ML12191A269
ML12191A269 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 07/05/2012 |
From: | Powers D Division of Reactor Safety IV |
To: | Matthew Sunseri Wolf Creek |
References | |
EA-12-135 IR-12-007 | |
Download: ML12191A269 (47) | |
See also: IR 05000482/2012006
Text
UNITE D S TATE S
NUC LEAR RE GULATOR Y C OMMI S SI ON
RE G IO N I V
1600 EAST LAMAR BLVD
AR L INGTON , TEXAS 7 60 11 - 4511
July 5, 2012
Matthew W. Sunseri, President and
Chief Executive Officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
SUBJECT: WOLF CREEK GENERATING STATION - NRC PROBLEM IDENTIFICATION
AND RESOLUTION INSPECTION REPORT 05000482/2012007 and NOTICE
OF VIOLATION
Dear Mr. Sunseri:
On May 24, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed a biennial
Problem Identification and Resolution inspection at your Wolf Creek Generating Station. The
enclosed inspection report documents the inspection results, which the team discussed on May
24, 2012, with you and members of your staff.
This inspection was an examination of activities conducted under your license as they relate to
problem identification and resolution and compliance with the Commissions rules and
regulations and the conditions of your license. Within these areas, the inspection involved
examination of selected procedures and representative records, observations of activities, and
interviews with personnel.
Based on the inspection sample, the inspection team concluded that the implementation of the
corrective action program and overall performance related to identifying, evaluating, and
resolving problems at Wolf Creek was adequate. Licensee-identified problems were generally
entered into the corrective action program at a low threshold, though the team noted some
exceptions, as documented in the enclosed report. Problems were generally prioritized and
evaluated commensurate with the safety significance of the problems. And, though the team
identified challenges to corrective action timeliness, most actions were implemented in a timely
manner commensurate with their safety significance and addressed the causes of the problems.
Lessons learned from industry operating experience were effectively reviewed and applied
when appropriate. Audits and self-assessments were effectively used to identify problems and
determine appropriate actions. Finally, the team determined that the station maintains a safety
conscious work environment where employees feel free to raise nuclear safety concerns without
fear of retaliation.
Six NRC-identified and two self-revealing findings of very low safety significance (Green) were
identified during this inspection and are documented in the enclosed report.
M. Sunseri -2-
Seven of these findings were determined to involve violations of NRC requirements.
Additionally, the NRC determined that one Severity Level IV traditional enforcement violation
occurred; this violation had no associated finding. The NRC is treating six of the eight violations
as non-cited violations (NCVs), consistent with Section 2.3.2 of the Enforcement Policy.
Two of the findings that the NRC evaluated under the risk significance determination process as
having very low safety significance (Green) did not meet the criteria to be treated as non-cited
violations. The violations associated with both of these issues were evaluated in accordance
with the NRC Enforcement Policy. The current version of this Policy is available on the NRC
website at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. These
violations are cited in the enclosed Notice of Violation (Notice) and the circumstances
surrounding them are described in detail in the subject inspection report. The violations are
being cited in the Notice because after the violations were previously documented as non-cited
violations, you failed to restore compliance within a reasonable time.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. Specifically, you are requested to provide a
firm commitment as to when plant modifications will be completed to prevent future water
hammer events in the essential service water system. If you have additional information that
you believe the NRC should consider, you may provide it in your response to the Notice. The
NRCs review of your response to the Notice will also determine whether further enforcement
action is necessary to ensure compliance with regulatory requirements.
If you contest any of these findings, you should provide a response within 30 days of the date of
this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission,
ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional
Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory
Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at Wolf Creek.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a
response within 30 days of the date of this inspection report, with the basis for your
disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at
Wolf Creek.
M. Sunseri -3-
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
enclosure, and your response (if any) will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of
NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
Electronic Reading Room).
Sincerely,
/RA/
Dr. Dale A. Powers, Chief (Acting)
Technical Support Branch
Division of Reactor Safety
Docket No: 50-482
License No: NPF-42
Enclosures:
1. Notice of Violation EA-12-135
2. Inspection Report 05000482/2012007
w/ Attachments:
1. Supplemental Information
2. Information Request
cc w/ encls: Electronic Distribution for Wolf Creek
SUNSI Rev Compl. ;Yes No ADAMS ;Yes No Reviewer Initials EAR
Publicly Avail. ;Yes No Sensitive Yes ; No Sens. Type Initials EAR
RIV/DRS/TSB DRS/EB2 DRS/OB DRS/EB2 DRP/PBB
ERuesch SMakor TFarina MWilliams LWilloughby
/RA/ /RA/ /RA-E/ /RA/ /RA/ - e-mail
7/05/2012 6/27/2012 6/27/2012 7/3/2012 7/03/2012
DRP/PBB NRR/DRA/AHPB C:DRP/PBB C:ORA/ACES AC:DRS/TSB
CPeabody KMartin NOKeefe HGepford DPowers
/RA/ - e-mail /RA-E/ /RA/ - e-mail RKellar for /RA/ /RA/
6/26/2012 6/21/12 7/03/2012 7/05/2012 7/05/2012
NOTICE OF VIOLATION
Wolf Creek Nuclear Operating Company Docket No: 50-482
Wolf Creek Generating Station License No: NPF-42
During an NRC inspection, conducted from May 7 through 24, 2012, two violations of NRC
requirements were identified. In accordance with the NRC Enforcement Policy, the violations
are listed below:
1. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in
part, that in the case of significant conditions adverse to quality, measures shall
assure that the cause of the condition is determined and corrective action taken
to preclude repetition.
Contrary to the above, from December 4, 2009, to May 24, 2012, the licensee
failed to assure that the cause of a significant condition adverse to quality was
determined and corrective action was taken to preclude repetition. Specifically,
after a water hammer event on August 19, 2009, the licensee failed to perform an
adequate evaluation to determine the cause of water hammers and of internal
corrosion in the essential service water system, and did not take corrective action
to preclude repetition of additional water hammer events and system leaks. The
condition recurred on January 13, 2012. This violation was identified on two
occasions by the NRC as NCV 05000482/2009007-03 and VIO
05000482/2012007-03; the licensee failed to restore compliance.
2. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in
part, that measures be established to assure that conditions adverse to quality
are promptly identified and corrected.
Contrary to the above, as of May 24, 2012, the licensee had failed to establish
measures to assure that a condition adverse to quality was promptly corrected.
Specifically, after identifying that safety-related spring-loaded tornado dampers
required testing to verify operability, the licensee failed to implement procedures
to test these dampers in the emergency diesel generator and essential service
water rooms. This violation was previously identified by the NRC as
NCV 05000482/2010007-02; the licensee failed to restore compliance.
These violations are associated with Green Significance Determination Process findings.
Pursuant to the provisions of 10 CFR 2.201, Wolf Creek Nuclear Operating Company is hereby
required to submit a written statement or explanation to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the
Regional Administrator, Region IV, and a copy to the NRC Resident Inspector Wolf Creek
Generating Station, within 30 days of the date of the letter transmitting this Notice of Violation
(Notice). This reply should be clearly marked as a "Reply to Notice of Violation EA-12-135," and
should include: (1) the reason for the violation, or, if contested, the basis for disputing the
violation or severity level, (2) the corrective steps that have been taken and the results
achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date
when full compliance will be achieved. Your response may reference or include previous
-1- Enclosure 1
docketed correspondence, if the correspondence adequately addresses the required response.
If an adequate reply is not received within the time specified in this Notice, an order or a
Demand for Information may be issued as to why the license should not be modified,
suspended, or revoked, or why such other action as may be proper should not be taken. Where
good cause is shown, consideration will be given to extending the response time. If you contest
this enforcement action, you should also provide a copy of your response, with the basis for
your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory
Commission, Washington, DC 20555-0001.
