ML20043B110
| ML20043B110 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 05/17/1990 |
| From: | Fay C WISCONSIN ELECTRIC POWER CO. |
| To: | Davis A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| CON-NRC-90-050, CON-NRC-90-50 IEB-79-14, VPNPD-90-239, NUDOCS 9005240201 | |
| Download: ML20043B110 (3) | |
Text
-
.~
~
Wisconsin Electnc V
POWER COMPANY 231 W MichWn, Po. Box 204$. Mdwoukee. VA $3201 (414)224 2345 VPNPD-90-239 NRC-90-050 May 17,-1990
[
Mr. A. Bert Davis-Regional Aduinistrator, Region III~
l U.
S. Nuclear Regulatory Commission 799 Roosevelt Road 1
Glen,Ellyn, IL'60137 l
Dear Mr.-Davis:
j DQQTt? 50-266 AND 50-301 IE_DULLETIN 79-14 POINT BEACli NUCLEAR PLANT, UNITS-1 AND 2 4
Reference:
- 1) WE letter VPNPD-89.-429/NRC-89-096 to_Mr.-A. Bert.
Davis, dated' August 04, 1989.
2)'WE Letter VPNPD-89-478/NRC-89-105~to Mr.'A'.:-LBert Davis, dated August-31,.1989.
{
'3) WE Letter VPNPD-89-436/NRC-89-098 to'Mr.'A.<Bert.'
j Davis, oated? August' 08, 1989.
-(
This letter documents the status of the_ evaluations committed to.
j be performed by Reference,1.regarding'theiIEB 79-14 program-for, j
the Poitt-Beach Nuclear Plant.
Each item below is numbared in,a-01 manner consistent with the order of the commitments in I
~
Reference 1.'
i
- 1. Additional sampling of fifty piping support ~ calculations-was a
performed in 1989 and the results were presanted to the NRC
(
in Reference 2.
- 2. The modification of the four integral 1 welded-attachment (IWA)' piping supports is being implemented.
The two supports identified as.part of the Unitt1 systems have been q-modifled-during the current. Unit ~1 refueling outage,-and the-two piping -supports associated with Ur.it 2~ will be modified _ _
7 during the Unit 2 refueling outage thisifall.- This' revised 1
schedule was discussed with Mr. Gavula of your' office'on' December 4, 1989 and supersedes the-original schedule 1
proposed in Reference l'.
l
~!
m 5
9005240201 900517 6
l ADOCK0500g6 PDR a
&pl n
AsassaudonnavnshEnugyCovpnum ;
x
Mr. A. Bert Davis L
May 17, 1990 Page 2
'3. Review of the remaining integral welded attachment (IWA) calculations that Bechtel had performed-as part of the original IEB 79-14 project was completed in February,.1990.
As a result ~of the re-calculations only one. additional' support required modification to meet applicable Code allowabies,.although operability allowables were met.-
This support (CH-151-4-H50)-was-modified during the Unit 1 refueling outage-and now is in Code' compliance.
Another IWA i
anchor.is currently being reanalyzed'as part ofLIEB 88-08 work.
This support,-a pressurizer spray line anchor 1"
(RC-2501R-1-2A4) which has'been determined to be operable-with the current design 1oads,31s' undergoing further 1
detailed analysis to determine whether-it.can:moet. existing Code allowables.
The total population of IWA supports evaluated for the effects of localized stresses is 49, including-the IWA supports previously reported.
Five of these 49 were required to be modified.
Additionally, 48 IWA supports-were-evaluated as a result of the reanalysis of the.RHR systems outside containment.
Due to significant load l increases, 3 of these IWA supports required modification.
SevenLIWA supports were evaluated as.a result of'the1 reconciliation-of the as-found piping-identified in item 4, below.
No
'a modifications were. required as a result of these evaluations.- In summary, a total of 100 IWA calculations were created as part of the IEB;79
~.4 closecut effort resulting in no operability allowable violations and 8 piping support modifications.
- 4. Walkdown of the fifteen. additional piping subsystems were L
completed by November 30,1990, as committed to in.
Reference 1.
The discrepancies between the. current walkdowns and the.as-built analyses required reconciliation cniculations'and.3 new piping subsystem analyses.
'As a i
result of these reanalyses, 48 piping support loads were increased.
These load increases resulted in 41 calculations and 7 documented evaluations.
Those supports that did not meet Code compliance with the new' loads.were evaluated for.
operability and were shown to meet operability limits.
The 10 supports associated with Unit 1 were modified during the Unit'l refueling outage, and the 2 supports asecciated with Unit 2 will be modified this fall.
o
-=
2w
+ee,,=
g-gr
<e y
l-e
- 3..
l a
Mr. A. Bert Davis May 17, 1990 Page 3 i
- 5. The-Justification for Continued' Operation (JCO)' criteria-1 for Major "As-built" Discrepancies ir. Safety Related Piping l'
Systern was submitted for review and concurrence by.
1 Reference 3 in August, 1989, as originally committed'to by Reference 1.' -NRC concurrence was obtained in November, 1
1989.
j
.The results of the evaluations, calculations and resnalyses are.
currently being finalized and summarized at this-time.
]
Electric. proposes to meet'with Region III during'the week of June j
18, 1990 or the week of. July'16, 1990 to present the complete 1;
results of these programs..
Please advise us of a'date that-would be acceptable for you.
We expect the meeting to last approximately 2-3 hours.
Very truly yours, 0W
~
C. W. Fay Vic'e President 3
Nuclear Power Copy to Resident Inspector Document Control Desk
-I l
_ _ _ _ _ _ - _ _ - - - _ _ - -