self-assessment program has been a very effective tool in

, identifying and correcting deficiencies in design and operation of

l critical safety systems (Section E7.2).

d

i Enclosure 2

i

.. - -. . -- --- . - - _ - - .. .

- - - . - ..

,

'

!

'

.

!

.

l

l 3 ,

'

Plant Sucoort

!;

e' Implementation of radiological controls in the radiologically controlled

areas were evident and generally effective. Overall. the radiologically

controlled areas were adequately maintained and posted (Section R1.1). i

o Primary and secondary water chemistry controls were appropriate, and in

compliance with regulatory requirements and industry guidelines, with  !

, some exceptions (Section R1.2 and R3.1). .

o Procedures, equipment, and practices for monitoring primary-to-secondary

leakage were appropriate (Section R2.1).  :

o Primary and secondary water chemistry program was subjected to

independent audits, with appropriate action taken for identified

weaknesses (Section R7.1).

e Emergency drills were well coordinated by Emergency Planning personnel.

and demonstrated the readiness of emergency response personnel and  !

facilities (Section P4.1).

L e Routine security _ activities continued to be performed in a conscientious

and capable manner, assuring the physical protection of protected and

, vital areas (Section S1.1). However, in one instance, miscommunication

between Security and Health Physics resulted in a -trailer entering the

protected area without being properly searched. This was identified as.

an unresolved item (Section S1.2).

'

e Two apparent violations were identified regarding inadequate

installation and inspection of Kaowool one-hour fire barriers required '

by the Fire Protection Program. An enforcement conference to consider

escalated enforcement has been scheduled (Section F2.1);

i e One unresolved item was identified concerning the adequacy of

qualification testing on Kaowool fire barriers (Section F2.1).

L e Fire brigade drill demonstrated proficiency of fire fighting capability

l

(Section F5.1).

I-

Enclosure 2

_ _ _

_

-

.

'  !

.

.

Reoort Details

Summary of Plant Status

l

1

Unit 1-_ operated steadily at 100% power for the entire inspection period. l

,

. Unit 2 operated steadily at 100% power for the entire ins)ection period.. )

except for two brief power reductions. On September 8. t1e unit was ramped

down to 70% power to search for main condenser tube leaks. Then again on

September 23. Unit 2 was ramped down to 95% power in response to transient l

conditions caused by the 2A steam generator feed pum) (SGFP). After 317 days i

of continuous operation. Unit 2 was shutdown on Octo)er 12 to begin its  !

eleventh refueling outage (U2RF11)..  !

I. Operations

l

01 Conduct of Operations

01.1 Routine Observations of Control Room Ooerations (71707)

Using Inspection Procedure (IP) 71707, the resident inspectors conducted l

frequent inspections of ongoing plant operations including routine tours

of the main control room (MCR) to verify proper staffing, operator

attentiveness, and adherence to approved operating procedures. The

inspectors also regularly reviewed operator logs and Technical

S)ecifications (TS) Limiting Condition of Operation (LCO) tracking ,

sleets, walked down the main control boards (MCB), and interviewed )

members of the operating shift crew to verify operational safety and

compliance with TS. The inspectors attended daily plant status meetings

to maintain awareness of overall facility operations, maintenance

activities, and recent incidents. Morning _ reports and.Farley Nuclear

Plant Incident Reports (FNPIR) were reviewed on a routine basis to

assure that potential safety concerns were properly reported and

resolved.

-Overall control and awareness of plant conditions during the inspection

period were excellent. During tours of the NCR, the inspectors

regularl

balance ofy observed thatannunciators

plant panel' very few MCB, emergency.

were in alarm atpower board

any one (EPB),

time. One

and

or two persistent annunciator alarms 3revented Unit 2 from achieving

" blackboard". However. Unit 1 and tie EPB were frecuently in a

blackboard condition. Operator attentiveness to, anc knowledge of..

plant conditions and status of ongoing activities continued at a high

level. The combined number of MCB deficiencies was reduced to less than

20. demonstrating management resolve for keeping MCB deficiencies as few

as possible. Many of the remaining deficiencies were on Unit 2 MCB.

awaiting tha upcoming refueling outage.

Enclosure 2

.

'

.

.

2

01.2 Unit 2 Transfer of New Fuel to the Soent Fuel Pool (60705 And 71707)

The resident inspectors observed the transfer of several new fuel

assemblies from the new fuel storage racks to the Unit 2 spent fuel pool

(SFP) in accordance with (IAW) FNP-0-FHP-3.0 " Receipt and Storage of

New Fuel." Revision 28. Licensee personnel were knowledgeable and very

methodical. The handling and transfer of new fuel assemblies was well

controlled and consistent with procedural and TS requirements.

01.3 Unit 2 Main Feedwater Flow Control Transient (93702)

On September 23, 1996. Unit 2 operators observed that the 2A and 2B

SGFPs were experiencing sudden speed oscillations. These oscillations

had a destabilizing effect on main feedwater flow to the steam

generators (SGs). Operators promptly initiated a >ower reduction and

sent a System Operator (50) to physically examine )oth SGFPs in the

turbine building. Operations subsequently concluded that the low

pressure turbine governor valve for the 2A SGFP was malfunctioning. The

steam supply to the low pressure governor valve was isolated and control

of the 2A SGFP was placed on the high In about

45 minutes after the transient began,plantpressure governor

conditions hadvalve.

stabilized

with the 2A SGFP back in automatic control. Unit 2 power reduction was

arrested at 95% power and then returned to full power a few hours later.

During the ramp up to full power, a resident inspector interviewed l

responsible operators, monitored 2A and 2B SGFP operation and walked -

down the Unit 2 MCBs. The inspector concluded that o)erator response to i

the transient was excellent and plant conditions had Jeen restored to )

normal, ,

l

01.4 Unit 2 Shutdown For U2RF11 (71707) ,

1

On October 11, 1966 Operations commenced a rampdown of Unit 2 IAW FNP- l

Unit '

2-UOP-3.1 " Power Operation."and was the removed

main turbine / generator

from the grid, which(MTG) power w

marked the commencement of U2RF11 at one minute after midnight on '

October 12. 1996. Immediately following removal from the grid,

operators conducted a MTG overspeed test IAW UDP-3.1. Appendix 4 and

FNP-2-STP-151.5 " Main Turbine Overspeed Test." The MTG tri) ped at 1934

rpm, well within the required acceptance criteria. Unit 2 slutdown

continued IAW FNP-2-UDP-2.1. " Shutdown of Unit from Minimum Load To Hot

Standby." After entering Mode 2. operators manually tripped the reactor

aursuant to UDP-2.1 and FNP-0-ETP-3661 " Control Rod Test and Evaluation

3rogram." Operators responded to the manual trip IAW FNP-2-EEP-0.

" Reactor Trip or Safety Injection." and then FNP-2-ESP-0.1 " Reactor

Trip Response." A resident inspector was in the MCR observing all of

the aforementioned activities. Overall, operator performance was

excellent and plant equipment response was per design. However, the i

inspector did note a few minor problems, which included: a) Manual i

reactor trip first out annunciator did not alarm (this problem had been

previously identified): b) Nuclear instrumentation system (NIS)

Enclosure 2

1

__

.

.

e

3

intermediate range channel NI-36 appeared undercompensated, and

prevented the automatic energization of NIS source range channels: and

c) Operators had difficulty maintaining Tavg within plus/minus 1.5

degrees of Tref as prescribed by UDP-2.1 (step 5.5.1). Each of these

problems were discussed with site management for resolution.

01.5 System Misalianments By System Ooerators (71707)

Within about a 6 week period, the plant experienced two serious system

misalignment events caused by S0 personnel errors that resulted in two

letdown system transients and the inoperability of an emergency diesel

generator (EDG).

On August 27, 1996, the licensee discovered that two valves (Transfer

Header To Storage Tank valve OSY52V524 and Manual Pump Discharge To

Transfer Header valve OSY52V529A) in the IB EDG fuel oil transfer system

were inadvertently left open. This misalignment of the fuel oil

transfer system effectively 3revented fuel oil makeup from the IB fuel

oil storage tank (FOST) to tie IB EDG day tank. Operations had

discovered the misaligned valves during a refill of the IC EDG FOST from

the auxiliary FOST when o)erators observed a high level alarm on the 1B

FOST and sent a S0 to checc out the problem. Subsequent investigation

by Operations, determined that the two valves in cuestion had not been

closed by the responsible 50 as was required by FhP-0-50P-42.0, " Diesel

Fuel Oil Storace and Transfer System " following a refill of the IB EDG

FOST on August 23, 1996. For about five days, fuel oil makeup to the IB  !

EDG day tank was not possible. With just the day tank as a fuel supply,

the 1B EDG would be expected to run at full load for ap3roximately four

hours. The licensee reported this event to the NRC by _icensee Event

Report (LER) 50-348/96-05 dated September 20, 1996.

On October 8,1996, a S0 mispositioned two valves during two separate .

'

incidents while attempting to fluff the 2B mixed bed demineralizer IAW

FNP-2-SOP-50.4 "Demineralizer Resin Removal and Addition." During the

first incident, while performing Step 4.5.1.3 of SOP-50.4 which required

closing demineralizer uutlet valve V167B. the S0 inadvertently selected )

valve V167A and began closing the valve. Upon hearing an unexpected 1

change in flow noise, the S0 immediately reopened the valve and notified

the Shift Supervisor (SS). Prompt action by the S0 prevented a serious

overpressurization of the letdown line which would have occurred had he j

succeeded in fully closing V167A. thereby dead-heading letdown flow.  !

During the partial closing of V167A, the Unit 2 MCR did receive a j

" Letdown Pressure High" alarm. After notifying the SS, the 50 proceeded

on with SOP-50.4, even though the SS was under the impression he had

secured from the evolution and was returning to the MCR to discuss the

incident. Unbeknownst to the Unit 2 operating crew, the 50 proceeded to

Step 4.5.1.5 which directed him to open demineralizer Johnson screen

outlet valve V161B. However, the S0 misread the )rocedure and 1

inadvertently selected V161A. which he opened. T1is caused letdown flow  ;

to be diverted from the inservice 2A mixed bed demineralizer to the  !

Enclosure 2 l

'

,

l

!

___ _ . _ . _ _ _ _ . ___.___ _ __ _ ___ ._

'

.

.

'

4

1

primary spent resin storage tank (SRST). In the MCR operators noticed

that auto makeup to the volume control tank (VCT) had initiated and VCT

level was dropping rapidly from the normal 40% level. Operators

promatly started manual makeup and were able to stabilize VCT level at

21% aut not restore it. The SS managed to contact the S0 and direct him

to close V161A. Operators were then able to restore VCT level.

Subsequent review of SRST level changes concluded that approximately 800

gallons had diverted from the VCT in about six minutes.

