Text

F e -

Consumers Donsed 8 Miller, Jr Power su,u ,

Company =a ' *a Midland Project: Po Box 1963, Midland, MI 48640 *(517) 631-8650 VLfgg JPRP p/RA DE October 14, 1983 If/RA wasF 4<C JiRn URMA g , gcf DAO SCS#24;t-J 60 330 TA ML O L TF File Jt/g Mr R A Hartfield Chief, Management Information Branch Office of Management and Program Analysis U S Nuclear Regulatory Commis.sion Washingten, DC 20555 MIDLAND ENERGY CENTER GWO 7020 NRC SCHEDULE File: 0652 UFI: 53*54 Serial: CSC-6954 In lieu of submitting a yellowbook update for the third quarter 1983 we elect to discuss herein the current construction status of the Midland Project.

On December 2, 1982, essentially all Q related construction work on the project ceased pending resolution of recognized quality related problems. Since then, a concerted effort towards developing the Midland Project Construction Completion Plan has been expended. As a result, on October 6, 1983 we received a NRC Board Order to the Midland Construction Permit to complete the project in accordance with the CCP. The schedule for completing the project under this new concept is currently under development and will not be finalized until release of work under the CCP is received sad some experience is gained. Consequently, we request approval to postpone a yellowbook update until a definitive schedule can be developed. A prompt submittal will be made at that time.

Please advise if the above does not meet with your approval.

/

g'A/ a<

DBM/DDJ/ kip cc: Mr James G Keppler, Regional Director, Region III Mr J J Harrison, Midland Project Inspector, Region III Mr Frederick C Williams, Isham, Lincoln and Beale, Washington Mr Phil Steptoe, Isham, Lincoln and Beale, Chicago 8310250058 801014 PDR A ADOCK 05000329 Jh/

PDR f 6 OCI 2 1 ISO 3