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS), accessible from the
NRC website at www.nrc.gov/reading-rm/pdr.html or www.nrc.gov/reading-rm/adams.html, to
the extent possible, it should not include any personal privacy, proprietary, or safeguards
information so that it can be made available to the public without redaction. If personal privacy
or proprietary information is necessary to provide an acceptable response, then please provide
a bracketed copy of your response that identifies the information that should be protected and a
redacted copy of your response that deletes such information. If you request withholding of
such material, you must specifically identify the portions of your response that you seek to have
withheld and provide in detail the basis for your claim of withholding (e.g., explain why the
disclosure of information will create an unwarranted invasion of personal privacy or provide the
information required by 10 CFR 2.390(b) to support a request for withholding confidential
commercial or financial information).
Dated this 5th day of July, 2012.
-2-
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Docket: 50-482
License: NPF-42
Report: 05000482/2012007
Licensee: Wolf Creek Nuclear Operating Corporation
Facility: Wolf Creek Generating Station
Location: 1550 Oxen Lane SE
Burlington, Kansas
Dates: May 7 through May 24, 2012
Team Leader: E. Ruesch, Senior Reactor Inspector
Inspectors: L. Willoughby, Senior Project Engineer
C. Peabody, Resident Inspector
M. Williams, Reactor Inspector
T. Farina, Operations Engineer
S. Makor, Reactor Inspector
K. Martin, Human Factors Engineer
Accompanying C. Franklin, General Engineer (NSPDP)
Personnel:
Approved By: Dr. Dale A. Powers, Chief (Acting)
Technical Support Branch
Division of Reactor Safety
-1- Enclosure 2
SUMMARY OF FINDINGS
IR 05000482/2012006; May 7, 2012 - May 24, 2012; Wolf Creek "Biennial Baseline Inspection
of the Identification and Resolution of Problems."
The team inspection was performed by one senior reactor inspector, one senior project
engineer, one resident inspector, one operations engineer, two reactor inspectors, and one
human factors engineer. Two cited violations and six non-cited violations of very low safety
significance (Green) were identified during this inspection. One severity level IV (SL-IV)
violation was also identified. The significance of most findings is indicated by their color (Green,
White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance Determination
Process." Findings for which the significance determination process does not apply may be
Green or be assigned a severity level after NRC management review. The NRC's program for
overseeing the safe operation of commercial nuclear power reactors is described in NUREG 1649, "Reactor Oversight Process," Revision 4, dated December 2006.
Identification and Resolution of Problems
The team reviewed approximately 300 condition reports, work orders, engineering evaluations,
root and apparent cause evaluations, and other supporting documentation to determine if
problems were being properly identified, characterized, and entered into the corrective action
program for evaluation and resolution. The team reviewed a sample of system health reports,
self-assessments, trending reports and metrics, and various other documents related to the
corrective action program.
Based on these reviews, the team concluded that the licensees corrective action program and
its other processes to identify and correct nuclear safety problems were adequate to support
nuclear safety. However, the team noted several challenges to licensee staffs willingness to
use the corrective action program for problems that were perceived as minor. The team also
noted several challenges to timely evaluations of adverse conditions. Further, the licensee had
several long-standing issues which had been in process for several years without resolution.
The team also concluded that the licensee thoroughly evaluated industry operating experience
for relevance to the facility, generally took prompt actions in response to relevant items, and
entered them into the corrective action program as appropriate. The licensee used industry
operating experience when performing root and apparent cause evaluations. The licensee
performed effective audits and self-assessments, demonstrated by self-identification of
marginally effective corrective action program performance and some identification of ineffective
corrective actions. While there had been some weaknesses in the quality assurance
organizations follow-up on audit findings, the team determined that recent program changes
had addressed these issues.
Finally, the team determined that the station continued to maintain a safety conscious work
environment. Employees felt free to raise nuclear safety concerns to the attention of
management without fear of retaliation.
-2-
A. NRC-Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green. The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix
B, Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to
adequately translate design information into procedures and requirements.
Specifically, the licensee had information that its calculation for vital switchgear
cooling included nonconservative assumptions. These assumptions called into
question the ability of air conditioning systems to adequately cool Class 1E
switchgear under all design conditions. The licensee failed to revise procedures to
include compensatory actions necessary to ensure the vital switchgear remained
operable. The licensee entered this finding in its corrective action program as
condition report 53393.
The inspectors determined that the licensees failure to adequately translate design
information into procedures was a performance deficiency. The performance
deficiency is more than minor because it affected the equipment performance
attribute of the Mitigating Systems cornerstone objective to ensure the availability,
reliability, and capability of systems that respond to initiating events to prevent
undesirable consequences. Using Inspection Manual Chapter 0609.04, Phase 1 -
Initial Screening an Characterization of Findings, the team determined the finding
was of very low safety significance (Green) because it did not represent a loss of
system safety function, did not represent the actual loss of safety function of a single
train for greater than its technical specification allowed outage time, and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event. The finding has a cross-cutting aspect in the corrective action
component of the problem identification and resolution cross-cutting area because
the licensee failed to thoroughly evaluate the problem such that its resolution
addressed its causes and extent of conditions (P.1(c)). (Section 4OA2.5.a)
- Green. The inspectors identified a violation of 10 CFR 50, Appendix B, Criterion XVI,
Corrective Action, for the licensees failure to take corrective action to preclude
repetition of system leaks due to water hammer events in the essential service water
system. Extensive inadequately evaluated corrosion in the system has led to
multiple water-hammer-induced leaks of essential service water piping. These leaks
were the subject of two previous violations issued by the NRC. The licensee failed to
take timely corrective action to restore compliance. The licensee entered this finding
in its corrective action program as condition report 53443.
The failure to preclude recurrence of water hammer in the essential service water
system and the failure to take adequate corrective action to control internal pitting
corrosion in essential service water system piping was a performance deficiency.
The deficiency was more than minor because it is associated with the equipment
performance attribute of the mitigating systems cornerstone objective to ensure the
availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences. It is therefore a finding. Using Inspection
Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of
Findings, the team determined that the finding was of very low safety significance
-3-
(Green) because the finding was a design or qualification deficiency that was
confirmed not to result in loss of system operability or functionality. This finding has
a cross-cutting aspect in the corrective action program component of the problem
identification and resolution cross-cutting area because the licensee failed to take
appropriate corrective actions to address safety issues and adverse trends in a
timely manner, commensurate with their safety significance (P.1(d)). (Section
4OA2.5.c)
- Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
Criterion XVI, Corrective Action, for the licensees failure to effectively correct
deficient procedures regarding the use of clearance orders. A number of clearance-
related problems revealed several deficiences in procedures to ensure that safe tag-
out of equipment occurred prior to the start of work, that independent reviews of
qualified individuals were being completed during clearance order preparation, and
that effective training was being conducted where performance gaps were identified.
The licensee failed to correct these deficiencies in a timely manner. The licensee
entered this finding in its corrective action program as condition report 53451.
The team determined that the failure to correct an adverse trend in the use of
clearance orders was a performance deficiency. This finding was more than minor
because if left uncorrected, it could lead to a more significant safety concern.
Specifically, continued failure to establish the correct clearance order boundaries
could result in the loss of configuration control for systems required to maintain
nuclear safety. Using Manual Chapter 0609.04, Phase 1 - Initial Screening and
Characterization of Findings, the team determined that this finding was of very low
safety significance (Green) because it was not a design or qualification deficiency,
did not represent a loss of system safety function, and did not screen as potentially
risk significant due to a seismic, flooding, or severe weather initiating event. The
team determined that this finding has a cross-cutting aspect in the resources
component of the human performance cross-cutting area because the licensee failed
to ensure complete, accurate and up-to-date design documentation, procedures, and
work packages were available and adequate to support nuclear safety (H.2(c)).
(Section 4OA2.5.d)
- Green. The team identified a non-cited violation of 10 CFR Part 50, Criterion V,
Instructions, Procedures, and Drawings, for the licensees failure to establish
adequate procedures for resolution of corrective actions. Specifically, the licensee
failed to establish procedures to ensure that planned corrective actions were
effectively implemented. The licensee entered this finding in its corrective action
program as condition report 53432.
The failure to establish adequate procedures for resolution of corrective actions was
a performance deficiency. This finding was more than minor because if left
uncorrected, it would have the potential to lead to a more significant safety concern.