In both of the aforementioned events, a responsible 50 failed to perform

applicable system operating procedures as written resulting in

mispositioned valves that adversely affected operability of the IB EDG '

and initiated two transients involving the Unit 2 letdown system. These >

personnel errors are considered a violation of TS 6.8.1 that requires

compliance with plant procedures SOP-42.0 and 50.4. This is identified i

as violation (VIO) 50-348, 364/96-09-01. Multiple Valve Misalignments By

System Operators.  ;

02- Operational Status of Facilities and Equipment ,

'

02.1 General Tours of Soecific Safety-related Areas (71707) .

General tours of FNP specific safety-related areas were performed by the i

resident inspectors to examine the physical conditions of plant

equipment and structures, and to verify that-safety systems appeared

properly aligned. Limited walkdowns of a more detailed nature of the i

accessible portions of safety-related structures, systems and components

l were also performed in the following specific areas:

o Control room air conditioning systems (CRACS) and emergency j

ventilation systems, trains A and B

e. Unit 1 and 2 residual heat removal heat exchanger (HX) rooms-

e Unit 1 and 2 turbine building

l e Unit 1 and 2 SFP and SFP HXs

j e Unit 1 and 2 component cooling water (CCW) pump and HX rooms

,

e Unit 1 and 2 low voltage switchyard

e Unit 1 and 2 service water intake structure (SWIS), including

service water system (SWS) pumas, switchgear, and strainers

e EDG Building - 1/2A.18.1C. 23. and 2C EDGs

i

e Unit 1 and 2 vital 4160 volt alternating current switchgear

e Unit 1 and 2 iping penetration room 100 foot elevation

e Unit 1 and 2 13ing penetration room on 121 foot elevation

o Unit 1 and 2 F) ventilation equipment rooms

e Unit 1 and 2 hot shutdown panels

e Unit 1 and 2 turbine-driven auxiliary feedwater (TDAFW) pump rooms

e Unit 1 and 2 main steam valve rooms

,

e Unit 1 and'2 new fuel storage areas

!

Enclosure 2 l

!

I

l

'

.

1

5

Overall material conditions and housekeeping for both units were

generally adequate. Minor equipment condition and housekeeping problems

identified by the inspectors were reported to the responsible SS and/or

maintenance department for resolution.

02.2 Biweekly Insoections of Safety Systems (71707)

The resident inspectors used IP 71707 to verify the operability of the i

following selected safety systems:

e Unit 2 Containment Integrity

The inspector verified Unit 2 containment integrity using FNP-2-STP-

14.0 " Containment Integrity Verification Test." Revision 14. The

inspector verified accessible valves, breakers, hatches, and capped

pipes were properly aligned. No discrepancies were noted.

02.3 TS LCO Trackina and EDG Test Data Loa (71707)

Resident ins)ectors routinely reviewed the TS LCO tracking sheets filled ,

out by the s11ft foremen whenever a TS LCO action statement was entered.  ;

All tracking sheets for Unit 1 and 2 reviewed by the inspectors were

consistent with plant conditions and TS requirements. An inspector also

reviewed the EDG Test Data Log book, and did not identify any

discrepancies.

02.4 Tao Orders (71707)

During the course of routine inspections, the following tag order (TO) I

and associated equipment clearance tags were examined by the inspectors:

e TO# 96-1012-2 2B CCW Pump

All tags and the T0 examined by the inspector were properly executed and  ;'

implemented.

03 Operations Procedures and Documentation

03.1 Untimely InCorDoration of TS Amendment Into Plant Procedures (71707) i

By letter dated December 19, 1995. the licensee proposed to amend its TS I

requirements for CRACS and the control room emergency filtration system.

In this letter. SNC requested that the effective date for the pro)osed

amendment be applicable when LCOs were entered to implement the CMCS

design change. However. Amendment number 119 (Unit 1) and 111 (Unit 2)

,

for Facility Operating Licenses (FOL) NPF-2 and 8 were issued on May 21.

l 1996 effective upon the date of issuance. SNC recognized the problem

and called the Office of Nuclear Reactor Regulation (NRR) for

clarification. The NRR project manager (PM) stated that it had been

their intent to issue the TS amendment as requested by SNC. Rather than

Enclosure 2

l

. _ . -, .~ . . - - - . . . --. . . - .-

.

t

'

.

!

t

'

!

6

i

submit a letter to correct the TS-amendment effective date. the licensee <

assumed their discussion with the NRR PM was sufficient. Some time .

later, as implementation of.the CRACS design change became delayed, a  !

resident inspector questioned the licensee's basis for not incorporating

these amendments into applicable plant procedures, and implementing the ,

associated CRACS surveillance requirements. Subsequent review by the'

'

NRC's Office of the General Counsel confirmed that both license i

amendments were in effect and could not be deferred without written NRC l

approval. Failure-to implement newly amended TS requirements in a

timely manner is usually a serious NRC concern. However, in this case,

the extenuating circumstances for this violation meets the guidelines of.

Section VII.B.1 of the NRC Enforcement Policy for a non-cited violation  !

(NCV) identified as NCV 50-348. 364/96-09-02. Untimely Incorporation of

TS Amendment Into Plant Procedures.

05 Operator Training and Qualification  !

05.1 Licensed 00erator Reaualification Proaram  !

l

a. Insoection Scone (71001) l

During the period September 17 - 20, 1996, the inspector reviewed the

licensee's-licensed o)erator requalification program to determine '

compliance with 10.CFR 55.59. Requalification. Specific areas of review ,

included job performance measures (JPM) administration.. operating  :

examination quality, documentation of results, and remediation, i

b. Observations and Findinas

1

The inspector observed the administration of -JPMs to staff Senior -l

Reactor Operators (SR0s) on the simulator and in the plant. The. '

licensee evaluators' grading was consistent with the inspector's

observations.. The evaluators effectively asked follow up questions

based on operator performance. This enabled them to determine the cause I

for an observed error and determine individual or generic program areas

in need of improvement.

JPM 3erformance'by the staff SR0s was marginal. Three JPMs were failed

by t1e operators. One of the SR0s failed two JPMs resulting in an

overall failure for that operator. Two operators missed the same JPM

when they misdiagnosed a problem with the rod control system and

unnecessarily tripped the reactor. 1

The documented remediation for the operator who failed the JPM

walkthrough adequately addressed the weaknesses observed by the

inspector. The inspector reviewed the documentation of remediation for

other operators who failed their annual examination this year. Farley

3rocedure FNP-0-TCP-17.3. " License Retraining Program Administration."

i Revision 14 dated 12/18/95. detailed the licensee's guidelines for

remedial training. Section 3.15.2 of this procedure stated that "At a

4

Enclosure 2

l

.- - .-- - -, .-

.

-

.

7

minimum, the remedial training will consist of a written study guide and

assignment to an instructor who will monitor the progress of the

trainee. This training will be documented using a memo similar to

Figure 2". In two cases, the guidance was not fully utilized. There

were not clear objectives of the training nor was there any

documentation of an instructor being assigned to monitor the training

and initial for its completion. The operators had been documented as

having weaknesses in several competency areas. However, the remediation

documented in a training department memorandum, listed only two discrete

3rocedure issues and one general communication issue to review.

Remedial training was not consistent with areas in need of improvement

documented in simulator evaluations. Although the remediation was not

properly documented, and its completion was not initialed for by the

assigned instructor, the inspector was able to determine that adequate

remediation had been conducted for the operators' performance

weaknesses. This issue will be tracked as Inspector Followup Item (IFI)

50-348,364/96-09-03. Inconsistent Application of Remedial Training

Documentation Guidance.

The inspector reviewed the licensee's system for providing feedback of

generic weaknesses observed during regualification examinations. Peer

evaluators reviewed the simulator evaluations and listed areas where

additional training could improve performance. These items were

documented in a memorandum to the Operations Training Supervisor. The

last review, dated June 10, 1996 contained fourteen such items. This

system adequately supported the feedback portion of.a systems approach '

to training. However, in one instance the training was not effective.

A crew of operators incorrectly interpreted the EEP-0, " Reactor Trip or  :

Safety Injection." foldout page guidance and implemented FRP-P.1. ]

" Response to Imminent Pressurized Thermal Shock Condition." >

unnecessarily during a lar e break loss of coolant accident. During' a 3

emergency preparedness dri 1 cbserved by the inspector on September 18, l

1996, the simulator crew made the same error despite remedial training. l

Training department evaluators had recommended a procedure change in i

March 1996, to help reduce the' susceptibility of operators making this

incorrect interpretation but they had not received any feedback on their

recommendation.

During review of the annual requalification training curriculum outline,

the inspector identified that more simulator training was provided for

shift operators than for staff operators. 10 CFR 55.59(a).

RequaHfication Requirements, does not distinguish between shift and

staff operators regarding participation in the program. Staff o3erators

received one week of simulator training per year. Included in tlat week

was the simulator portion of their annual operating examination. With  ;

the annual examination typically being administered on Thursday and )

Friday, there were actually only three days of simulator training for '

staff operators. Control room operators received additional training .

during other weeks based on plant needs such as startups or shutdowns. l

Updated Final Safety Analysis Report (UFSAR) section 13.2.1.2 states the

Enclosure 2

!

i

.

.

.

8

retraining will last approximately one week requiring the student to

perform each of a list of 26 items. The training department tracked

completion of these items using license simulator retraining form OPS-

564, " Task Tracking Sheet." The inspector verified that all licensed

operators were documented as receiving at least this minimum training.

c. Conclusions

The inspector concluded that the licensee's requalification program

complied with the requirements and standards of plant procedures as well

as the recuirements of 10 CFR 55.59 for the areas inspected. The

licensee ceveloped and administered examinations that effectively

identified areas in need of improvement. Documentation of remediation

was in need of improvement to ensure adequate completion. Although

staff operators did not receive as much simulator training time as the

shift operators, all operators were found to have completed the minimum

requirements.

06 Operations Organization and Administration

1

06.1 Administrative Control of Ooerator Overtime (71707)

The requirements for control of operator overtime are contained in TS 6.2.2 and FNP-0-AP-64, " Work Schedules for Personnel." Revision 3. The

inspector interviewed two shift clerks and reviewed the shift manning

and biweekly payroll time records for Crews 1 and 6 for the period July

1 - August 1. 1996. The inspector did not identify any discrepancies

with the records cr control of operator overtime. There were no

instances of excessive overtime. The inspector also reviewed the

proposed schedule for the Fall 1996 Unit 2 Outage. The inspector found

that the schedule maintained overtime within the requirements of TS 6.2.2. The inspector concluded that o)erator overtime was adequately

controlled and that the records were t1orough.

08 Hiscellaneous Operations Issues (92901)

08.1 (Closed) IFI 50-348. 364/95-12-01. Lack of Measurable Performance

Indicators Due to Use of Westinohouse Owners' Grouo Emeroency Response

Guideline

This IFI identified that critical tasks were not an objective measure by

which the facility evaluators could determine if an individual or crew's

performance was satisfactory. Since that inspection, the licensee has

revised the critical tasks to provide the evaluator with measurable

objectives for determining satisfactory performance. This IFI is

considered closed.

l

l

l

l

Enclosure 2

1

.

.

.

9

II. Maintenanqq

M1 Conduct of Maintenance

M1.1 General Comments

Inspectors observed and reviewed portions of various licensee corrective

and preventative maintenance activities, and witnessed routine

surveillance testing, to determine conformance with plant procedures,

work instructions, industry codes and standards. TS and regulatory

requirements.

a. Jnsoection Scooe (61726 and 62707)

The resident inspectors observed all or portions of the following

maintenance and surveillance activities, as identified by their

associated work order (WO), work authorization (WA) or surveillance test

procedure (STP):

e FNP-2-STP-80.2 1C EDG Operability Test

e WA 121388 1A CCW HX Epoxy Coating Application

e WA 123723 2A CCW HX Epoxy Coating Application

e WO 596001466 1A CCW HX Tube Ins)ection Cleaning, Repair.

Stabilization and )1ugging

e WO S96001476 2A CCW HX Tube Ins)ection, Cleaning, Repair,

Stabilization and ) lugging

e FNP-2-STP-608.1 Loop A Main Steam Safety Valve Operability Test

e FNP-2-STP-151.5 MTG Overspeed Test

e FNP-0-ETP-3661 Control Rod Test And Evaluation Program

o WO S00079525 Train A CRACS modification

e WO 0463607 U2 TDAFW Pump (Turbine) lubrication

b. Observations. Findinos and Conclusions

All of the aforementioned maintenance work and surveillance testing

observed by the inspectors were performed IAW WO instructions,

procedures, and applicable clearance controls. No adverse findings were

identi fied. Safety-related maintenance and surveillance testing

evolutions were well planned and executed. Responsible personnel

demonstrated familiarity with administrative and radiological controls.

