ML20043B110

From kanterella
Jump to navigation Jump to search
Documents Status of Evaluations Committed to Be Performed Re IE Bulletin 79-14 Program.Support CH-151-4-H50 Modified During Unit 1 Refueling Outage & Now in Code Compliance. Meeting Proposed During Wks of 900618 or 900716
ML20043B110
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/17/1990
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
CON-NRC-90-050, CON-NRC-90-50 IEB-79-14, VPNPD-90-239, NUDOCS 9005240201
Download: ML20043B110 (3)


Text

-

.~

~

Wisconsin Electnc V

POWER COMPANY 231 W MichWn, Po. Box 204$. Mdwoukee. VA $3201 (414)224 2345 VPNPD-90-239 NRC-90-050 May 17,-1990

[

Mr. A. Bert Davis-Regional Aduinistrator, Region III~

l U.

S. Nuclear Regulatory Commission 799 Roosevelt Road 1

Glen,Ellyn, IL'60137 l

Dear Mr.-Davis:

j DQQTt? 50-266 AND 50-301 IE_DULLETIN 79-14 POINT BEACli NUCLEAR PLANT, UNITS-1 AND 2 4

Reference:

1) WE letter VPNPD-89.-429/NRC-89-096 to_Mr.-A. Bert.

Davis, dated' August 04, 1989.

2)'WE Letter VPNPD-89-478/NRC-89-105~to Mr.'A'.:-LBert Davis, dated August-31,.1989.

{

'3) WE Letter VPNPD-89-436/NRC-89-098 to'Mr.'A.<Bert.'

j Davis, oated? August' 08, 1989.

-(

This letter documents the status of the_ evaluations committed to.

j be performed by Reference,1.regarding'theiIEB 79-14 program-for, j

the Poitt-Beach Nuclear Plant.

Each item below is numbared in,a-01 manner consistent with the order of the commitments in I

~

Reference 1.'

i

1. Additional sampling of fifty piping support ~ calculations-was a

performed in 1989 and the results were presanted to the NRC

(

in Reference 2.

2. The modification of the four integral 1 welded-attachment (IWA)' piping supports is being implemented.

The two supports identified as.part of the Unitt1 systems have been q-modifled-during the current. Unit ~1 refueling outage,-and the-two piping -supports associated with Ur.it 2~ will be modified _ _

7 during the Unit 2 refueling outage thisifall.- This' revised 1

schedule was discussed with Mr. Gavula of your' office'on' December 4, 1989 and supersedes the-original schedule 1

proposed in Reference l'.

l

~!

m 5

9005240201 900517 6

l ADOCK0500g6 PDR a

&pl n

AsassaudonnavnshEnugyCovpnum ;

x

Mr. A. Bert Davis L

May 17, 1990 Page 2

'3. Review of the remaining integral welded attachment (IWA) calculations that Bechtel had performed-as part of the original IEB 79-14 project was completed in February,.1990.

As a result ~of the re-calculations only one. additional' support required modification to meet applicable Code allowabies,.although operability allowables were met.-

This support (CH-151-4-H50)-was-modified during the Unit 1 refueling outage-and now is in Code' compliance.

Another IWA i

anchor.is currently being reanalyzed'as part ofLIEB 88-08 work.

This support,-a pressurizer spray line anchor 1"

(RC-2501R-1-2A4) which has'been determined to be operable-with the current design 1oads,31s' undergoing further 1

detailed analysis to determine whether-it.can:moet. existing Code allowables.

The total population of IWA supports evaluated for the effects of localized stresses is 49, including-the IWA supports previously reported.

Five of these 49 were required to be modified.

Additionally, 48 IWA supports-were-evaluated as a result of the reanalysis of the.RHR systems outside containment.

Due to significant load l increases, 3 of these IWA supports required modification.

SevenLIWA supports were evaluated as.a result of'the1 reconciliation-of the as-found piping-identified in item 4, below.

No

'a modifications were. required as a result of these evaluations.- In summary, a total of 100 IWA calculations were created as part of the IEB;79

~.4 closecut effort resulting in no operability allowable violations and 8 piping support modifications.

4. Walkdown of the fifteen. additional piping subsystems were L

completed by November 30,1990, as committed to in.

Reference 1.

The discrepancies between the. current walkdowns and the.as-built analyses required reconciliation cniculations'and.3 new piping subsystem analyses.

'As a i

result of these reanalyses, 48 piping support loads were increased.

These load increases resulted in 41 calculations and 7 documented evaluations.

Those supports that did not meet Code compliance with the new' loads.were evaluated for.

operability and were shown to meet operability limits.

The 10 supports associated with Unit 1 were modified during the Unit'l refueling outage, and the 2 supports asecciated with Unit 2 will be modified this fall.

o

-=

2w

+ee,,=

g-gr

<e y

l-e

3..

l a

Mr. A. Bert Davis May 17, 1990 Page 3 i

5. The-Justification for Continued' Operation (JCO)' criteria-1 for Major "As-built" Discrepancies ir. Safety Related Piping l'

Systern was submitted for review and concurrence by.

1 Reference 3 in August, 1989, as originally committed'to by Reference 1.' -NRC concurrence was obtained in November, 1

1989.

j

.The results of the evaluations, calculations and resnalyses are.

currently being finalized and summarized at this-time.

Wisconsin

]

Electric. proposes to meet'with Region III during'the week of June j

18, 1990 or the week of. July'16, 1990 to present the complete 1;

results of these programs..

Please advise us of a'date that-would be acceptable for you.

We expect the meeting to last approximately 2-3 hours.

Very truly yours, 0W

~

C. W. Fay Vic'e President 3

Nuclear Power Copy to Resident Inspector Document Control Desk

-I l

_ _ _ _ _ _ - _ _ - - - _ _ - -