Specifically, failure to establish adequate procedures for resolution of corrective
actions could result in important actions not being accomplished. Using Manual
Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings, this
finding was determined to be of very low safety significance (Green) because it was
not a design or qualification deficiency, did not represent a loss of system safety
-4-
function, and did not screen as potentially risk significant due to a seismic, flooding,
or severe weather initiating event. This finding has a cross-cutting aspect in the
decision making component of the human performance cross-cutting area because
the licensee failed to demonstrate that nuclear safety is an overriding priority by
making safety-significant or risk-significant decisions using a systematic process
(H.1(a)). (Section 4OA2.5.e)
- Green. The team identified a violation of 10 CFR Part 50, Appendix B, Criterion XVI,
Corrective Action, for the licensees failure to perform testing of safety-related
spring-loaded tornado dampers in the emergency diesel generator and essential
service water rooms. In 2008, the licensee identified that because the updated
safety analysis report (USAR) incorrectly classified these active components as
passive, they had not been included in a periodic testing or surveillance program.
Since 2010, action items to test the dampers have received four due date
extensions. Additonally, required training for this testing was completed and closed.
However, no testing or surveillance was accomplished. This failure was the subject
of a previous violation issued by the NRC. The licensee failed to take timely
corrective actions to restore compliance. The licensee entered this finding in its
corrective action program as condition report 53363.
The team determined that the licensees failure to implement corrective action was a
performance deficiency. This finding was more than minor because it affected the
equipment reliability attribute of the mitigating systems cornerstone objective to
ensure the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. Specifically, failure to implement this
corrective action could result in reduced reliability of safety-related equipment during
an event initiated by a tornado. Using Chapter 0609.04, Phase 1 - Initial Screening
and Characterization of Findings, the team determined that this finding was of very
low safety significance (Green) because it was not a design or qualification
deficiency, did not represent a loss of system safety function, and during a tornado,
would not cause a plant trip if failed, would not degrade two or more trains of a multi-
train safety system, and would not degrade one or more trains of a system that
supports a safety system or function. This finding has a cross-cutting aspect in the
resources component of the human performance cross-cutting area because the
licensee failed to provide complete, accurate, and up-to-date design documentation,
procedures, and work packages were available and adequate to support nuclear
safety (H.2(c)). (Section 4OA2.5.f)
- Green. On February 23, 2011, a non-cited violation of 10 CFR Part 50, Appendix B,
Criterion XVI, Corrective Action, was revealed when an anomalous start of
component cooling water pump B indicated gas voiding in the component cooling
water piping. This violation was due to the licensees inadequate root cause
evaluation and failure to prevent recurrence of the voiding that had previously
occurred in May 2010. The licensee entered this finding in its corrective action
program as condition report 33925.
The failure to properly identify design issues as a root cause and to take action to
prevent the recurrence of a component cooling water system voiding was a
performance deficiency. The performance deficiency is more than minor because it
-5-
impacted the equipment performance attribute of the mitigating systems cornerstone
objective to ensure the availability, reliability, and capability of systems that respond
to initiating events to prevent undesirable consequences. Specifically, excessive
voiding of the component cooling water system could lead to lack of cooling to
important safety-related components. Using Manual Chapter 0609.04, "Phase 1 -
Initial Screening and Characterization of Findings," the team determined that the
issue was of very low safety significance (Green) because it did not represent a loss
of system safety function or loss of a single train longer than its technical
specification allowed outage time. This finding has a cross-cutting aspect in the
corrective action program component of the problem identification and resolution
cross-cutting area because the licensee failed to thoroughly evaluate a problem such
that its resolution addressed its cause and extent of condition. Specifically, condition
report 25918 did not properly identify design issues as a root cause requiring
immediate system modifications to preclude recurrence (P.1(c)). (Section 4OA2.5.g)
- Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
Criterion III, Design Control, for the licensees failure to evaluate the suitability of
nonsafety-related gaskets, o-rings, and seals installed in safety-related components.
These nonsafety-related parts were originally installed due to erroneous Safety
Classification Assessments. After determining that the parts were inappropriate in
safety-related joints, the licensee failed to promptly correct the condition and failed to
fully identify which components were affected. The licensee entered this finding in its
corrective action program as condition report 53456.
The failure of the licensee to evaluate the suitability of the specific nonsafety-related
material installed in safety-related equipment and to determine the extent to which
this condition existed was a performance deficiency. This performance deficiency
was more than minor because it affected the design control attribute of the mitigating
systems cornerstone objective to ensure the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences.
Specifically, the inadequate evaluation of nonsafety-related gaskets, o-rings, and
seals installed in safety-related equipment adversely affected the reliability of the
affected systems. Using Manual Chapter 0609.04, "Phase 1 - Initial Screening and
Characterization of Findings," the team determined that the finding was of very low
safety significance (Green) because the finding was a design or qualification
deficiency confirmed not to result in loss of operability or functionality. This
performance deficiency had a cross-cutting aspect in the corrective action program
component of the problem identification and resolution cross-cutting area because
the licensee did not take appropriate corrective actions to address safety issues and
adverse trends in a timely manner, commensurate with their safety significance and
complexity (P.1(d)). (Section 4OA2.5.h)
- Green. The team identified a finding for the licensees failure to ensure that condition
reports were initiated as required by procedure. The licensees implementing
procedure for its corrective action program did not contain clear guidance as to what
conditions were required to be entered into the corrective action program, or how
soon after discovery the condition report was required to be generated. The team
identified several examples where condition reports were not generated, though it
-6-
appeared from the guidance that they were required. The licensee entered this
finding in its corrective action program as condition report 53445.
The failure of licensee personnel to promply initiate condition reports for identified
issues, contrary to procedural requirements, is a performance deficiency. This
performance deficiency is more than minor because if left uncorrected, it could lead
to a more significant safety concern. Using Inspection Manual Chapter 0609.04,
Phase 1 - Initial Screening and Characterization of Findings, the team determined
that this finding was of very low safety significance (Green) because it did not involve
a design or qualification deficiency, did not represent a loss of system safety
function, and did not screen as potentially risk significant due to a seismic, flooding,
or severe weather initiating event. This finding has a cross-cutting aspect in the
resources component of the human performance cross-cutting area because the
licensee failed to ensure procedures necessary for complete, accurate, and up-to-
date procedures were available and adequate to support nuclear safety. Specifically,
the corrective action program procedure was vague in its guidance as to when a
condition report was required (H.2(c)). (Section 4OA2.5.i)
Cornerstone: Miscellaneous
- SL-IV. The inspectors identified a non-cited violation of 10 CFR 50.73(a)(2)(i)(b) for
the licensees failure to submit a licensee event report upon discovery that a
condition prohibited by technical specifications had existed in the preceding three
years. On April 18, 2011, the licensee issued calculation GK-06-W, SGK05A/B
Class 1E Electrical Equipment Rooms A/C Units, Single Unit Operation Capability,
Revision 2. This calculation concluded that with one of the two air conditioning units
inoperable, the use portable fans and the opening of doors was required to maintain
vital switchgear rooms below the maximum operability limits. The calculation further
concluded that even with these compensatory actions, required temperatures could
be maintained only if the temperature of all surrounding areas remained below 78F.
Calculation GK-06-W thus demonstrated that a single cooler was incapable of
maintaining the switchgear rooms within technical specification limits, without
compensatory actions. Because one of the two air conditioning units had been out of
service on multiple occasions during the preceding three years with no
compensatory actions taken, the condition was reportable. The licensee entered this
finding in its corrective action program as condition report 53452.
The failure to submit a licensee event report was a performance deficiency. The
team evaluated this performance deficiency using the NRCs significance
determination process (SDP) and determined that it was of minor safety significance.
It is therefore not associated with a finding or assigned a color. However,
performance deficiencies which impact the NRCs regulatory ability are processed
using traditional enforcement separately from the SDP evaluation. The NRC relies
on the licensee to identify and report conditions or events meeting the criteria
specified in regulations in order to perform its regulatory function. When this is not
done, the regulatory function is impacted. Therefore, the team determined that this
performance deficiency was most appropriately processed using traditional
enforcement. Using the Enforcement Policy and the available risk information, the
-7-
inspectors concluded that this violation is a traditional enforcement violation of
Severity Level IV. (Section 4OA2.5.b)
B. Licensee-Identified Violations
None
-8-
REPORT DETAILS
4. OTHER ACTIVITIES (OA)
4OA2 Problem Identification and Resolution (71152)
The team based the following conclusions on the sample of corrective action documents
that were initiated in the assessment period, which ranged from May 26, 2010, to the
end of the on-site portion of the this inspection on May 24, 2012.