Surveillance tests of safety-related equipment were consistently

performed in a deliberate step-by-step manner by personnel in close

communication with the control room. Overall, the craftsmen and

technicians appeared knowledgeable, experienced, and well trained for

,

the tasks they performed.

In addition, see the discussion below regarding certain major

maintenance activities observed by the resident inspectors (Section M1.2

and 3).

Enclosure 2

i

>

_- .

,

'

,

!

.

,

,

.

10 ,

'

M1,2 WO 596001466 and S96001476. and WA 121388 and 123723. 1A and 2A CCW HX

Preoaration. Reoair. and Eooxy Coatina '

a. Insoection Scoce (62707)

Resident inspectors observed various aspects of the modification - i

activities associated with e) oxy coating of the service water inlet and  !

outlet channel heads, tube sleet, and down tube'(inlet side only) for '

the 1A and 2A CCW HX. The work observed included hydroblasting, grit

blasting, tube sheet weld repairs, CCW tube stabilization, and the epoxy -

application. Inspectors also reviewed and verified imalementation of

applicable WO instructions: WAs: FNP-0-ETP-4418, CCW leat Exchanger i

Epoxy Coating Application; and Plastocor Application Specification for  ;

tubesheet cladding, inlet end coating, and channel head coating.

l

b. Observations and Findinas

'

This was a major modification that involved a number of plant. employees )

and contractors for over three weeks. The work on the 1A and 2A CCW HXs '

was performed in parallel. In general, all observed work was

accomplished IAW work instructions and applicable procedures (i.e'., ETP-

4418 and Plastocor Application Specification). However, several process I

control and equipment problems were identified.

e Eleven broken / severed tubes in the 2A CCW HX, some with missing l

sections of tube;

e During application of 2A CCW HX primer inlet coat of epoxy,

ambient air and surface temperatures slightly exceeded the

established-limits: ,

e During the mixing of one batch of epoxy for_ the 2A CCW HX, epoxy

material temperature slightly exceeded the established limit;

e While being stored at a complex 3 warehouse, ambient air

temperature for epoxy materials slightly exceeded the established

limit for about four hours; and

e Inadequate control of combustible materials in the CCW HX rooms

Broken, severed, and fragmented tubes in the 2A CCW HX were subsequently  ;

stabilized and fenced in as well as possible. Not all tube fragments

could be located or secured. A Nonconformance Disposition Report (NDR),

including a 10 CFR 50.59 safety evaluation, was issued to address this

condition. In this report the licensee concluded that the " failed tubes

and missing tube fragments within CCW heat exchanger 2A will not impact

_the CCW system capability to Jerform its intended design function or the

continued safe o)eration of t1e CCW system." [ Note, licensee also

discovered a num)er of damaged tubes in the 1C and 2C CCW HXs .sometime

later.] With regard to the temperature limits that were. exceeded during

Enclosure 2

. -. .- -- - - - -. - . - . .. --

.

i

.

I

11

the application and storage of epoxy material, the licensee requested

and received a letter from the e) oxy manufacturer confirming that the

slightly increased temperatures lad insignificant consequences.

Furthermore, the licensee confirmed that appropriate adjustments to the

curing times, and special application instructions, were implemented to  ;

,

. accommodate the increased temperatures. ,

During the conduct of CCW HX epoxy coating modification activities, the  !

,

licensee failed to exhibit positive control over the quantities of ,

combustibles in the CCW HX room. More specifically, no attemat was made

to minimize the storage and placement of intervening combustiales -

between redundant service water inlet valves to the CCW HXs during epoxy ,

work on the CCW HXs. Controls were put in place for the 1C and 2C CCW

HX work. Subsequent evaluations by the Engineering Support (ES) group

confirmed that general fire loadings did not exceed limits established i

by the fire protection program. However, the program was explicit about

maintaining no intervening combustibles between redundant trains. The

inspector did note that hourly fire watches were in effect during the

duration of work on the A CCW HX. although for different reasons (i.e..

Kaowool concerns, see section F2.1). Also, continuous fire watches were

in place during those periods when activities required an Open Flame  :

Permit.  !

c. Conclusions

i

In general, all observed work was accomplished IAW work instructions and i

applicable procedures by qualified individuals. The overall process was I

'

l well controlled in a conscientious and deliberate manner. Application

of lessons learned was evident as the licensee progressed from the B. to

the A. and then to the C CCW HXs. Problems were appropriately addressed

and resolved. The review of CCW HX epoxy process, and NDRs for the

fragmented CCW HX tubes, was identified as IFI 50-348. 364/96-09-04. CCW I

HX Epoxy Coating And Broken Tubes, pending additional review by the

inspector.

M1.3 WO S00079525. Tie-In of New CRACS. A Train

a. Insoection Scoce (62707)

Resident inspectors observed selected portions of the CRACS modification  ;

'

including: 1) installation of duct blankoffs: 2) removal of old

compressor, receiver, and cooling coils
and 3) installation and hookup

of new cooling coils. Previous observations of work on the CRACS

modification were documented in Inspection Report 50-348, 364/96-03. .

The CRACSWork

S95-0-8816. modification was implemented

was performed under WO- by#S00079525. Design Change Packa

I

Enclosure 2

!

<

.

.

.

12

b. Observations and Findinas

The licensee planned to take the A train CRACS out of' service (00S) on

Se)tember 5. -1996, to complete modification work. The work was

scleduled to take 25 days. The licensee planned to implement a revised

TS 3/4.7-.7.2 per FOL Amendment No. 119 coincident with taking the A-

train 00S. Amendment No. 119 waived the provisions of 3.0.4 (as applied

to TS 3.7.7.2) during the initial 30 days of implementation of control

room cooling design changes. Also, the revised TS adopted the Improved

TS surveillance for verification that the CRACS units can remove the

design basis accident (DBA) heat loads.

The licensee identified, on September 2.1996. that the test procedure.

FNP-0-ETP-1052 "B Train Control Room Air Conditioning System Test."

Revision 0. would not be a valid test as written for the current .

conditions. The IB control room pressurization filter unit heaters  !

would not remain energized in test and the outside air temperature was

not greater than 85 degrees fahrenheit as required by the test ,

procedure. The licensee submitted Request for Engineering Assistance  :

(REA) 96-1291 to Southern Company Services (SCS) to determine if l

additional heat was required for the MCR due to reduced outside

temperatures to assure the DBA heat load during test conditions. SCS

determined that the pro)osed test conditions (with outside temperatures

70 to 90 degrees fahrenleit) provided heat loads greater than the DBA' ,

heat loads. SCS also recommended that the direct current emergency

~

lighting be energized during the test to add conservatism. The licensee i

subsequently revised Engineering Test Procedure (ETP) 1052 to '

incor) orate SCS's recommendations. The inspectors reviewed the revision

to ET)-1052 and the SCS response to REA 96-1291 and determined they were

adequate. The licensee performed FNP-0-ETP-1052. Revision 1. i

successfully on September 7, 1996 and placed the A train CRACS 00S on

September 12. 1996.

The modification was completed and A train CRACS was returned to service

on September 27, 1996

On September 27. 1996, during-an internal review. licensee personnel

identified that locking tabs were tack welded to the cooling coil

mounting bolt heads without documented approval from engineering. The

licensee found that craft personnel had experienced difficulties with

tightening the cooling coil mounting bolts because the bolt head was not

accessible with the coils in place. The engineer and craft personnel  ;

determined the solution was to tack weld sheet metal locking tabs onto  !

the bolt heads to prevent them from rotating. The engineer discussed  ;

this solution with SCS. SCS stated that they did not see a 3roblem with '

the locking tabs so the engineer incorporated the locking ta)

installation into the WO. The licensee initiated FNPIR 1-96-263 to

document the problem. Mock-up testing was aerformed to assure that the

attachment process had not degraded the meclanical properties of the

bolts. The licensee produced a sample set of tab attached bolts using  !

l

Enclosure 2 '

.- _. - - - - - .- - - . . - - - - -- - .

.

\

'

.

2

.

13

the same material, welder etc.. as those installed. Testing involved

mechanical testing at FNP and metallurgical / nondestructive testing in i

Birmingham. Test results indicated that there was no adverse effect >

upon the life of the bolts with the attached tabs. The inspectors

reviewed the test results and concurred with the licensee's evaluation.

c. Conclusions

'

The inspector determined that overall the work was well coordinated and

craftsmanshi) was good. The licensee's responses to the deficiencies

were thoroug1 and well thought out. I

H2 Maintenance and Material Condition of Facilities and Equipment

M2.1 Steam Generator Intearity Maintenance and Testina

a. Insoection Scoce (73753)

Through licensee procedures, programs and associated records the

inspector reviewed the history of the Farley Units 1 and 2 SGs.

b. Observations and Findinas

Farley 1 and 2 are Westinghouse 3-loop units with series 51 SGs. Each  !

SG contains 3388 U-bend tubes made of Inconel 600. The nominal tube

outside diameter is 0.875 inch with a nominal wall thickness of 0.050

inch. In Unit 1. the tubes were ex)anded full length of the tube-sheet

using the Westinghouse Explosive Tu]e Expansion (WEXTEX) process: in

Unit 2. the tubes were expanded using a mechanical hardroll process. l

Both units have replaced their original anti-vibration bars (AVB) with  ;

adjustable 405 stainless bars.

'

Unit I reached initial criticality in August 1977, and to date has

completed thirteen (13) refueling outages. Tube degradation modes of

.

the Unit 1 SGs were as follows: l

l

e Outside Diameter Stress Corrosion Cracking (0DSCC) at Hot Leg l

Support Plates: (Confirmed by tube pull in 10/89 - R20C26

'

l

l from SG C.)

e Thinning at Lower Cold Leg Support Plates: (No significant change

l

'

in percent value since 1986.)

e ODSCC above Hot Leg Tubesheet: (Indications in sludge pile and in

free span area to first tube support plate. Confirmed by

tube pull in 10/89 - R20C26 from SG C.)

e Pitting above Cold Leg Tubesheet: (Confirmed by tube pull in

10/89 --R21C48 in SG C.)

e Primary Wate.' Stress Corrosion Cracking (PWSCC) at the WEXTEX Hot

. Leg Tubesheet Transition: (4/91 inspection was first  !

rotating pancake coil at the top of the hotleg WEXTEX

. transitions. Circumferential and axial indications have

Enclosure 2

i

__ . _ - _ _ . _ _ _ - _ . _ _ _ _ . . _ _ _ _ _ . _ _ _ _ . _ _ _ _

.

l

'

i

14 i

i

been reported since 4/91. Ultrasonic testing (UTEC)  ;

confirmed that all circumferential indications were  !

initiated from the inside diameter-of the tube.) i

e PWSCC in Low Row U-bends: (Row 1 tube preventatively plugged in  !

