NPL-99-0473, Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months

From kanterella
Jump to navigation Jump to search
Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months
ML20211F719
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 08/27/1999
From: Cayia A
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NPL-99-0473, NUDOCS 9908310059
Download: ML20211F719 (3)


Text

w ,

Wisconsin Electnc POWER COMPANY Point Beach Nuclear Plant (920) 755-2321 6610 Nuclear Rd.. Two Rivers. WI 54241 ll I

I NPL 99-0473 l

l August 27,1999

)

Document Control Desk U.S. NUCLEAR REGULATORY COMMISSION Mail Station Pl-137 Washington, D. C. 20555 Ladies and Gentlemen:

l DOCKET 50-266 ASME SECTION XI ISI LONG TERM PLAN EXTENSION POINT BEACH NUCLEAR PLANT, UNIT 1 This letter informs you of a change that is being made to the Point Beach Nuclear Plant (PBNP) Unit 1 Third 10-year interval ISI Long Term Plan. The change extends the interval fror.uhe current end date of November 30,2000 to August 31,2002. The interval is being extended because the operating cycle has been increased from 12 months to 18 months and to account for an extended shutdown period that occurred during 1997. This extension is permitted in accordance wi.'.h ASME Section XI. Therefore, reliefis not being requested.

10 CFR 50.55a(g)," Inservice inspection requirements," requires in part that ASME Class 1,2 and 3 systems must be examined in accordance with the requirements set forth in the ASME Boiler and Pressure Vessel Code, Section XI, " Rules for Inservice Inspection of Nuclear Power Plant Components."' For Point Beach, these requirements are reiterated in Technical Specification 15.4.2.B.,

" Inservice Inspection and Testing of Safety Class Components other than Steam Generator Tubes." The Edition of ASME Section XI 1986 Edition, no Addenda is currently applicable to Point Beach.

ASME Section XI, IWA-2430, and IWA-2432 require that the inservice inspection (ISI) program be divided into four 10-year inspection intervals. IWB-2412, IWC-2412 and IWD-2412 require that each 10-year ISI interval be divided into three periods, which are approximately 40 months in length. The required ISI examinations are to be distributed within the three periods between a fixed minimum and maximum percentage of the total examination population. Any additional examinations performed during the first or second periods above the percentages allowed cannot be credited toward the ensuing periods. All required Class 1,2 and 3 inservice exaeinations are to be completed by the end of the third d M.  ;

period, which coincides with the er.d of thepf .inte7b gr

~ i?-

,t ,

,g 9908310059 990827 PDR ADOCK 05000266 PDR I[. kil G

hubsk/mofMisawsh Ewg Capwatiw

' NPL 99-0473

' August 27,1999

' Page 2 i

The current third 10-year interval for Inservice Inspection at PBNP Unit 1 is: i Beginning Date Ending Date Existing Third 10-YearInterval 12/1/1990 11/30/2000 Period 1 12/1/1990 3/31/1994 Period 2 4/1/1994 7/31/1997 Period 3 8/1/1997 11/30/2000 The revised and extended third 10-year interval Inservice Inspection at PBNP Unit I will be:

Beginning Date Ending Date Revised Third 10-YearInterval 12/1/1990 8/31/2002  !

Period 1 12/1/1990 3/31/1994 Pcriod 2 4/1/1994 7/31/1997  !

Period 3 8/1/1997 8/31/2002 This 21-month extension of the Third Interval is allowed by ASME Section XI, and is being applied to the ISI Program. The Inservice Testing (IST) Program is maintained as a separate program and is not being extended. The Fourth 10-Year Interval Inservice Inspection Program will be shortened by ,

21 months so that the end of the Fourth Interval remains unchanged.

Extension of a 10-Year Intervalis allowed by ASME Code Section XI. Specifically,IWA-2430(d) states, "each of the inspection intervals may be extended or decreased by as much as 1 year.

Adjustments shall not cause successive intervals to be altered by more than 1 year from the original pattern ofintervals." In addition, IWA-2430(e) states, "for power units that are out of service continuously for 6 months or more, the inspection interval during which it autage occurred may be extended for a period equivalent to the outage and the original pattern ofintervals extended accordingly for successive intervals." During the timeframe which spanned both Periods 2 and 3, PBNP Unit I had a c'ontinuous nine-month outage from February 18,1997 to December 1,1997. Applying those nine months, along with the one-year Code allowance results in the 21-month extension of Period 3 and the Third Interval. The approach applied to this extension is supported by various ASME Code #

Interpretations, including XI-1-86-54 and XI-1-92-57.

1 The benefit of extending the Unit 1 interval is that the Unit 1 ISI interval will end at the same I approximate time as the Unit 1 Pressure Test Program Interval. This will allow consolidating the program.c for the fourth interval to the same ASME Section XI Code edition and addenda. In addition, the inter 31 extension will allow the Unit I programs to end at approximately the same time as the Unit 2

'ISI and Pressure Test Programs. This will allow both units to be inspected utilizing the same ASME l, Section XI code edition and addenda.

NUREG-1482, t' Guidelines for Inservice Testing at Nuclear Power Plants," Section 3.3.1 addresses the extension ofintervals for IST and includes'a discussion about ISI as well. This document supports the l

w

- NPL 99-0473 '

- August 27,1999  ;

Page 3

.a 1

approach being taken at PBNP Unit I when it states,"In Interpretation XI-1-86-54, the committee stated that the one year extension need not be applied only during the last one-third of the interval and that the

. extensions may be applied serially for both out-of-service and plant outage conditions." The document also confirms that no reliefrequest is needed by stating,"Because the Code does not allow extension beyond one year, other than for extended outages, such an extension would require an alternative to the Code or exemption in order to comply with the regulatory requirements. The ASME Code allows intervals to be extended or decreased up to one year cumulative and also allow intervals to be extended ;

when outages greater than 6 months occur."

This addition of 21 months to the Third Interval for ISI has no adverse effect on plant safety since the change is allowed by ASME Section XI. An amount of time equal to the extension of the Third Interval will be removed from the Fourth Interval so the original pattern ofintervals will be maintained within  ;

the allowances granted by the ASME Code.

If you have any questions concerning the ISI Long Term Plan extension, please feel free.to contact us.  ;

i Sincerely, 14 W .1 -

9 j A. Ca a Man. r, Regu t ry Services & Licensing  !

1

- CTP/ tat -

l

- cc: NRC Resident Inspector l NRC Regional Administrator NRC Project Manager PSCW