.1 Assessment of the Corrective Action Program Effectiveness
a. Inspection Scope
The team reviewed approximately 300 corrective action program documents, including
associated root cause, apparent cause, and direct cause evaluations, from
approximately 25,000 that had been initiated between May 26, 2010, and May 24, 2012.
The team focused its review on condition reports that were evaluated as significant to
determine if problems were being properly identified, characterized, and entered into the
corrective action program for evaluation and resolution. The team reviewed a sample of
system health reports, operability determinations, self-assessments, trending reports
and metrics, and other documents related to the corrective action program. The team
evaluated the licensees efforts in establishing the scope of problems by reviewing
selected logs, work requests, self-assessments results, audits, system health reports,
action plans, and results from surveillance tests and preventive maintenance tasks. The
team reviewed work requests and attended the licensees daily Screening Review Team
(SRT) and Senior Leadership Review Team (SLRT) meetings to assess the reporting
threshold, prioritization efforts, and significance determination process, as well as
observing the interfaces with the operability assessment and work control processes.
The teams review included verifying that the licensee considered the full extent of cause
and extent of condition for problems as well as how the licensee assessed generic
implications and previous occurrences. The team assessed the timeliness and
effectiveness of corrective actions, completed or planned, and looked for additional
examples of similar problems. The team conducted interviews with plant personnel to
identify other processes that may exist where problems may be identified and addressed
outside the corrective action program.
The team also reviewed corrective action documents that addressed past NRC-identified
violations to ensure that the corrective action addressed the issues as described in the
inspection reports. The inspectors reviewed a sample of corrective actions closed to
other corrective action documents to determine whether corrective actions were still
appropriate and timely.
The team considered risk insights from both the NRCs and Wolf Creeks risk
assessments to focus the sample selection and plant tours on risk significant systems
and components. Based on this review, samples reviewed by the team focused on, but
were not limited to, the essential service water and emergency diesel generator
systems. The team also expanded its review to include a five-year in-depth review of
-9-
the emergency diesel generator system to determine whether problems were being
effectively addressed. The team conducted a walkdown of these systems to assess
whether problems were identified and entered into the corrective action program.
b. Assessments
1. Assessment - Effectiveness of Problem Identification
The team concluded that in most cases, the licensee identified issues and adverse
conditions in accordance with the licensees corrective action program guidance and
NRC requirements. The team determined that the licensee generally identified these
problems at a low threshold and entered them into the corrective action program.
The team further noted that the licensees condition report initiation rate had
increased significantly in recent years. This increase included a change in the
condition report initiation process in 2010 that required all work orders to be initiated
with a condition report, resulting in a large increase in the initiation rate. The
average number of condition reports initiated per year had increased from fewer than
4000 in 2005 to over 8000 before the change was implemented. Under the new
process in 2011, the licensee initiated over 15,000 condition reports.
The team noted that this high rate of condition report generation is generally a sign of
a healthy corrective action program. However, the team identified several issues
and adverse conditions that were not entered into the corrective action program.
Some of these were the subject of finding FIN 2012007-09, included in this report.
See section 4OA2.5.i.
2. Assessment - Effectiveness of Prioritization and Evaluation of Issues
In general, the licensee adequately performed and documented evaluations of
conditions adverse to quality during this assessment period. However, the team
noted that the licensee had some challenges with timeliness of evaluations:
- The stations evaluation timeliness goal was 30 days for all corrective action
program cause evaluation products. The average age at closure for these
evaluations was 43 days in March and 53 days in April. The licensee had
documented this in condition report 52961.
- Condition report 51292 was initiated anonymously on April 5, 2012,
documenting multiple past-due corrective actions. This condition report went
past due on May 9, 2012, with no actions taken.
- Many condition reports had multiple due date extensions for their corrective
actions. Many actions were not completed until well after the 120-day base
completion metric; in the sample of higher-tier corrective action program
documents the team reviewed, few significant actions were completed within
120 days. Two examples follow:
o Condition report 34987 identified three deficiencies in procedures for
recovery from a safety injection actuation. It took 30 days for the condition
- 10 -
report to be approved and then six more months to implement the
procedure changes.
o Condition report 34964 included an action to track completion of an action
from CR 37931. After several extensions of the latter action, the actions
were completed nine months after the deficiencies were identified that the
actions were designed to address. The team concluded that these
corrective actions were untimely.
Additionally, the team reviewed several condition reports that involved potential
challenges to operability. The team assessed the quality, timeliness, and
prioritization of these operability assessments. In general, the licensee
completed these operability assessments adequately and evaluated operability
appropriately.
3. Assessment - Effectiveness of Corrective Action Program
Overall, the team concluded that the licensee generally developed appropriate
corrective actions to address problems. However, the team identified a number of
corrective actions associated with conditions adverse to quality that were not
completed in a timely manner:
- The average age of corrective actions to prevent recurrence (CAPRs) was 428
days in March 2012, having increased from 180 days in November 2011. The
stations goal is to complete CAPRs within 180 days when they do not require
an outage or other long-term constraint.
- In March 2012, the station had 52 open condition reports associated with NRC-
issued findings. The average age of these condition reports was 438 days.
- After determining that nonsafety-related gaskets had been installed in safety-
related components, the licensee took some actions to replace these materials,
but did not track these actions through the corrective action program. Further,
the licensee inappropriately determined that because the gaskets had not yet
leaked, they would not leak under any service condition until the next time
maintenance was performed on the affected joint. This performance deficiency
is the subject of a non-cited violation documented in section 4OA2.5.h.
- The licensee failed to take timely corrective actions to prevent water-hammer-
induced leaks from the essential service water system. This is further discussed
in section 4OA2.5.c of this report.
- Similarly, after identifying voiding in the component cooling water system, the
station failed to adequately identify the cause of the voiding and to take
appropriate actions to prevent its recurrence. The team documented this issue
as a self-revealing non-cited violation in section 4OA2.5.g of this report.
- 11 -
- The licensee identified that safety-related tornado dampers on the essential
service water and emergency diesel generator buildings required periodic
testing, and that this testing had never been performed. Although this condition
was originally identified by the licensee in 2008, and was documented by the
NRC as a violation in a 2010 report, the licensee took no actions to correct this
deficiency. This is further discussed in section 4OA2.5.f of this report.
Additionally, the team identified several instances where identified corrective actions,
which had been approved by the stations corrective action review board (CARB),
were unilaterally canceledor were marked as complete with no action takenby
the condition report owner. The team determined that the licensees failure to ensure
corrective actions were accomplished was a violation of NRC requirements; this
violation is further discussed in section 4OA2.5.e of this report.
.2 Assessment of the Use of Operating Experience
a. Inspection Scope
The team examined the licensee's program for reviewing industry operating experience,
including reviewing the governing procedure and self assessments. The team reviewed
a sample of condition reports examining operating experience documents that had been
issued during the assessment period to assess whether the licensee had appropriately
evaluated the notification for relevance to the facility. The inspectors also examined
whether the licensee had entered those items into their corrective action program and
assigned actions to address the issues. The inspectors reviewed a sample of root cause
evaluations and significant condition reports to evaluate whether the licensee had
appropriately included industry operating experience.
b. Assessment
Overall, the team determined that the licensee had appropriately evaluated industry
operating experience for relevance to the facility, and had entered applicable items in the
corrective action program. The team observed several interactions in management
meetings where operating experience information was discussed in near-real time, and
where prompt action was taken to determine whether the station was vulnerable to a
similar adverse condition. The team determined that this was a highly effective method
of incorporating operating experience into plant operations. The team noted that both
internal and external operating experience was being incorporated into lessons learned
for training and in pre-job briefs for routine and non-routine tasks.