12/81. - Row 1 tubes unplugged and Rows 1 & 2 U-bends were ,

heat treated in 4/91.) +

e AVB Wear: (Indications represent old wear spots corresponding to i

locations of original AVB's, which were replaced with l

adjustable 405 stainless steel AVB's in the 1985 & 1986  !

outages.) '

e ODSCC at Free-Span Locations: (First identified during the 9/92 l

tube pull- (R18C40 - SG B.) No clear eddy current signals at

that time. In the 10/95 inspections, eight indications t

confirmed above the hot leg tubesheet and seven other indi-  !

cations confirmed in other hot leg free-span areas.)  ;

Status of Unit 1 SGs after the 13th refueling outage was as follows: ,

.SG_A SG_B SS_C i

Total Inservice Tubes: 3116 3223 3131 l

Total Inservice Sleeved Tubes: 56 37 115

Total Inservice Sleeves: 67 42 149 >

Total Plugged Tubes: 272 165 257 j

Cumulative Plugging Equiv. for 2.41% 1. 564% 5.212%  !

'

Sleeved Tubes:

Cumulative P1ugging Equivalent: 8.10% 4.92% 7.74% ['

Average Plugging Equivalent (All i

SGs) 6.92%

l

Unit 2 reached initial criticality in May 1981, and to date, has  !

completed ten (10) refueling outages. Tube degradation modes of the

'

Unit 2 SGs were as follows: ,

e ODSCC at Hot Leg Support Plates: (Confirmed by tube pulls' 4/86 - I

'

R31C46 and R38C46 from SG C.)

e ODSCC above Hot Leg Tubesheet: (Have not been confirmed by tube t

pull.to date. Minor intergranular attack observed on the '

outside diameter surface above the tubesheet in 10/90 - l

R19C48 from SG C.)  !

e _PWSCC at the Mechanical Roll Tubesheet: (Confirmed by tube pull'  !

in 4/89 - R16C50 from'SG C. Shotpeening was performed in .

10/87 and F* criteria implemented.)  !

e PWSCC in Low Row U-bends: (Row 1 tubes 3reventatively plugged in  :

10/82. Row 1 tubes unplugged and leat treated in 10/90. No  ;

indications to date.) l

Enclosure 2 i

!

, _

. . .

- . -

>

,

.

.

'

15

i e AVB Wear: (Indications represent old wear spots corresponding to 1

'

locations of original AVB's, which were replaced with

, adjustable 405 stainless steel AVB's in the 4/86 & 11/87

.

outages.) i

j- e Free-Span !.ocations: (Responsible for plugging of six tubes. Not

- characterized by a tube pull, but data suggests that the  ;

mechanism is most likely ODSCC.)

,

Status of Unit 2 SGs after the tenth refueling outage was as follows:

1

] SLA S_G_H SLC )

<

Total Inservice Tubes: 3074 3189 3190 i

i

Total Inservice Sleeved Tubes: 77 56 140 l

l Total Inservice Sleeves: 112 58 170

-Total, Plugged Tubes: 314 199 198 l

l

l Cumulative Plugging Equiv. for 4.04% 2.15% 5.99%

Sleeved Tubes:  !

i

j Cumulative Plugging Equivalent: 9.39% 5.94% 6.02% j

Average Plugging Equivalent (All l

-

SGs) 7.12%

i

3 c. Conclusions  !

'

The reviews of the current status, and the history of FNP SGs provided )

an indication that the licensee has been doing a conscientious job of

j

managing the SG degradation modes as they are identified.

1

i M3 Maintenance Procedures and Documentation  :

i

-

a. Insoection Scooe (73753)

,

The inspector reviewed licensee and contractor procedures for the eddy  !

current inspection of FNP SGs.

'

,

b. Observations and Findinas

'

Procedures reviewed included the following:

'

e Farley Nuclear Plant Surveillance . Test Procedure. FNP-2-STP-159.0.

" Steam Generator Inspection. Plugging and Repair." Revision 13. l

5 e Farley Nuclear Plant Systems Performance Procedure. FNP-2-SYP-3.0,

"

"SG Data Management." Revision 3.

'

i

!

i i

Enclosure 2 j

!  !

2

, _ _ - , , . ,,

.

.

.

16

e Westinghouse Nuclear Services Division Procedure No. MRS 2 4.2

APC-37. " Steam Generator Eddy Current Data Analysis Techniques."

Revision 1.

e Westinghouse Nuclear Services Division Procedure No. MRS 2.4.2  ;

APC-38, " Steam Generator Data Management." Revision 1  !

I

e Rockridge Technologies Procedure 42-EC-266. " Data Analysis Proce-  :

dure For Farley Nuclear Plant Units 1 & 2." Revision 0.

>

e Rockridge Technologies Procedure 42-EC-267. " Data Management

Procedure Farley Nuclear Plant Units 1 & 2." Revision 0.

'

'

The procedures reviewed were either new, or very recently revised.

procedures. These procedures and/or revisions were arepared as a result i

of the Unit 2 data management problem identified in _ER 50-364/96-002-00

and VIO 50-364/96-03-03. The completion of the procedures and revisions

were required to support SG inspections during U2RF11.  ;

c. Conclusions I

The licensee and contractor procedures for the evaluation and management  !

of SG eddy current data appear to be adequate for the circumstances.  ;

M6 Maintenance Organization and Administration

a. Insoection Scooe (73753)

Through review of documentation and discussions with licensee personnel,

the inspector reviewed the management involvement with the SG program.

b. Observations and Findinas

SNC intracom)any correspondence, dated-May 8, 1996 from: D. N. Morey,

forwarded "rarley Steam Generator'- Roles and Responsibilities." This

memorandum provided documentation of the assigned responsibilities for

the various facets of SG management.

The inspector met-with SG management personnel from the licensee's-

corporate office for a- presentation of the licensee's long range plans

and goals for the Farley SGs. The presentation.provided insights into

.the licensee's plans to systematically recover previously plugged SG

tubes by installing sleeves at the locations of the' degradation. The

presentation also provided various computer models of the projected

recovery process, which showed how the recovery and sleeving of plugged

tubes could be managed to maintain the plugging levels at or below 7%

per unit.

Er. closure 2

1

., _ _ ,_ -

- - . . _ -

.

.

.

17

'

c. Conclusions

The review of the history of the Farley SGs. as discussed in section M2

above, and the discussions with chemistry personnel, as discussed in

Section IV Plant Support of this ins)ection report. provided indication

that the licensee has been managing t1e degradation of the SGs even

though the integrated program for management has not been documented.

M8 Miscellaneous Maintenance Issues (92902)

M8.1 (Closed) VIO 50-364/96-03-03. Steam Generator Tube Flaws Within F*

Distance

The licensee's response dated June 27. 1996, provided a commitment to

revise and formalize instructions used by SG inspection data analysts

and data managers to ensure compliance with TS requirements. The

response also stated that a broadness review was in progress to review

FNP's safety related vendor services used to support safety-related

activities.

The inspector reviewed the close-out Jackage for Corrective Action

Report (CAR) No. 2193. Revision 0. T1e package contained copies of the

signature pages for the SG surveillance and data management procedures

which will be used in the up-coming Unit 2 outage. (The inspector also

reviewed the individual procedures as described in Section M3 above.) l

The CAR package also contained a ten question checklist for use in

conducting the broadness review to ensure that other safety related l

vendor activities are properly controlled. The CAR close-out contained l

tables showing seventy-nine (79) safety-related vendor-provided. 1

services and procedures that were reviewed during the broadness review  !

for this violation. j

M8.2 (Closed) LER 50-364/96-002. Misacolication of Technical Soecification

4.4.6 Reauirement Reaardina F' i

l

'

Root cause analysis and corrective actions for VIO 50-364/96-03-03. as

reported to NRC and described above, are sufficient to close this LER.

M8.3 (Closed) LER 50-364/95-001 and LER 50-364/95-001-01. Steam Generator

Tube Dearadation and Tube Status

The original LER (95-001) was provided to satisfy TS 4.4.6.5.c which l

requires that SG tube inspection results which fall in the Category of  !

C-3 shall be considered to be a reportable event and reported pursuant l

l to 10 CFR 50.73 prior to resumption of plant operation. The LER also

served to satisfy TS 4.4.6.5.a which requires that following each

'

inservice inspection (ISI) of SG tubes. the number of tubes plugged,

repaired or designated F*/L*, in each SG shall be reported to the

Commission within fifteen days of the completion of the inspection.

Enclosure 2

l

!

1

__ _ . _ _ . _ _ _ _ _ _ _ _ _ . _ _ _ _ . _ . _ _ _ _ _ _ _ . _ _ . . _ _ . . _ _ . . .

-

'

.

,

18

plugging, or repair effort. The revised LER (95-001-01) was issued to I

show the change in status of six tubes from F* to L* These LERs are  ;

considered closed. ,

!

M8.4 (Closed) LER 50-348/95-009. Steam Generator Tube Dearadation and Tube  !

Status i

This LER was provided to satisfy TS 4.4.6.5.c which requires that SG

tube inspection results which fall in the Category of C-3 shall be ,

considered to be a reportable event and reported pursuant to 10 CFR '

50.73 prior to resumption of plant operation. The LER also served to i

satisfy TS 4.4.6.5.a which requires that following each ISI of SG tubes. l

the number of tubes plugged or repaired, in each SG shall be reported to i

the Commission within fifteen days of the completion of the inspection.  ;

plugging. or repair effort. This LER is considered closed. '

(

III. Enaineerina

El Conduct of Engineering l

t

El.1 pm ian Chance Control Processes

l

'

n. insoection Scoce (37550)

The inspectors reviewed the licensee's procedures which control

the design change program. ]

>

b. Observations and Findinas  :

!

The inspectors reviewed the procedures listed below which control l

design changes and verified that the design control measures were i

consistent with 10 CFR 50. Appendix B. Criterion III and 10 CFR j

50.59. The following procedures were reviewed

FNP-0-AP-8. Design Modification Control. Revision 22. dated 3/1/96

FNP-0-AP-88. Nuclear Safety Evaluations. Revision 0. dated 2/1/96

'

From review of the above procedures the inspectors concluded that

'the following attributes were adequately addressed: design

processes, design inputs interface controls, design verification,

document control )ost-modification testing, control of field

changes, and 10 CFR 50.59 safety evaluations. The inspectors

concluded that adecuate controls were in piace to ensure effective

implementation of cesign changes.

.

1

Enclosure 2

- -. --

_ . _ - . . _ - _ _ _ _ _ _ _ _ . . _.__ _ _

_.__.____.____m __

.

'

.

.

'

19

c. Conclusions

l

The inspectors concluded that the licensee's design change control  :

procedures complied with the requirements of 10 CFR 50, Appendix  ;

B, Criterion III, and 10 CFR 50.59.  ;

E1.2 Review and Walkdown of Desian Chanae and Modification Packaaes  !

a. Insoection Scooe (37550)

The ins)ectors reviewed the design change and modification packages

listed ]elow to: 1) determine the adequacy of the safety evaluation

screening and the 10 CFR 50.59 safety evaluations: 2) verify that the  ;

modifications were reviewed and approved in accordance with TS and

'

.'

applicable administrative controls: 3) verify that applicable design 2

bases were included: 4) verify that UFSAR requirtwents were met.

'

b. Observations and Findinas

The inspectors reviewed the following design change and

modification packages:  ;

Desian Chanae Descriotion

S95-1-8857 Modification on Cable Tray Support No. 427

.

S95-1-8976 Repair of Main Steam Pipe Support MS-R205

l l

584-2-2915 Service Water 2" Diameter and Under Piping Replacement

S94-2-8752 Replacement of William Powell Service Water Valves

i

S95-2-8982 EDG 2B Exhaust Piping Hanger Support Modification

S96-1-9021 Repair of the Unit 1 Auxiliary i

Building / Containment Cork Interface in Room 186 l

Design Change numbers S95-1-8857..S95-1-8976 and S96-1-9021 were

i- completed. Design Change numbers S84-2-2915. S94-2-8752, and S95-2-8982

are scheduled to be implemented during U2RF11.

