Forwards Final Exercise Rept for Biennial Radiological Emergency Preparedness Exercise Conducted on 981103 for Point Beach Power Plant.One Deficiency Identified for Manitowoc County.County Corrected Deficiency Immediately
ML20206B823
Person / Time
Site: Point Beach  
Issue date: 03/30/1999
From: Shipley D
Federal Emergency Management Agency
To: Dyer J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20206B815 List:
References
NUDOCS 9904300091
Download: ML20206B823 (1)


Text

'

A., M w_-

FederalEmergency Management Agency Region V 175 West Jackson Blvd.,4th Floor Chicago, IL 60604-26%

March 30,1999 Mr. James Dyer Regional Administrator, Region til U. S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, Illinois 60532-4351

Dear Mr. Djer:

Enclosed is a copy of the Final Exercise Report for the Biennial Radiological Emergency Preparedness (AEP) Exercise conducted on November 3.1998 for the Point Beach Power Plant.

The February 12,1999 letter from Mr. Garrett Nielsen adequately addassed the planning issues that wew identified for the State of Wisconsin.

State and local organizations, except where noted in the report, demonstrated knowledge of their emergency response plans and satisfactorily implemented them. There was one Deficiency identified for Manitowoc County. However, the county corrected it immediately after the exercise as outlined in the final exercise report.

Based on the results of the November 3,1998 exercise, the offsite radiological emergency response plans and preparedness for the State of Wisconsin, Manitowoc and Kewaunee Counties, site-specific to the Point Beach Power Plant can be imp!emented. These plans are adequate to provide reasonable assurance that appropriate measures can be taken offsite to protect the health and safety of the public in the event of a radiological emergency at the site.

Therefore, Title 44 CFR, Part 350 approval of the offsite radiological emergency response plans and preparedness for the State of Wisconsin, site-specific to the Point Beach Power Plant, granted on March 9,1987 remains in effect.

Copics of the report were also sent to the Nuclear Regulatory Commission (NRC) National Office, the Federal Emergency Management Agency (FEMA) National Office and the State of Wisconsin.

If there should be any questions, please do not hesitate to let me know or have a member of your staff contact Cleven Lloyd at (312) 408-5321.

Sincerely, 4.%

W. Shipley Regional Director 9904300091 990423 PDR ADOCK 05000266 F

PDR y

APR 5 1999 1