.3 Assessment of Self-Assessments and Audits
a. Inspection Scope
The inspectors reviewed a sample of licensee self-assessments and audits to assess
whether the licensee was regularly identifying performance trends and effectively
addressing them. The inspectors also reviewed audit reports to assess the
effectiveness of assessments in specific areas. The specific self-assessment
documents and audits reviewed are listed in Attachment 1.
- 12 -
b. Assessment
The inspectors concluded that the licensee had an effective self-assessment process.
Licensee management was involved in developing the topics and objectives of self-
assessments. Attention was given to assigning team members with the proper skills and
experience to do effective self-assessments and to include people from outside
organizations. Audits were self-critical and identified deficiencies in various programs
such as the corrective action program and several root cause evaluations. While the
team identified that there had been some weaknesses in the quality assurance
organizations follow-up of audit findings, recent changes to the licensees quality
programs had addressed and begun to correct many of these issues.
.4 Assessment of Safety-Conscious Work Environment
a. Inspection Scope
The team conducted ten focus groups that included more than 60 individuals from a
cross-section of functional organizations: engineering, operations, maintenance, quality
programs (quality assurance, quality verification, and quality control), heath physics, and
chemistry. Both supervisory and non-supervisory personnel were included, though
separate focus groups were conducted for supervisors. The discussions assessed
whether conditions existed that would challenge an effective safety conscious work
environment (SCWE). The team also interviewed the ombudsmanWolf Creeks
employee concerns program managerand reviewed the last two safety culture self-
assessment documents.
b. Assessment
Overall, the team concluded that a safety conscious work environment exists at Wolf
Creek. Employees demonstrated familiarity with the various avenues available to raise
safety concerns. They appeared comfortable with submitting all nuclear safety issues.
The team noted a potential vulnerability in the licensees safety conscious work
environment in discussions with security personnel. There was a perception among
some members of the plant staff that management was not willing to address security-
related issues with the same rigor with which it addressed issues of nuclear safety not
related to physical security. Also, security personnel stated that they generally did not
write condition reports, but rather passed the comments along to supervisors who would
enter them into the corrective action program.
Overall, individuals were familiar with the employee concerns program and its location
on site. There was visibility of the program throughout the site; the resolutions of
anonymous issues were reported site-wide through an article in the site newsletter.
Many of the individuals interviewed had had direct interactions with the ombudsman with
varying degrees of satisfaction. Some personnel were unsure of the ombudsmans
authority to resolve issues raised through him. But personnel understood and were
confident in the confidentiality of the program.
- 13 -
Site personnel were required to participate in a read and sign training annually which
covers the SCWE policies. Many individuals who were interviewed were familiar with
this training and with the overall message in the training. But not everyone was familiar
with the details of the policy. None of the individuals interviewed cited any examples of
harassment, intimidation, retaliation or discrimination or any negative reactions from
management when individuals raised nuclear safety concerns. The message from
management that nuclear safety is more important than production goals was well-
received by plant personnel. Finally, individuals indicated that if they were to believe
unsafe conditions existed, they would feel comfortable stopping work without fear of
retaliation, even if such actions would prolong an outage or extend a planned schedule.
.5 Specific Issues Identified During This Inspection
a. Inadequate Procedure for Compensatory Measures
Introduction. The inspectors identified a Green non-cited violation of 10 CFR Part 50,
Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees
failure to adequately translate design information into procedures and requirements.
Specifically, the licensee had information that its calculation for vital switchgear cooling
included nonconservative assumptions. These assumptions called into question the
ability of air conditioning systems to adequately cool Class 1E switchgear under all
design conditions. However, the licensee failed to revise procedures to include
compensatory actions necessary to ensure the vital switchgear remained operable.
Description. Wolf Creek is designed with two vital switchgear air conditioning units.
Each air conditioning unit cools one vital 4160V switchgear room, two sets of vital dc
battery rooms, and two sets of vital dc switchgear. In 2010, the NRC identified that the
heat transfer calculation for the sizing of these units was inadequate (see NCV 2011002-
05). In reviewing the licensees corrective actions for this violation, the team reviewed
the licensees compensatory actions and calculation GK-06-W, SGK05A/B Class 1E
Electrical Equipment Rooms A/C Units, Single Unit Operation Capability, Revision 2.
This calculation concluded that using portable fans and opening the room doors would
maintain temperatures in the switchgear rooms below 104F for at least 7 days if
temperatures in all surrounding areas remained below 78F.
However, the team identified several examples that contradicted or failed to incorporate
the evaluated design requirements in calculation GK-06-W:
- The compensatory measures identified in procedure SYS GK-200, Inoperable
Class 1E A/C Unit, Revision 24, were not consistent with the conclusions in
calculation GK-06-W. Step 5.3 of SYS GK-200 stated, IF desired, THEN portable
fans and ducting are available. This allowed portable fans to be optionally installed
at the operators discretion, contradicting the assumptions of the calculation.
- The bases for Technical Requirement (TR) 3.7.23 stated, With the interior doors
opened as described above, portable fans may be installed to facilitate air
circulation among rooms; however, this is not required based on operating
experience.
- 14 -
- A note in TR 3.7.23 required entry into the associated technical specification (TS)
action statementsTS 3.8.4 for dc power sources, TS 3.8.7 for inverters, and TS 3.8.9 for electrical distribution systemswhen room temperature was equal to or
greater than 104F. However, calculation GK-06-W only demonstrated that
operability of these systems can be maintained with a single operable air
conditioning unit when (1) portable fans are installed prior to the evaluated transient
and (2) surrounding areas remain below 78F.
- The box fans used in the compensatory actions to maintain operability of safety-
related equipment relied on nonsafety-related power. This power supply would not
be available under all design basis conditions where the compensatory actions
would be required.
- The box fans and trunks were not modeled in calculation GK-06-W to demonstrate
operability.
These discrepancies resulted in non-conservative entry assumptions into technical
specification action statements and invalid assumptions of continued operability.
Analysis. The inspectors determined that the licensees failure to adequately translate
design information into procedures was a performance deficiency. The performance
deficiency is more than minor because it affected the equipment performance attribute of
the Mitigating Systems cornerstone objective to ensure the availability, reliability, and
capability of systems that respond to initiating events to prevent undesirable
consequences. Using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening
an Characterization of Findings, the team determined the finding was of very low safety
significance (Green) because it did not represent a loss of system safety function, did
not represent the actual loss of safety function of a single train for greater than its
technical specification allowed outage time, and did not screen as potentially risk
significant due to a seismic, flooding, or severe weather initiating event. The finding has
a cross-cutting aspect in the corrective action component of the problem identification
and resolution cross-cutting area because the licensee failed to thoroughly evaluate the
problem such that its resolution addressed its causes and extent of conditions (P.1(c)).
Enforcement. Title 10 of the Code of Federal Regulations (CFR) Part 50, Appendix B,
Criterion V, Instructions, Procedures, and Drawings, requires in part that activities
affecting quality be prescribed by documented instructions, procedures, or drawings, of a
type appropriate to the circumstances and shall be accomplished in accordance with
these instructions, procedures, and drawings. Contrary to this requirement, from 2010
through May 2012, the licensee failed to prescribe an activity affecting quality in an
instruction, procedure, or drawing appropriate to the circumstances. Specifically,
procedure SYS GK-200, Inoperable Class 1E A/C Unit, Revision 24, failed to provide
reasonable assurance that the electrical systems would be maintained operable under
postulated conditions. Because this violation was determined to be of very low safety
significance (Green) and was entered into the licensees corrective action program as
condition report 53393, this violation is being treated as a non-cited violation in
accordance with section 2.3.2 of the NRC Enforcement Policy: NCV 05000482/2012007-01, Inadequate Procedure to Implement Compensatory Measures.