The inspectors found that the DCPs had been reviewed and approved

in accordance with the licensee's design control procedures and

that the format and content of the design changes were consistent

with design control procedures. The quality of the DCPs was good

,

)

Enclosure 2 I

!

_ l

- - . - . . - . - . . . - ~ . . . . - -------- - - - . - -

,

.

-

.

,

l 20

'

l

overall except for the minor discrepancies listed below in the

installation drawings for design change S95-2-8982. The discrepancies-

were as follows:

-

No general control dimensions were shown in the drawings.  ;

-

-

No dimensions were given in the drawings for unequal sizes (or

dimensions) of structural members such as TS 8X4. L4X3. Plate 4X2,

, etc. At least one dimension is required to be shown for member

l orientation so installation matches the design analysis.

-

Sheet No. 228B of Support SCS-2H228 should be interchanged with

Sheet No. 229B of Support SCS-2H229.

'

l -

Section C-C on Sheet No. 228B of Support SCS-2H228 should be

rotated 90 degrees to be consistent with Support SCS-2H229.

i

The licensee's engineers took action to revise the drawings to correct

l the above discrepancies. The scope of each design change package was

l found to be adequate. The 10 CFR 50.59 Safety Evaluations were found to

be adequate. Except for the discrepancies noted in design change S95-2-

'

8982, the installation instructions were considered adequate to

implement the modifications. The inspectors also verified that the <

l

'

UFSAR and other documents e.g., drawings and procedures, had been

identified in the modification packages for revision.

'

The inspectors walked down the completed modification for design changes

l S95-1-8857 and S95-1-8976. The inspectors examined the supports and

l compared the completed modifications with the design drawings. The

i

inspectors.found the.following discrepancies:  ;

SUDoort No. Discreoancies

'

i

Cable Tray DCP Discrepancy:

Support 427

The fillet weld located at inside of the north-west

flange for the 5" wide flange post connected to 1/2"

top plate was measured to be 3/16". The drawing

required 1/4" fillet weld.

,

Pipe Support Pre-existing Discrepanci6s: '

l MS-R205

1) All four pre-existing fillet welds were found to

have 3/16" weld size. The drawings-showed the weld

size to be 1/4".

1

,

2) Two fillet welds shown on the drawings did not

'

exist at the top ends of Item 2 connected to Item 1

(both L3x3) (flush condition existed at the back of

Enclosure 2

i

!

_ _ _ ....___ _ ._-

- _ . - _ . - . _ . _ . . _ _ . . - _ . _

~

.

-

i

,

-

j '

i 21  :

4

l

the two angles). The fillet welds could not be -

performed at these locations.

.

3) Item 4. 1/2"X7" Hilti Kwik anchor bolts, in the '

Bill of Materials on the drawings shows the number .

4

required to be four. The correct number is one.  !

i DCP Discrepancy:

)

" i

'

One weld between the 4X4 tube steel and the base plate

was not recorded in Weld Data Form WD-0100 by the

welder and had not been inspected. This weld was .

'

required to be recorded and visually inspected per  !

4

pre-determined weld data form by the modification ,

j planner-for ISI perpose, j

s

i Pre-existing discre)ancies refer to those that existed arior to

implementation of t1e design changes (modifications). )CP discrepancies

i are those that occurred during implementation of the design change. The

i

discrepancies listed above are considered additional examples of VIO 50-

348, 364/96-10-01, applicable to Unit 1 only.

l In addition, the inspectors also found insufficient groove bevel welds

!-

between the bottom plate and the existing 5X5 tube steel for the

modification to cable tray support 427. The groove bevel welds should

' be made flush with the tube steel wall. The inspectors considered this

slightly insufficient weld practice to be a weakness in the weld quality

, and workmanship.

.The preliminary investigation for the undersized weld at cable tray

support 427 was that this weld was not selected for inspection within

the 10 percent weld surveillance sample inspected by the foreman for-

final acceptance of the weld products. The Weld Data Form WD-0100

contained in the work. order package and Section 3.15 of Procedure FNP-0-

I

'

SPP-WD-001 " Documentation of Welding and Related Activities", of FNP - i

Special Process Manual FNP-0-M-23. only requires inspection of 10

'

percent of the welds completed.in each modification, unless engineering

t specifies additional inspections. The weld at the pipe support MS-R205

I

was not recorded on the weld data sheet and therefore was not inspected.

, .

'

t c. Conclusions

The above discrepancies -combined with those identified in NRC IR 50- ,

-

325, 324/96-07, indicates that the licensee's welding inspection program  !

may be deficient.

!

'

1 In general, the modification packages were judged to be of good quality.

y The modification packages contained sufficient specifications, drawings

, Enclosure 2-

4-

!

!

- _ ~

. . . . - - - - - _ - - - . ~ . . - - - - . - _ _ - - - - . . - . - . -

'

!

.

.

22 .

,

and 3rocedures for the installation. Two deficiencies were identified i

in t1e areas of the design drawing control and~ weld quality.

E1.3 Heavy Load Proaram

a. Insoection Scooe (37550)

The inspectors reviewed the licensee's procedures which control the

heavy load program.

b. Observations and Findinas

The inspectors discussed the Farley heavy load program with licensee 3

engineers and reviewed the current revisions of the procedures used for  !

controlling heavy load lifts and movements. Procedures reviewed were:  !

FNP-0-GMP-6.1 -6.4. -6.6. -57.0. -58.0: FNP-0-MP-11.0, FNP-1-MP-11.4:  :

'

and FNP-2-MP-11.4. These procedures were used to control the operation.

maintenance, inspection, testing, qualification, load paths, and  ;

operation of polar and mobile cranes, slings, load cells, lifting ,

devices, crane operators and riggers. Procedure Nos. FNP-1-MP-11.4 and

FNP-2-MP-11.4 for the reactor polar crane operations specify safe load

paths to limit the load traveling paths in order to prevent the loads ,

from accidently dropping into the reactor fuel and/or on safety-related  ;

components.  ;

,

The slings used for rigging were required to be visually inspected

annually and color marked after the inspections. Hoists were required

j

to be load tested annually and color marked also. The inspectors '

examined hand hoists stored in the cold tool room to verify the hoists

were marked with current color coded-red. No discrepancies were found.

c. Conclusions

The inspectors concluded that the procedures were adequate for control

and handling heavy loads. The licensee has established adequate

.

procedures for control of heavy loads for plant routine operations and

l

maintenance.

E1.4 Enaineerina Sucoort (ES) of Larae Scale. Comolex Evolutions (37551) ,

!

, The resident inspectors observed several major activities that involved I

l considerable engineering support, oversight, and interface by j

'

responsible engineers in the ES and Plant Modifications and Design (PMD) ,

departments. These actvities for the most  !

first time at FNP and represented complex,part were

resource beingtasks.

intensive done for.the

[ ES and PMD involvement was very evident and effective throughout the

j implementation of these activities:  ;

e Train A CRACS modification I

Enclosure 2 1

- _ _ .

.

_ . - - _. . - . - - - . . . _ - - . .- .- - -- - . -- --

.

-

.  ;

.

23

e Augmented Kaowool walkdowns

e 1A and 2A CCW HX epoxy coating ,

E7 Quality Assurance in Engineering Activities  !

'

E7.1 Quality Assurance Assessment and Oversiaht

a. Insoection Scooe (37550) .

The inspectors reviewed audits performed by the onsite Safety Audit and

Engineering Review group. i

b. Observations and Findinas ,

,

The inspectors reviewed the results of audits of engineering and

design activities. Audits reviewed were as follows:

-

Audit 94-PMD/09. Plant Changes and Modifications. An audit .

i finding was identified regarding failure to issue as-built i

!

notices for evaluation of equivalent parts for procurement. l

Several examples were identified. j

-

Audit 95-ISI/29-1 and 95-STP/95-1. Inservice Inspection and i

Surveillance Testing. An audit finding was identified

'

regarding an engineer who performed acceptance of a

containment leak test who was not properly certified to

accept and evaluate the results in accordance with licensee

procedures.

-

Audit 95-ISI/29-2. Inservice Inspection. Two audit findings

were identified regarding failure of a vendors performing

ISI activities to comply with site procedures. One finding

concerned an unqualified individual (a trainee) performing

eddy current testing. The other finding concerned improper

'

review of certificates of calibration for equipment used for

ISI work.

-

Audit 96-STPe/34-1. Engineering Support Surveillance Tests.

,

There were no findings in this audit. Two comments

!

concerning minor procedure discrepancies were included in

the audit report.

l -

Audit 96-CSP /04. Control of Special Processes. An audit

l finding was identified concerning nine examples of welding

l inspections which were not )erformed by independent

! inspectors. In all cases t1e foreman in charge of the work

performed the weld visual inspections. The licensee's weld

inspection program permits weld inspections to be performed

by foremen but not of work they were responsible for. The

i

Enclosure 2

l  !

,

.

.

24

weld inspections are known as peer inspections and are not

performed by independent quality control inspectors.

c. Conclusions

The ins)ectors concluded that the audits were useful in providing

oversig1t to management regarding performance of engineering

activities. The audit finding regarding non-independent weld

inspections is indicative of failure of the mainteriance foremen in

understanding the licensee's welding inspection program regarding

independent inspections. This issue, although it has been

corrected, is another example of a deficient weld inspection

program (see Section E1.2).

E7.2 Safety System Self Assessment Proaram

a. Insoection Scooe (37550)

The inspectors reviewed the results from the safety system self

assessment (SSSA) program.

b. Observations and Findinas

The licensee performed self assessments on 13 safety related

systems. The assessments were performed by independent teams of

individuals with design engineering and operations experience who

performed an in depth review of system design and operation. The

teams were supplemented with contract personnel experienced in

performing these types of assessments. The assessments were

performed between 1990 and 1995 and included the following,

systems: control room ventilation service water, residual heat

removal, emergency diesel generators, reactor protection, safety

related electrical distribution, auxiliary feedwater, instrument

air post accident sampling. component cooling, containment '

isolation, containment spray, chemical and volume control, high

head safety injection and accumulators, and reactor cooling water.

Findings from the assessments were reported as strengths or

weakness. Weaknesses were identified by an action item which

required a response from the plant to resolve. More than 400 '

weaknesses were identified in the assessments of the 13 systems.

These weaknesses resulted in a number of LERs. changes to the

UFSAR. changes to design basis calculations, design changes, and

changes to operating procedures.

The inspectors reviewed the SSSA results for the auxiliary

feedwater, service water control room ventilation, and containment

isolation systems. The inspectors also reviewed corrective

actions performed in resport ! to weaknesses identified in the

SSSAs. The inspectors concluded that the corrective actions were

Enclosure 2

. _ _ _ _ _ _ _ _ _ . _ . _ _ _ . _ _ _ _ _ _ _ _ _ _ - _ . _ _ _ _ _

l  :

.

.

25

appropriate to resolve the identified weaknesses. As of the

inspection date only six action items remained open to resolve all

the weaknesses identified in the 13 SSSAs.

!

c. Conclusions

The safety system self assessments were an effective program to

identify and correct deficiencies in design and operation of the i

13 systems assessed. Discussions with the licensee disclosed that  !

a new self assessment program to address balance of plant (non-

p safety related) systems is currently under review.

l

l IV. Plant Suooort i

R1 Radiological Protection and Chemistry Controls

,

R1.1 Tours of the Unit 1 and 2 Radioloaically Controlled Areas (71750) i

;

During the course of the inspection period the resident inspectors  !

l conducted numerous tours-of the. radiologically controlled area (RCA) of '

! the auxiliary building for Units 1 and 2. In general. Health Physics

l (HP) control over the RCA and the work activities conducted within it.  !

l were good. Material condition and housekeeping in the Unit 1 and 2 RCA

L were typically well maintained.

l  !

