Forwards Revision to Tech Spec Table 15.4.1-1 Re Periodic Testing of Auxiliary Feedwater Sys Automatic Actuation Logic.Nrc Review of Tech Spec Change Request 76 Should Include Addl Change
ML20054K847
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/30/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Clark R, Denton R
Office of Nuclear Reactor Regulation
Shared Package
ML20054K848 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.E.1.1, TASK-2.E.1.2, TASK-TM TAC-48373, TAC-48374, TAC-53271, TAC-53272, NUDOCS 8207060214
Download: ML20054K847 (3)


Text

Wisconsin Electnc ma coursur 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 June 30, 1982 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U. S. NUCLEAR REGULATORY COMMISSION Washington, D. C. 20555 Attention: Mr. R. A. Clark, Chief Operating Reactors Branch 3 Gentlemen:

DOCKET NOS. 50-266 AND 50-301 MODIFICATION TO TECHNICAL SPECIFICATION REQUEST NO. 76 AUXILIARY FEEDWATER SYSTEM OPERABILITY POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 On April 27, 1982, Wisconsin Electric Power Company submitted a license amendment application to the NRC to incorporate certain changes into the Point Beach Nuclear Plant Technical Specifications to further define minimum operability requirements for the auxiliary feedwater system. On May 5, 1982, we sent a letter which provided a correction to this license amendment application. Subsequently, we received on May 7, 1982 your letter dated May 3, 1982 which transmitted the Staff's safety and technical evaluations of NUREG-0737, Item II.E.1.2, Auxiliary Feedwater System Automatic Initiation and Flow Indication. This letter concluded that contingent upon completion of the items identified in the safety evaluation, the Staff would consider this item resolved for the Point Beach facility.

Among the items identified in the safety evaluation is a request that the Point Beach Technical Specifications be revised to include periodic testing of the auxiliary feedwater system automatic actuation logic. Accordingly, we proposed to revise Ttem 11 of Technical Specification Table 15.4.1-1 to read as follows:

8207060214 820630 DRADOCK05000g g\

Mr. II . R. Denton June 30, 1982 CIIANNEL DESCRIPTION CIIECK CALIBRATE TEST REMARKS

11. Steam Generator Level S** R M(1) *
  • 1) Includes test of logic for reactor trip on low-low level and automatic actuation logic for auxiliary feedwater pumps We have attached a revised page for the Technical Specification which includes this change. It is requested that your review of our Technical Specification Change Request No. 76 be modified to include this additional change proposed at your reques*.

Your May 3 letter also requested that we inform you of the schedule for completion of the auxiliary feedwater system modifications identified in the safety evaluation. These modifications are to upgrade flow indication power supplies, to provide a continuous indication in the control room of motor-driven auxiliary feedwater automatic initiation bypass when the main or auxiliary feedwater pump control switches are placed in pull-out position, and to modify the auxiliary feedwater system automatic actuation circuitry to allow periodic testing which will verify proper operation of the relay coil / contact combination used to initiate auxiliary feedwater on steam generator s

low-low level.

The first of these modifications, the upgrade of the auxiliary feedwater flow indication power supply, is dependent upon completion of the instrument bus modification presently underway. As discussed in our April 26, 1982 letter reporting on the status of NUREG-0737 items, the instrument bus modifications, which include new batteries, inverters, and chargers, will not be completed until June 1983.

The other modifications, a switch in pull-out annunciation and actuation test circuitry addition, have not been initiated. We anticipate we shall be able to design, approve, and install these modifications by the end of 1982.

5 I

Mr. H. R. Denton June 30, 1982 Accordingly, we also request that the Technical Specification change request modification described earlier in this letter not be made effective until after these modifications have been completed.

As required by the Commission's regulations, we have enclosed three signed originals and 40 copies of this modifica-tion to our application.

Please contact us if you have any questions regarding these changes or commitments.

Very truly yours,

/.,

Assistant Vice President C. W. Fay Attachment Copy to NRC Resident Inspector Subscribed and sworn to before me this 3a g day of June 1983.