- 15 -
b. Failure to Report Conditions that Could have Prevented Fulfillment of a Safety Function
Introduction. The inspectors identified a Severity Level IV non-cited violation of 10 CFR
50.73(a)(2)(i)(b) for the licensees failure to submit a licensee event report upon
discovery that a condition prohibited by technical specifications had existed in the
preceding three years. On April 18, 2011, the licensee issued calculation GK-06-W,
SGK05A/B Class 1E Electrical Equipment Rooms A/C Units, Single Unit Operation
Capability, Revision 2. This calculation concluded that with one of the two air
conditioning units inoperable, the use of portable fans and the opening of doors was
required to maintain vital switchgear rooms below the maximum operability limits. The
calculation further concluded that even with these compensatory actions, required
temperatures could be maintained only if the temperature of all surrounding areas
remained below 78F. Calculation GK-06-W thus demonstrated that a single cooler was
incapable of maintaining the switchgear rooms within technical specification limits,
without compensatory actions. Because one of the two air conditioning units had been
out of service on multiple occasions during the preceding three years with no
compensatory actions taken, the condition was reportable.
Description. On September 22, 2010, the licensee identified from operating experience
that with one Class 1E Electrical Equipment A/C train nonfunctional, single failure
protection would no longer exist for this support function. The licensees reportability
evaluation determined that the Class 1E electrical equipment rooms cooled by
SGK05A/B had not exceeded technical specification temperature limits. The licensee
incorrectly determined that because temperatures had not exceeded limits, a condition
prohibited by Technical Specifications had not existed. The licensee thus incorrectly
concluded that the condition did not require a report to the NRC.
On April 18, 2011, the licensee issued GK-06-W, SGK05A/B Class 1E Electrical
Equipment Rooms A/C Units, Single Unit Operation Capability, Revision 2. This
calculation concluded that with one of the two air conditioning units inoperable, the use
of portable fans and the opening of doors was required to maintain vital switchgear
rooms below the maximum operability limits. The calculation further concluded that
even with these compensatory actions, required temperatures could be maintained only
if the temperature of all surrounding areas remained below 78F.
The team concluded that this calculation demonstrated that with one cooler out of
service, the licensee was unable to provide reasonable assurance that room
temperatures could be maintained within technical specification operability limits without
compensatory actions. Operation with one cooler out of service would thus require entry
into the action statements of technical specifications 3.8.4 for dc power sources, 3.8.7
for inverters, and 3.8.9 for electrical distribution systems. The shortest of these action
statements requires plant shutdown within eight hours. The licensees reportability
evaluation determined that one cooler had been removed from service for more than two
hours on multiple occasions in the preceding three years. This represented a condition
prohibited by technical specification and required a report to the NRC in accordance with
10 CFR 50.73 requirements.
- 16 -
Analysis. The failure to submit a licensee event report was a performance deficiency.
The team evaluated this performance deficiency using the NRCs significance
determination process (SDP) and determined that it was of minor safety significance. It
is therefore not associated with a finding or assigned a color. However, performance
deficiencies which impact the NRCs regulatory ability are processed using traditional
enforcement separately from the SDP evaluation. The NRC relies on the licensee to
identify and report conditions or events meeting the criteria specified in regulations in
order to perform its regulatory function. When this is not done, the regulatory function is
impacted. Therefore, the team determined that this performance deficiency was most
appropriately processed using traditional enforcement. Using Enforcement Policy
section 6.9, the inspectors concluded that this violation is a traditional enforcement
violation of Severity Level IV.
Enforcement. Title 10 CFR 50.73(a)(2)(i)(B) requires, in part, that licensees submit a
Licensee Event Report to the NRC within 60 days of discovery of any operation or
condition which was prohibited by the plants Technical Specifications and that occurred
within three years of the date of discovery. Contrary to this requirement, in September
2010, the licensee failed to report to the NRC within 60 days of discovery a condition
that was prohibited by the plants Technical Specifications that had occurred withing
three years of the date of discovery. Specifically, the licensee failed to report a condition
in which it could not provide reasonable assurance of the operability of Class 1E
switchgear for greater than its technical specification allowed outage time. The licensee
documented this issue in its corrective action program as condition report 53452.
Reviewing the finding using the NRCs Enforcement Policy and the available risk
information, the team concluded that this violation is appropriately characterized as
Severity Level IV. Because it is a Severity Level IV violation and was entered into the
corrective action program, this violation is being treated as a non-cited violation,
consistent with section 2.3.2 of the NRC Enforcement Policy: NCV 05000482/2012007-
02, Failure to Report Conditions that Could Have Prevented Fulfillment of a Safety
Function.
c. Failure to Take Timely Corrective Actions to Preclude Repetition of a Significant
Introduction. The inspectors identified a Green violation of 10 CFR 50, Appendix B,
Criterion XVI, Corrective Action, for the licensees failure to take corrective actions to
preclude repetition of system leaks due to water hammer events in the essential service
water system. Extensive inadequately evaluated corrosion in the system has led to
multiple water-hammer-induced leaks of essential service water piping. These leaks
were the subject of two previous violations issued by the NRC. However, the licensee
failed to take timely corrective actions to restore compliance.
Description. During normal operations, normal service water supplies components in the
essential service water system. During a loss of off-site power, normal service water
pumps stop. Approximately twenty-five seconds later, after the emergency diesel
generators start and power the emergency buses, the essential service water pumps
start to provide cooling water to the essential service water loads. During these twenty-
five seconds when no pumps are running, the essential service water system partially
drains. The starting of the essential service water pumps rapidly fills the system and
- 17 -
causes water hammera rapid pressure spike. This pressure spike can cause leaks in
eroded or corroded sections of essential service water piping.
On August 19, 2009, Wolf Creek Station experienced a loss of off-site power. As a result
of pump cycling during the event, several water-hammer-induced leaks were initiated in
degraded essential service water system piping.
As a result of the 2009 event, the licensee initiated a program to non-destructively
inspect the above ground large bore piping and accessible portions of essential service
water piping located in underground bunkers. This program was intended to collect and
analyze data to determine when repairs were required and when sections of piping
would require replacement. The program was supposed to track the repaired and
replaced portions of piping. After discovering leaks in buried essential service water
piping, ground-penetrating radar was used to confirm these leaks; the ground-
penetrating radar was incorporated into the program.
On January 13, 2012, Wolf Creek experienced another loss of off-site power. Similar to
the 2009 event, this loss of off-site power caused a water hammer of sufficient
magnitude to cause a through-wall leak in corroded essential service water piping. This
leak occurred in the riser piping of the Train C containment cooler. Though this piping is
part of the essential service water flowpath, it was not scoped into the licensees
inspection and tracking program. The licensees system designation for the piping
changed at the flange joints between essential service water and the containment
coolers. Containment coolers were never included in the non-destructive inspection
program.
The team determined that the licensees corrective actions from the August 2009 loss-of-
off-site-power event, which developed the non-destructive inspection program of the
essential service water system, were inadequate because the inspection program did
not include the containment coolers. Additionally, the team noted that the program did
not accurately track and document which sections of essential service water piping had
been inspected and which had not. At the conclusion of the inspection, the licensee was
developing a design change to mitigate the impact of pump restarts on the essential
service water system. The licensee was also performing localized pipe repairs on
corroded areas while evaluating which sections of pipe require larger-scale replacement.
The NRC previously issued Wolf Creek two violations for failure to adequately evaluate
the essential service water system for corrosion and for the effects of water hammer on
corroded areas: NCV 05000482/2009007-03 was identified during a special inspection
following the 2009 water hammer event; VIO 05000482/2010006-05 was identified
during the 2010 problem identification and resolution inspection. The second violation
was cited because the licensee failed to restore compliance within a reasonable time
following the identification of the first violation. Because the licensee still has not
restored compliance, this violation is also cited.
Analysis. The failure to preclude recurrence of water hammer in the essential service
water system and the failure to take adequate corrective action to control internal pitting
corrosion in essential service water piping was a performance deficiency. The deficiency
was more than minor because it is associated with the equipment performance attribute
- 18 -
of the mitigating systems cornerstone objective to ensure the availability, reliability, and
capability of systems that respond to initiating events to prevent undesirable
consequences. It is therefore a finding. Using Inspection Manual Chapter 0609.04,
Phase 1 - Initial Screening and Characterization of Findings, the team determined that
the finding was of very low safety significance (Green) because the finding was a design
or qualification deficiency that was confirmed not to result in loss of system operability or
functionality; the January 12, 2012, leak was too small to cause a loss of system
function. This finding has a cross-cutting aspect in the corrective action program
component of the problem identification and resolution cross-cutting area because the
licensee failed to take appropriate corrective actions to address safety issues and
adverse trends in a timely manner, commensurate with their safety significance (P.1(d)).
Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
requires, in part, that in the case of significant conditions adverse to quality, measures
shall assure that the cause of the condition is determined and corrective action taken to
preclude repetition. Contrary to this requirement, from August 19, 2009, through May
25, 2012, the licensee failed to assure that the cause of a significant condition adverse
to quality was determined and corrective action was taken to preclude repetition.
Specifically, water hammer in a safety-related system that leads to through-wall leaks
from corroded piping is a significant condition adverse to quality. On August 19, 2009, a
loss-of-off-site-power event caused a water hammer in safety-related essential service
water piping. This water hammer resulted in a leak from corroded portions of piping.
The licensee failed to take corrective action to preclude repetition of additional water
hammer events and system leaks due to internal pitting corrosion in the essential service
water system. This was demonstrated on January 13, 2012, when a loss-of-off-site-
power event caused a water hammer event and system leak due to internal pitting
corrosion in the essential service water system. The finding has been entered into the
licensees corrective action program as condition report 53443. Due to the licensees
failure to restore compliance within a reasonable time following previous
NCV 05000482/2009007-03 and VIO 05000482/2012006-05, this violation is being cited
in a Notice of Violation consistent with Section 2.3.2 of the NRC Enforcement Policy:
VIO 05000482/2012007-03, Failure to Take Timely Corrective Action to Preclude
Repetition.
d. Untimely Corrective Actions
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
Appendix B, Criterion XVI, Corrective Action, for the licensees failure to effectively
correct deficient procedures regarding the use of clearance orders. A number of
clearance-related problems revealed several deficiences in procedures to ensure that
safe tag-out of equipment occurred prior to the start of work, that independent reviews of
qualified individuals were being completed during clearance order preparation, and that
effective training was being conducted where performance gaps were identified. The
licensee failed to correct these deficiencies in a timely manner. This finding was entered
into the licensees corrective action program as condition report 53451.
Description. The team determined that effective corrective actions had not been
implemented in a reasonable time following identification of an adverse trend in
clearance order performance during maintenance of both safety-related and nonsafety-
- 19 -
related systems. On September 21, 2010, clearance order D-QA-N-041 included a tag-
out of breaker 8 for the replacement of a light socket. When proceeding with the work, a
live-dead-live test indicated that the circuit was still energized. Further examination
revealed that the wrong breaker had been tagged open. The licensee documented this
error in condition report 28224 and perfomed a root cause evaluation. Though the event
evaluated in the root cause did not involve safety-related equipment, the evaluation
documented a history of work order preparation errors, inadequate clearance order
boundaries, and negative feedback on the use of clearance orders from self-
assessments and surveys. These included a number of issues with safety-related
systems. Corrective actions included procedure changes and training. However, the
root cause indicated that corrective actions to prevent recurrence were not effective.
The most recent post-training survey, completed in February 2012, indicated that the
Clearance Order Group had not noticed a change or improvement since the training on
the revised procedures. This resulted in training needs analysis (TNA) 2012-1087-1,
which was delayed from being reviewed by management for several months due to the
stations forced outage in early 2012. The team determined that effective corrective
actions had not been timely implemented.
Analysis. The team determined that the failure to correct an adverse trend in the use of
clearance orders when performing maintenance on safety-related systems was a
performance deficiency. This finding was more than minor because if left uncorrected, it
could lead to a more significant safety concern. Specifically, continued failure to
establish the correct clearance order boundaries could result in the loss of configuration
control for systems required to maintain nuclear safety. Using Manual Chapter 0609.04,
Phase 1 - Initial Screening and Characterization of Findings, the team determined that
this finding was of very low safety significance (Green) because it was not a design or
qualification deficiency, did not represent a loss of system safety function, and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event. The team determined that this finding has a cross-cutting aspect in the
resources component of the human performance cross-cutting area because the
licensee failed to ensure complete, accurate and up-to-date design documentation,
procedures, and work packages were available and adequate to support nuclear safety
(H.2(c)).
Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
requires, in part, that measures be established to assure that conditions adverse to
quality are promptly identified and corrected. Contrary to this requirement, from
September 2010 through February 2012, the licensee failed to assure that measures
were established to assure that a condition adverse to quality was promptly corrected.
Specifically, following identification of an adverse trend in the effective use of clearance
orders for safety-related and nonsafety-related equipment maintenance, the licensee
failed to implement corrective action to ensure safe tag-out of equipment had occurred
prior to the start of work, that independent reviews of qualified individuals were being
completed in the clearance order preparation, and that effective training was being
conducted where performance gaps were identified. This finding was entered into the
licensees corrective action program as condition report 53451. Because this finding is
of very low safety significance (Green) and has been entered into the licensees
corrective action program, this violation is being treated as a non-cited violation
- 20 -
consistent with section 2.3.2 of the NRC Enforcement Policy: NCV 05000482/2012007-
04, Untimely Corrective Action.
e. Failure to Establish Procedures to Ensure Completion of Corrective Actions
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to
establish adequate procedures for resolution of corrective actions. Specifically, the
licensee failed to establish procedures to ensure that planned corrective actions were
effectively implemented. This finding was entered into the licensees corrective action
program as condition report 53432.
Description. The team identified two examples where the licensee had failed to
establish procedures to ensure that corrective actions were completed as intended:
Attachment G to Procedure AP 28A-100, Condition Reports, Revision 16, noted that
level 3 (apparent cause) condition reports fall under the oversight of the corrective action
review board (CARB). Paragraph 6.14.1.2 of this procedure required that the condition
report owner ensure that actions have been satisfactorily performed prior to closing the
action. Contrary to this, on June 8, 2011, actions 02-06, 02-07, and 02-08 of apparent
cause 34661 to add caution statements or notes to work order templates or instructions
were closed by the assigned action owner without the procedure changes being made.
In the closure documentation, the action owner stated that he did not feel the changes
should be made to the documents listed. Instead, the action owner added a document
to the maintenance history noting a need for these notes. However, the team noted that
there was no procedural requirement that such comments from maintenance history be
incorporated into new work orders. Rather, procedure AI 16C-007, Work Order
Planning, Revision 31, noted that when developing a work instruction, a check for
existing instructions or procedures and a review of maintenance history were among a
six-page list of elements to consider for the planners. The most recent revision of AI
16C-007Revision 38contained identical language.
Corrective actions for the apparent cause documented in condition report 27015
included action 02-03 to investigate plants that received violations for not having
evaluations for crimping failure on the external Emergency Diesel Generator exhaust.
On September 10, 2010, this item was closed by the assigned action owner citing a
statement in the updated safety analysis report (USAR) that diesel operation inhibition
was extremely unlikely due to tornado missiles. Closure of this item due to existing
USAR reference did not meet the intent of evaluating other plant violations for
vulnerabilities at Wolf Creek. The original actions were assigned by the stations CARB,
a management-level group. The action owner closing the item with no actions
completed did so at a lower organizational level; there was no management or CARB
review of this closure. It should also be noted that the historical USAR reference does
not necessarily negate the need for a current evaluation of crimping.
Analysis. The failure to establish adequate procedures for resolution of corrective
actions was a performance deficiency. This finding was more than minor because if left
uncorrected, it would have the potential to lead to a more significant safety concern.
Specifically, failure to establish adequate procedures for resolution of corrective actions
- 21 -
could result in important actions not being accomplished. Using Manual Chapter
0609.04, Phase 1 - Initial Screening and Characterization of Findings, this finding was
determined to be of very low safety significance (Green) because it was not a design or
qualification deficiency, did not represent a loss of system safety function, and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event. This finding has a cross-cutting aspect in the decision making
component of the human performance cross-cutting area because the licensee failed to
demonstrate that nuclear safety is an overriding priority by making safety-significant or
risk-significant decisions using a systematic process (H.1(a)).