R1.2 Review of Water Chemistry Controls and History

l

a. Insoection Scooe (79501)

By walk-down inspections, interviews and document review, the inspectors

l examined the licensee's primary and secondary water chemistry controls

'

and history to verify compliance with commitments and regulatory  !

' requirements.

.

b. Observations and Findinas

The. licensee's on-line chemistry monitoring includes: cation conductiv-

.ity. monitors in 12 locations: specific conductivity monitors in six

_

'

locations: )H monitors in ten locations: sodium monitors in six loca- .

tions: two lydrazine monitors: and ten dissolved oxygen monitors. In _ l

addition the licensee has an in-line ion chromatograph with both units  !

, samples being routed over to it. Future plans are to shut down these

sample' streams and rely upon the SG blowdown analysis, when the Unit 1

streams are connected to the Unit 2 monitor. There were no in-line real-

.

time chlorine monitors.

I

The licensee indicated that they have removed all the co)per alloy

materials from the secondary side, of both units, with tie exception of

l the aluminum bronze (CA614) condenser tube sheets. -As a result of

sludge lancing the licensee has removed as much as 1885.5 lbs. of copper

l

.

Enclosure 2

,

4-, , ,

_ __ _ _ . _ .. __ __ _ _ _ _ _ _ _ _ _ _ _ _ _ . .

,

'

.

. ,

26

!

(Unit 1 refueling outage 2). more recently amounts under 300 lbs. were

removed. In-line instrumentation reported a total copper transport, for ,

a fuel cycle, at power levels above 30%, to be approximately 10 lbs, per

unit. The licensee has not identified any degradation to the aluminum

bronze tube sheets. The licensee has not chemically cleaned the SGs.  ;

The licensee explains the difference between ten and something less than

300 lbs. to be a redistribution of the circulating load of copper

deposited in earlier cycles. .

The licensee has adequate procedures to identify locate, and repair

condenser tube leaks.

The licensee's program for SG layup is adequate. j

c. Conclusions

The licensee's water chemistry controls were appropriate for the circum-

stances.

Status of Radiological Protection and Chemistry Facilities and Equipment

'

R2

R2.1 Monitorina of Primary-to-Secondary Leakaae *

i

a. Insoection Scooe (79502)

By walk-down inspections, interviews and document review, the inspectors  ;

evaluated the effectiveness of the licensee's procedures, equipment, and '

practices for monitoring primary-to-secondary leakage to verify compli-

ance with commitments and regulatory requirements.

b. Observations and Findinas

The licensee's actions related to NRC Bulletin 88-02. NRC Information

Notice Nos. 88-99. 91-43 and 93-56 were appropriate.

Primary-to-secondary leakage is monitored by real time N6 monitors

alarmed and annunciated in the control room at 5 gallons per day. In

addition, the licensee takes the following grab sam)les: gross

beta / gamma once per 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />; tritium once per monti: gaseous leak rate

once per month: gamma isotopic once per month: and steam jet air ejector

every 31 days, when no leakage is identified. The analysis periodicity

is progressively increased when primary to secondary leaks are

identi fied.

,

l The licensee does not perform condensate polishing. As a consequence, i

j the licensee was not concerned with regeneration or disposal of conden- l

! sate demineralizer resin and the associated effluent.

!

1

i

Enclosure 2

i

f-

'

1

_._ . . _ _ _ _ . . _ . . _ - . _.- _ . _ _. _ _ ._ . . _ _ _ _ _ . _ _ . - . . _ . -

'

i -

i

.  :

- , ,

.

27 j

l~ c. Conclusions

4

'

The licensee's current procedures. equipment, and practices for monitor-  !

ing primary-to-secondary leakage are appropriate. j

.

i R3 Radiological Protection and Chemistry Procedures and Documentation

R3.1 Review of Radioloaical Protection and Chemistry Records and i

j Documentation l

a. Insoection Scooe (79501) l

.

The inspectors reviewed the TSs UFSAR and selected procedures to  !

evaluate compliance of licensee's chemistry program with regulatory

, commitments procedural requirements and industry recommendations. 1

4

b. Observations and Findinas

, .

Except as noted below, the licensee's' procedures are consistent with the- .

r TSs. the UFSAR including in 3rocess changes, and Electric Power Research

1 Institute (EPRI) TR-102134. Revision 3. PWR Secondary Water Chemistry  ;

i Guidelines, and EPRI NP-7077. Revision 2, PWR Primary Water Guidelines.  :

i

Procedures for layup of SG are appropriate.  ;

'

i

-

'

e EPRI TR-102134 Revision 3 Table 2-1._ recommends, during cold

'

shutdown / wet layup (reactor coolant system (RCS) <200 F), once per

day dissolved 02 analysis. The licensee was unable to conduct

l- this analysis due to plant configuration.  !

- . i

e EPRI TR-102134. Revision 3. Table 2-2a recommends, during  ;

. heatup/ hot shutdown (RCS>200 F.to 5% reactor power), feedwater be '

.

analyzed once daily for pH# c

<

ppb. The licensee's procecIur. Dissolved 0. ppb and Hydrazine,esprovid ,

,

did not provide any periodicity.  ;

. e EPRI TR-102134. Revision 3. Table 2-2b recommends, during

heatup/ hot shutdown (RCS>200 F to 5% reactor power). SG blowdown.  :

l

be analyzed once daily for Chloride., pab and Sulfate, ppb. Due to

work load considerations the licensee las chosen to conduct these  !

analyses three times per week,

}

e. EPRI TR-102134. Revision.3, Table 3-5b. recommends, with the.

reactor critical -once per day analysis of_ Conductivity gS/cm @

, 25 C and pHa s.c. and once per week analysis.of Suspended Solids,

ppb and Silica, ppb. Due to work load and dose considerations the

licensee has chosen to conduct all these analyses once monthly-

except for pH 2s c, which they conduct once per week.

e The licensee primary to secondary program was based on EPRI NP-

7077. Revision 2. The licensee was currently in the process of

Enclosure 2

!

$

"

, _- .. _ _ _ _ -- _ .

.

.

.

28

updating their program to Revision 3 dated November 1995. The

target completion date was December 31. 1996.

e A review of procedures 1-SOP-69.0 R2. 2-SOP-69.0 R2. CCP-201 R54

1-ARP-1.6 R28,62-ARP-1.6 R21. and CCP-31 R18 revealed an inconsis-

tency in the N monitors set points stated in CCP-31. The li-

censee made an immediate procedure change to correct the inconsis-

tency. The N6 monitors in the field had set points properly set.

e As described in NRC IR 50-348.364/96-02, the inspectors noted a i

number of wheeled instrument carts, chairs. and work platforms ,

unsecured and unattended in the control room back board area. To

address this issue the licensee issued a Night Order dated March

6, 1996, directing personnel to keep wheeled furniture out of the

rack area when not in use and to assure that the wheels are locked

when these items are in the rack area. During this inspection the

ins)ectors noted several wheeled carts and chairs with wheels not l

locted or blocked, unattended in the rack area. Apparently the l

Night Order was ineffectual. '

c. Conclusions

The licensee's water chemistry program is in compliance with regulatory

requirements and with industry guidelines, with some exceptions.

R7 Quality Assurance in Radiological Protection and Chemistry Activities

R7.1 Review of the Audit History for the Primary and Secondary Water

Chemistry Control Proarams i

a. Insoection Scooe (79502)

l

The inspectors reviewed the last two licensee Chemistry STP audits, the

last two biannual Chemistry audits as well as a spot audit in response

to EPRI PWR Primary to Secondary 1.eak Guidelines, to verify compliance

with commitments and regulatory requirements.

b. Observations and Findinos  ;

Audit findings included weakness related to: alarm set points: control

of chemicals; improper response to air sample monitor alarm; improper

tag order implantation; shelf life:'and consistency with EPRI Guide-

lines. Appropriate corrective actions were taken or planned.

c. Conclusions

The area of primary and secondary water chemistry was subjected to

independent audits, with appropriate action taken for identified

weaknesses.

Enclosure 2

.. . _ . . __ _ __ _ _ _- .. _ _ _ - _ _ . _ _ _ ___ .__

.

'

.

29

j P4 Staff Knowledge and Performance in Emergency Preparedness

c P4.1 Emeraency Drill (71750)

i

Resident inspectors observed the conduct of two emergency plan (EP)

-

3ractice drills on September 11 and 18. and participated in the annual

i EP dress rehearsal conducted on October 9. 1996.

The inspectors observed licensee emergency response activities in the  !

plant simulator (simulated control room), emergency offsite facility.

'

technical support center. Operations Support Center. The drills and )

, dress rehearsal was well coordinated by the EP staff. Emergency

4

"

response facilities ap] eared adequate, with no real significant ,

ecuipment problems. T1e emergency response crews were effective in  !

acdressing onsite accident conditions and offsite consequences during  !

l the drills and exercise. In preparation for the annual exercise on

i December 11, 1996, the EP staff went to considerable lengths to simulate 1

NRC headquarters and site team play with additional plant em)1oyees. i

This effort added realism, and increased the communication clallenges '

, for the response crew, during the drill of September 18. and the dress  :

rehearsal. The inspectors participated in the subsequent drill and ,

<

dress rehearsal critiques, and provided their observations. '

S1 Conduct of Security and Safeguards Activities ,

S1.1 Routine Observations of Plant Security Measures (71750)

During routine inspection activities, resident inspectors verified that

. portions of site security program plans were being properly implemented.

1 This was evidenced by: 3 roper display of picture badges by plant

personnel: appropriate (ey carding of vital area doors: adequate

stationing / tours of security personnel: . proper searching of

packages / personnel at the Primary Access Point and SWIS: and adequacy'of

I compensatory measures (i.e., posting of guards) during disablement of

vital area barriers. Security activities observed during the inspection

<

period were well performed and appeared adequate to ensure physical

protection of the plant. Guards were observed to be alert and attentive

while stationed at disabled doors and access covers to critical

-underground equipment (e.g., SWS valve boxes and FOSTs). Posted

positions were manned with frequent relief.

'

S1.2 Search of Trailers Enterina The Protected Area (71750)

On October 10. 1996, a resident inspector observed security guards

escort a Westinghouse sludge lance trailer into the protected area'that

was not searched. The trailer was posted as a RCA. The security guard

outside the protected area gate did search the truck, cab and driver

prior to entering the protected area. However, he'did not search inside

the trailer because he did not have his personnel dosimetry. Also, the

shift security supervisor instructed him that a search would not be

Enclosure 2

-

,. .- - - - . - . - - - . . - . - - - - - - .

-

,

.

'

t

30

necessary based on her communications with a senior HP technician. The

l inspector also noticed that certain cargo spaces under the trailer which

were not part of the posted RCA, were not searched. All the cargo door

pad locks had been unlocked, apparently to facilitate a search. Pending

the inspectors actions to ascertain additional information on the

circumstances surrounding this incident, interview responsible ,

individuals and meet with the Security Chief, this issue is identified

as Unresolved Item (URI) 50-348, 364/96-09-05. Failure to Search

<

Contractor Trailer Prior to Entry into the Protected Area.

! F2 Status of Fire Protection Facilities and Equipment

F2.1 Installation and Insoection of Kaowool One-Hour Fire Barriers

a. Insoection Scooe (71750)

A detailed discussion of the initial inspection findings associated with

Kaowool one-hour fire barriers was documented in Section F2.1 of IR 50-

348, 364/96-07. Due to resident inspector concerns regarding the

l adequacy of Kaowool installation practices and independent inspection

program. URI 50-348. 364/96-07-03. Inadequate Installation and

l Inspection of Kaowool Fire Barriers, was identified. Since this initial

i inspection, the resident inspectors have conducted additional walkdowns

l of Kaowool installations in the plant interviewed responsible

personnel, reviewed ap)licable regulatory and FNP program requirements,

conducted meetings wit 1 plant staff and management, and monitored

licensee implementation of compensatory and corrective actions.

b. Qbservations and Findinas

! On September 3.1996, in addition to the discrepancies described in IR

96-07, an inspector identified some cable trays with Kaowool

l

installation deficiencies (flammastic fire seal installation and

degradation). During the exit meeting on September.5. the inspectors

l expressed concerns about problems with Kaowool installations. The

licensee promptly establish fire watches to address the immediate

'

concern of adequate fire safety, but did not consider conducting their

own inspections to ascertain the scope of the problem.

l

l On September 25. and 30. the inspectors conducted further walkdowns of

l

Kaowool cable tray installations and identified additional installation

deficiencies similar to those of September 3. All inspector identified

deficiencies were identified to the Operations SS and shift clerk. The

l shift clerks promptly initiated the appropriate compensatory actions

(i.e. fire watches) pursuant to the Fire Protection Program (FPP)

described in UFSAR. Appendix 9B. On October 2. the inspectors

identified three raceways that were not completely wrapped with Kaowool

as depir.ted by " Safe Shutdown Raceway and Identification of Kaowool ,

,

Wrap" .dr awings 0-180536. Revision 9. and D-203281. Revision 14. These

raceways were BDE-15 and BHF21 in Room 160 (1C Charging Pump power

Enclosure 2

!

,'

.. - - . - ~ -- - . - - -- -- . . - - - - - .

.

'

.

t

.

,

31

cables and control wiring) and BDE-15 in room 2159 (2C Charging Pump

power cables), and appeared to be part of the licensee's FPP for l

ensuring safe shutdown capability. ,

The licensee performed a preliminary engineering evaluation of the

raceways with missing Kaowool and informed the inspectors that the

drawings were in error and the raceway sections were not required to be

wrapped. A further, more detailed review by the licensee determined

that raceway BDE-15 (1C Charging Pump power cables) in room 160 was

required to be wrapped with a one-hour fire barrier to meet 10 CFR 50.

Appendix R requirements of SIII.G.2 as described by the UFSAR. Appendix

9B.

1

On October 2. the inspectors met again with licensee management to

discuss the continuing concern regarding the adequacy of Kaowool fire

barrier installations throughout the plant. After the meeting. the

licensee immediately initiated one-hour roving fire watches in every

room of the plant that contained Kaowool. Later that same day,

management briefed the inspectors on their Kaowool Action Plan which

included: Revising FNP-0-FSP-43, " Visual Inspection of Kaowool Wraps,"

Revision 5: Training additional personnel to perform comprehensive

Kaowool inspections: Performing walkdowns of all Kaowool installations

recuired by the Fire Protection Program for safe shutdown: Evaluating

anc correcting any identified deficiencies;. and updating the FPP and

Appendix R Compliance Report as needed.

On October 3. an inspector interviewed one of the two electricians

responsible for performing the most recent Kaowool inspection per FNP-0- i

FSP-43. This inspection had been conducted March 4-7, 1996. The

'

responsible electrician-stated that the drawings and raceway metal

labels were difficult to read. He also stated that he had never

installed or inspected Kaowool before the March 1996 inspections, nor

had he received any training, was not knowledgeable of Kaowool

installation or design requirements. UFSAR, Appendix 9B..Section 9B.6.1

of the FPP, requires an independent inspection program to verify fire

protection systems conform with installation drawings and test

procedures. Paragraph 9B.6.1.E. requires that the inspection program

includes measures to assure that personnel performing these inspections

are knowledgeable in the design and installation requirements for fire

)rotection. The failure to ensure inspection personnel were

(nowledgeable in the assigned inspection area was identified as an

'

example of an apparent violation (EEI) 50-348, 364/96-09-07. Inadequate

Kaowool Inspection Program.

The inspector reviewed FNP-0-FSP-43 to determine if it provided adecuate

guidance to the personnel performing the inspections. UFSAR, Appencix

9B, paragraph 98.6.1.F.1 requires that inspection procedures,

instructions, and checklists provide identification of characteristics

to be inspected. The inspectors found that the procedure only verified

that there were no breaks in the continuous run of Kaowool wrap. The

'

Enclosure 2

- _ _

_ _

.

.

32

inspectors determined that FNP-0-FSP-43 did not direct the inspection

personnel to examine the Kaowool for compression or the flammastic fire

seals for proper installation and deterioration. These are important

characteristics which ensure the Kaowool was installed, and maintained.

IAW original installation design requirements. Inspections conducted by

the NRC and the subsequent detailed walkdowns by the licensee identified

numerous deficiencies related to these characteristics. This failure of

the inspection procedure to identify all necessary design and

maintenance characteristics is another example of EEI 50-348. 364/96-09-

07. Inadequate Kaowool Inspection Program.

On October 4. the licensee trained approximately 24 Kaowool inspectors

and certified them as Level II inspectors to perform inspections of

Kaowool installation. The training focused on identification and

installation details. It consisted of 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of classroom

instruction and 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of on-the-job training in the plant. An

inspector observed the classroom portion of the training. At the

conclusion of the training the ins)ector observed that the trainees .

appeared to be confused. During oaservations by the inspector of some

of these personnel performing inspections, this confusion was apparent

during their inspections. The inspector also reviewed the proposed

inspection plan, ETP-3409. and determined it was adequate.

On October 5 the licensee commenced detailed Kaowool inspections of all

installations in the plant. All inspections were coordinated by the ES

Performance Review Group. A resident inspector observed three two-

person teams during the first four hours of inspection activities. The

first team observed by the resident inspector failed to identify an

apparent aroblem with the flammastic seal. This deficiency was on

raceway AED454 in Room 2316 which had no flammastic being visible eight

inches up the raceway. The resident inspector discussed this oversight

with the inspection team and the overall inspection coordinator. The

licensee coordinator agreed that this kind of deficiency should be

documented for further engineering evaluation. He then contacted each

team to ensure they understood this part of the installation criteria

and the necessity of documenting all deficiencies. The resident

inspector observed two more teams in the field and did not identify any

more performance problems. The resident inspector concluded that this

comprehensive inspection effort by the licensee should be adequate to

identify existing Kaowool installation deficiencies.

The licensee's inspection took about four days to complete and

identified the following:

l

1) The 1B and 1C Charging Pump (B train) power cables and room cooler

j cables in Room 175 of fire area 1-004 were not fully enclosed in a

i fire barrier having a 1-hour rating as required 10 CFR 50.

Ap)endix R and the FPP. In these four particular raceways (i.e.,

BDE-0A, BFDB06. BFDD15 and BHF-36) the Kaowool wrap was missing

,

Enclosure 2

i

l

1

.

33

for approximately 24 inches between the cable tray and the

opposing firewall.

2) Cables for Unit 1 main steam isolation and auxiliary feedwater

flow control in raceway BHFC33 that traversed across room 319 of

fire area 1-042 were not wrapped by Kaowool. The licensee had

failed to install the one-hour fire barrier required by the

Appendix R compliance report referenced by the FPP.

3) The licensee verified the resident inspectors finding that 18 feet

of raceway BDE-15 carrying power cables for the 1C Charging Pump

(B train) in Room 160 of fire area 1-004 was not enclosed in a

fire barrier having a 1-hour rating as required by 10 CFR 50.

Appendix R and the FPP.

4) Thirty-six deficiency reports (DR) were generated. The DRs were

broken down as follows:

Kaowool that has been compressed 21 DRs

Kaowool that is partially missing 5 DRs

Kaowool missing 5 DRs

Kaowool damaged or deteriorated 5 DRs

5) Over 100 instances were found where FNP-0-PMP-507 "Kaowool

Installation Procedure." Revision 5, was not strictly followed.

PMP-507. step 6.2.8. stated that "In areas such as floors, walls,

and ceilings where the blanket wrap ends, fire protection seals

shall be installed as specified using mastic coatings such as... ,

The sealant shall be troweled completely around the wra) ped cable

tray at the floor, walls, or ceiling. The seals shall 3e not less

than 1/4" thick and extend not less than 8" onto the Kaowool and

not less than 8" onto the floor, wall or ceiling." The licensee  !

inspection identified numerous junctions where the flammastic was i

not troweled for 8" completely around the Kaowool wrapped cable i

tray and/or did not extend 8" onto the floor, wall or ceiling. In I

many instances, the flammastic was also cracked. damaged, or )

indeterminate due to the Zetex outer wrap. i

FOL NPF-2. Condition 2.C(4), and FOL NPF-8. Condition 2.C(6), prescribes '

i

that Southern Nuclear shall implement and maintain in effect all

provisions of the approved FPP as described in the UFSAR. Appendix 9B. )

Items 1) through 3) above represent examples where the licensee failed j

to install one-hour fire barriers as specified by the 10 CFR 50. l

Appendix R program described in the FPP. These noncompliant conditions

are identified as EEI 50-348/96-09-06. Failure to Install Required One-

hour Fire Barriers.

Items 4) and 5) above. are additional performance-based examples of the l

inadequacy of the licensee's independent inspection program to verify

Kaowool fire-barriers properly installed and maintained in the plant. '

Enclosure 2

l

- - - - .- -- - . - - - . . . - - - - - . . - .

.

.

-

i

.

34

Section 9B.6.1 of the FPP. requires an independent inspection program to

verify fire protection systems conform with installation drawings and

test procedures. Fire Surveillance Procedure. FNP-0-FSP-43. " Visual '

Inspection of Kaowool Wraps." Revision 5. provided the acceptance

criteria, instructions, and references for installation details for

conducting inspections of Kaowool wraps used to provide the 1-hour rated ,

fire barriers prescribed by the FPP. The number of longstanding 1

deficiencies identified in the ETP-3409 inspection plan demonstrated

that the Kaowool inspection program was ineffective. This is another

example of EEI 50-348. 364/96-09-07. Inadequate Kaowool Inspection

Program.

A resident inspector also )erformed reviews of the Kaowool Qualification

testing documentation whic1 the licensee provided in res)onse to

questions regarding what configuration was required for (aowool

terminations at walls and ceilings and the effects of uninsulated

conduits and support penetrating the Kaowool wraps. The ins)ector was

not able to conclude that plant configurations were within t1e scope of

the tested ccafiguration based on the documentation provided by the

licensee. The qualification test configurations consisted of a Kaowool i

wrapped raceway and conduit extending through a catenary furnace. In  ;

all cases the Kaowool wraps extended twelve inches )ast the ends of the

furnace. The furnace openings were then sealed witi Kaowool and

firebrick dust. These tests do not appear to reflect the configuration l

' of a Kaowool wrap butting against a fire rated barrier, nor penetrating I

conduits and supports, which are used throughout the plant. The tests

indicate that any gaps in the Kaowool wrap will significantly degrade

its effectiveness. This issue is identified as URI 50-348, 364/96-09-

08. Adequacy of Kaowool Qualification Tests to Scope Installed

Configurations. Resolution of this item will require additional review

of the Kaowool Qualification test report and inspection of plant

specific configurations by the NRC.

c. Conclusions

1

'

The inspectors identified two apparent violations regarding 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> rated

fire barriers. One apparent violation was for failure to install

required one-hour fire barriers. The second apparent violation was for

a failure to have an adequate inspection program for Kaowool fire

barriers. The inspectors also opened URI 50-348, 364/96-09-08. Adequacy

of Kaowool Qualification Tests to Scope Installed Configurations,

pending further NRC review.

!

Enclosure 2

1

. _ _ _.._ _ _ _ _ _ __ _ _ . - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _..~ . _ _

.

.

.  !

35 i

F5 Fire Protection Staff Training and Qualification ,

F5.1 Fire Briaade Drill

a. Insoection Scoce (71750) i

On September 30. 1996, a resident inspector observed the actions of the ,

dayshift fire brigade during a scheduled drill. I

b. Observations and Findinas

Fire protection training personnel notified the control room of a

simulated fire at the onsite Water Treatment Facility. The dayshift .

fire brigade mustered at the emergency response van and drove to the )

Water Treatment Facility towing the fire hose trailer. Fire brigade  ;

members donned appropriate protective clothing, including self-contained '

breathing apparatus, and laid out the necessary fire hoses from the i

closest hydrant station to the simulated fire. Brigade members, under  !

direction of the brigade leader then demonstrated appropriate fire i

fighting techniques. Afterwards, a criti ue of the drill was conducted '

by the drill director with the entire bri ade.

c. Conclusions

,

Fire brigade response was timely. Fire fighting equipment was in good

!

condition. Brigade member actions demonstrated proficiency in fire

fighting capability. The drill scenario was adequate.

F8 Miscellaneous Fire Protection Issues (71750)

F8.1 (Closed) URI 50-348. 364/96-07-03. Inadeauate Installation and

lnsoection of Kaowool Fire Barriers

This URI is closed based on the written discussion and the EEIs

identified in Section F2.1.

V. Manaaement Meetinas and Other Areas

X1 Review of UFSAR Commitments

'

A recent discovery of a licensee o)erating their facility in a manner

contrary to the UFSAR description lighlighted the need for a special

focused review that compares plant practices, procedures and/or

parameters to the UFSAR descriptions. While performing the inspections

discussed in this report, the inspector reviewed the applicable portions

l

'of the UFSAR that related to the areas inspected. The inspectors

verified that the UFSAR wording was consistent with observed plant ,

practices, procedures and/or parameters. Certain exceptions were  !

identified as follows. 1

!

'

Enclosure 2

.

m -

r- --

.

.

.

36

e UFSAR Appendix 98. Attachment B. 10 CFR 50 Appendix R Exemptions.

Section 29.2 states " intervening combustibles between redundant

service water valves for CCW are minimal, consisting of primarily -

of cable insulation." Licensee failed to control the. storage and

placement of intervening combustibles between redundant SW inlet  !

valves to the CCW HXs during epoxy work on the 1A 2A.1B and 2B  !

CCW HXs. Positive controls were put in place during work on the  !

1C and 2C CCW HXs. Refer to section M1.2.

e UFSAR Appendix 9B. Attachment B. 10 CFR 50 Appendix R Exemptions,

described Kaowool wraps which should have been installed but were

actually missing. Refer to section F2.1.

X2 Exit Meeting Summary

The resident inspectors presented the inspection results to members of

licensee management on October 17, 1996, after the end of the inspection

period. The licensee acknowledged the findings presented.

The resident inspectors asked the licensee whether any materials

examined during the inspection should be considered proprietary. No

proprietary information was identified.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

W. Bayne, Chemistry / Environmental Superintendent

R. Coleman. Maintenance Manager

P. Crone. Training Supervisor  !

S. Fulmer. Technical Manager

H. Garland. Assistant Maintenance Manager

D. Grissette. Operations Manager

R. Hill General Manager - Farley Nuclear Plant

C. Hillman Security Chief

R. Martin. Su)erintendent Operations Support ,

M. Mitchell, iealth Physics Superintendent  !

C. Nesbit. Assistant General Manager - Support

J. Odom. Superintendent Unit 1 Operations  ;

- J. Powell. Superintendent Unit 2 Operations '

R. Rogers. . Supervisor. Engineering Support

L. Stinson. Assistant General Manager - Plant Operations

J. Thomas. Engineering Support Manager

Enclosure 2

. . _ - _ _ _ _ _ . _ _ _ _ _ _ _ _ _ . _ - . _ _ _ _ _ _ . _ _ .

.

-

. i

l

.

t

37

,

B. Yance. Plant Modifications and Maintenance Support Manager

W. Warren. Engineering Support Supervisor - Performance Review

G. Waymire. Safety Audit and Engineering Review Site Supervisor

L. Williams. Training and Emergency Planning Manager >

l

NRC

!

J. Zimmerman. NRR Project Manager - Farley Nuclear Plant

INSPECTION PROCEDURES USED

IP 37550: Engineering  !

IP 37551: Onsite Engineering

IP 40500: Effectiveness of Licensee Controls in Identifying. Resolving, and

Preventing Problems ,

IP 61726: Surveillance Observations .

IP 62707: Maintenance Observations  :

IP-71001: Licensed Operator Requalification Program Evaluation *

IP 71707: Plant Operations >

IP 71750: Plant Support Activities

IP 79501: PWR Water Chemistry Control and Chemical Analyis - Audits i

IP 79502: Plant Systems Affecting Plant Water Chemistry

'

IP 73753: Inservice Inspection .

'

IP 92901: Followup - Operations '

IP 92902: Followup - Maintenance ,

IP 92904: Followup - Plant Support

ITEMS OPENED CLOSED, AND DISCUSSED

!

Ooened l

1

Iygg Item Number Status Descriotion and Reference

-VIO 50-348, 364/96-09-01 Open Multiple Valve Misalignments By '

System Operators (Section 01.5)

NCV 50-348.-364/96-09-02

-

Open Untimely Incorporation of TS

Amendment Into Plant Procedures

! (Section 03.1)

IFI 50-348. 364/96-09-03 Open Inconsistent Application of Remedial

l Training Documentation Guidance

'

(Section 05.1)

i IFI 50-348. 364/96-09-04 Open CCW HX Epoxy Coating And Broken

Tubes (Section M1.2)

1

Enclosure 2

L

!-

.

'

.

.

38

URI 50-348. 364/96-09-05 Open Failure to Search Contractor Trailer

Prior to Entry into the Protected

Area (Section S1.2)

EEI 50-348/96-09-06 Open Failure to Install Required 1-hour

Fire Barriers (Section F2.1)

EEI 50-348, 364/96-09-07 Open Inadequate Kaowool Inspection

Program (Section F2.1) '

URI 50-348. 364/96-09-08 Open Adequacy of Kaowool Qualification i

Tests to Scope Installed ,

Configurations (Section F2.1)

Closed

.

Iygg Item Number Status Descriotion and Reference

,

IFI 50-348, 364/95-12-01 Closed Lack of Measurable Performance

Indicators Due to Use of WOG ERG

(Section 08.1)

i

URI 50-348, 364/96-07-03 Closed Inadequate Installation and

Inspection of Kaowool Fire Barriers

(Section F8.1)

NCV 50-348, 364/96-09-02 Closed Untimely Incorporation of TS

Amendment Into Plant Procedures

(Section 03.1) l

l

VIO 50-364/96-03-03 Closed Steam Generator Tube Flaws Within F.

Distance (Section M8.1). l

l

LER 50-364/95-001 & Closed Steam Generator Tube Degradation and

LER 50-364/95-001-1 Closed Tube Status (Section M8.3).

LER 50-348/95-009 Closed Steam Generator Tube Degradation and

Tube Status (Section M8.4). q

LER 50-364/96-002 Closed Misapplication of Technical

Specification 4.4.6, Requirement

Regarding F*- (Section M8.2).

I

' Enclosure 2

.

- _ . _ _ . -_ .... - .... . _ _ . _ . _ . . _ . _ . . _ - _ _ . _ - _ _ . _ _ _ _ _ _ _ _ _. __ _ __ _ _

,

p .

.

v

39  ;

{ .

j LIST OF ACRONYMS USED l

t

ARP Annunciator Response Procedure

a

AVB Anti-Vibration Bar

Corrective Action Report

'

CAR  ;

1 CCP Chemistry-Radiochemistry Procedure

. CCW Component Cooling Water '

1

CFR Code of Federal Regulations

I

CRACS Control Room Air Conditioning System

i

DBA Design Basis Accident *

- DCP Design Change Package

DR Deficiency Report ,

! EDG Emergency Diesel Generator

EEI Escalated Enforcement Item

EP Emergency Plan

EPRI Electric Power Research Institute

r- EPB Emergency Power Board

ES . Engineering Support group ~;

ETP Engineering Test Procedure  !

'

F* A TS-defined SG tube acceptance criteria

FHP Fuel Handling Procedure

FNP Farley Nuclear Plant

FNPIR Farley Nuclear Plant Incident Report  :

FOL Facility Operating License

FOST Fuel Oil Storage Tank

FPP Fire Protection Program

HP- Health Physics

HX Heat Exchanger

IAW In Accordance With

IFI Inspector Followup Item

lbs. Pounds

IP Inspection Procedure

IR Inspection Report

ISI Inservice Inspection

JPM Job Performance Measure

L* A TS-defined SG tube acceptance criteria

- LCO Limiting Condition for Operation

LER Licensee Event Report

- MCB Main Control Board

MCR Main Control Room-

-MTG Main Turbine Generator

NCV Noncited Violation

NDR Nonconformance Disposition Report

NIS Nuclear Instrumentation System

- N" Nitrogen 16 isotope

NRC U.S. Nuclear Regulatory Commission

NRR- Office of Nuclear Reactor Regulation

0 Gaseous Oxygen _- i

ObSCC Outer Diameter Stress Corrosion Cracking l

00S Out of Service  !

Enclosure 2 l

l

,

.__ _. ~. . _ . . . _ _ . - . . _ _ . . _ . _ . - . . - - - - _ . _ - _ .

,

.

.

>

.

40

i

PWSCC Primary Water Stress Corrosion Cracking

PDR Public Document Room

pH The negative logarithm of the hydrogen concentration.

pH .c )H determined at 25 C

l ns 3 arts Per Billion

M Project Manager ,

PMD Plant Modifications and Design group

PMP Plant Maintenance Procedure

l PWR Pressurized Water Reactor

i

'

RCA Radiologically Controlled Area

RCS Reactor Coolant System

REA Request For Engineering Assistance

l SCS Southern Company Services

l SFP Spent Fuel Pool

SG Steam Generator

'

SGFP Steam Generator Feed Pump

SNC Southern Nuclear Operating Company

SO System Operator

<

S0P _ System Operating Procedure

l SR0 Senior Reactor Operator

l SRST S)ent Resin Storage Tank

i

SS S11ft Supervisor l

l SSSA Safety System Self Assessment

.

STP Surveillance Test Procedure '

l

SW Service Water -

SWS Service Water System ,

'

-SWIS Service Water Intake Structure

,

'

Tm Average Reactor Coolant System Temperature ,

'

T Reference Program Temperature

TEdFW Turbine Driven Auxiliary Feedwater

TO Tag Order

TS Technical Specifications l

U2RF11 Unit 2 eleventh refvaling outage

UFSAR Updated Final Safei.y Analysis Report -

<

URI Unresolved Item l

' UTEC Ultrasonic Testing )

VCT Volume Control Tank l

VIO Violation i

WO Work Order l

WEXTEX Westinghouse Explosive Tube Expansion i

U

L

L

.

4

J

! Enclosure 2

!

!

!

l