Enforcement. Title 10 CFR Part 50, Criterion V, Corrective Action, requires, in part,
that activities affecting quality be prescribed by documented instructions, procedures, or
drawings of a type appropriate to the circumstances and shall be accomplished in
accordance with those instructions, procedures, and drawings. Contrary to this
requirement, on September 10, 2010, and June 8, 2011, the licensee failed to ensure
that activities affecting quality were prescribed in documented procedures and
accomplished in accordance with those procedures. Specifically, the licensee failed to
establish adequate procedures to ensure that corrective actions were completed as
intended. Because this finding is of very low safety significance and has been entered
into the licensees corrective action program as condition report 53432, this violation is
being treated as a non-cited violation consistent with section 2.3.2 of the NRC
Enforcement Policy: NCV 05000482/2012007-05, Failure to Establish Procedures to
Ensure Completion of Corrective Actions.
f. Failure to Implement Corrective Actions to Test Safety-Related Equipment
Introduction. The team identified a Green violation of 10 CFR Part 50, Appendix B,
Criterion XVI, Corrective Action, for the licensees failure to perform testing of safety-
related spring-loaded tornado dampers in the emergency diesel generator and essential
service water rooms. In 2008, the licensee identified that because the updated safety
analysis report (USAR) incorrectly classified these active components as passive, they
had not been included in a periodic testing or surveillance program. Since 2010, action
items to test the dampers have received four extensions. Additionally, required training
for this testing was completed and closed. No testing or surveillance had been
accomplished. This failure was the subject of a previous violation issued by the NRC.
However, the licensee failed to take timely corrective actions to restore compliance.
Description. The Wolf Creek emergency diesel generator room and essential service
water room ventilation system design includes four spring-loaded dampers that are
required to automatically close in the event of high differential pressures associated with
a design basis tornado. The safety function of these dampers is to protect the heating
ventilation and air conditioning system ductwork and components from postulated high-
pressure differentials. In 2008, Wolf Creek personnel identified that these dampers had
been incorrectly classified as passive components and were not being periodically
tested; Condition Report 2008-003276 was initiated to revise Procedure MPE VD-001,
Ventilation Damper Maintenance, to accomplish testing. Later in 2008, the procedure
was updated and the corrective action was closed. However, no action was taken to
ensure that the required testing would be performed as part of the scheduled preventive
maintenance activities.
- 22 -
In 2010, the NRC issued a violation (NCV 05000482/2010007-02) for the licensees
failure to implement the planned corrective actions. On September 20, 2010, the
licensee initiated condition report 28185, noting that the procedure change was never
communicated to the planners and that there was no corrective action initiated to write a
work order for the testing. Condition report 29602 was written in October 2010
documenting NCV 2010007-02. Since 2010, corrective actions from these condition
reports have received four due date extensions. No testing or surveillance had ever
been accomplished.
This finding was entered into the licensees corrective action program as condition report
53363.
Analysis. The team determined that the licensees failure to implement corrective action
was a performance deficiency. This finding was more than minor because it affected the
equipment reliability attribute of the mitigating systems cornerstone objective to ensure
the availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences. Specifically, failure to implement this corrective
action could result in reduced reliability of safety-related equipment during an event
initiated by a tornado. Using Chapter 0609.04, Phase 1 - Initial Screening and
Characterization of Findings, the team determined that this finding was of very low
safety significance (Green) because it was not a design or qualification deficiency, did
not represent a loss of system safety function, and during a tornado, would not cause a
plant trip if failed, would not degrade two or more trains of a multi-train safety system,
and would not degrade one or more trains of a system that supports a safety system or
function. This finding has a cross-cutting aspect in the resources component of the
human performance cross-cutting area because the licensee failed to provide complete,
accurate, and up-to-date design documentation, procedures, and work packages
available and adequate to support nuclear safety (H.2(c)).
Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
requires, in part, that measures be established to assure that conditions adverse to
quality are promptly identified and corrected. Contrary to this requirement, from 2008
through May 2012, the licensee failed to establish measures to assure that a condition
adverse to quality was promptly identified and corrected. Specifically, the licensee failed
to assure that the identified emergency diesel generator and essential service water
pump room tornado damper testing deficiency was corrected. This finding was entered
into the licensees corrective action program as condition report 53363. Because the
licensee failed to restore compliance in a timely manner after this condition was
identified as a non-cited violation in inspection report 05000482/2010007, this violation is
being cited in a Notice of Violation consistent with Section 2.3.2 of the NRC Enforcement
Policy: VIO 05000482/2012007-06, Failure to Implement Corrective Actions to Test
Safety-Related Equipment.
g. Failure to Determine the Cause of a Significant Condition Adverse to Quality
Introduction. On February 23, 2011, a Green non-cited violation of 10 CFR Part 50,
Appendix B, Criterion XVI, Corrective Action, was revealed when an anomalous start of
component cooling water (CCW) pump B indicated gas voiding in the CCW piping. This
- 23 -
violation was due to the licensees inadequate root cause evaluation and failure to
prevent recurrence of the voiding that had previously occurred in May 2010.
Description. On May 24, 2010, the licensee observed acoustic anomolies during the
start of a test of CCW pump A. During investigation, ultrasonic testing revealed multiple
voids in the pump suction piping, the pump discharge piping, and the shell side of the
residual heat removal heat exchanger. The licensee took immediate corrective action to
vent the voids where possible; however, they were unable to get the piping sufficiently
vented to justify continued operability. Train A CCW was declared inoperable on June 3,
2010.
On September 1, 2010, the licensee completed a root cause evaluation of this event.
The evaluation identified the root cause was personnels misconceptions and
misunderstanding of gas voiding and gas accumulation within the CCW piping.
Specifically, the evaluation identified that operators and engineers believed that the
system was self-venting through the CCW surge tank. Further, personnel did not
understand the mechanisms of void formation (i.e., gas coming out of solution with
increases in temperature). The licensee identified plant design issues only as a
contributing cause, not as a root cause. The licensee failed to recognize that without
system modifications to install additional high point vents, there would not be a
significant reduction in the likelihood of this voiding condition occurring, regardless of the
knowledge level of personnel. While the action plan did specify evaluation and
installation of such vents, implementation was deferred until the next scheduled outage
in March 2011 despite a forced outage opportunity in October 2010.
On February 23, 2011, Wolf Creek experienced a similar anamolous start of CCW pump
B. During this event, the CCW system pressure dropped such that the second pump on
the train started automatically. Once again, ultrasonic readings confirmed unsatisfactory
voiding and the CCW train was declared inoperable. On July 24, 2011, Wolf Creek
completed another root cause analysis as part of condition report 33925. This root
cause evaluation properly identified the plant design issues as the root cause. By the
time the root cause evaluation was completed, the additional eight high-point vents had
already been installed during the Spring 2011 refueling outage. Since the installation of
the additional vents, routine CCW void monitoring has identified only very small voids
well below the established operability limits.
The team determined that the corrective actions to install the required vents were not
implemented timely to prevent recurrence. The root cause performed under condition
report 33925 also identified the inadequacies in evaluation and actions implemented by
condition report 25918. However, because the significant condition adverse to quality
recurred, the inspectors determined that the finding was self-revealing rather than
licensee-identified.
Analysis. The failure to properly identify design issues as a root cause and to take
action to prevent the recurrence of a CCW system voiding was a performance
deficiency. The performance deficiency is more than minor because it impacted the
equipment performance attribute of the mitigating systems cornerstone objective to
ensure the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. Specifically, excessive voiding of the
- 24 -
CCW system could lead to lack of cooling to important safety-related components.
Using Manual Chapter 0609.04, "Phase 1 - Initial Screening and Characterization of
Findings," the team determined that the issue was of very low safety significance
(Green) because it did not represent a loss of system safety function or loss of a single
train for longer than its technical specification allowed outage time. This finding has a
cross-cutting aspect in the corrective action program component of the problem
identification and resolution cross-cutting area because the licensee failed to thoroughly
evaluate a problem such that its resolution addressed its cause and extent of condition.
Specifically, condition report 25918 did not properly identify design issues as a root
cause requiring immediate system modifications to preclude recurrence (P.1(c)).
Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
requires, in part, that for significant conditions adverse to quality, measures shall assure
that the cause of the condition is determined and that corrective actions are taken that
preclude repetition. Contrary to this requirement, from May 24, 2010, through February
23, 2011, the licensee failed to assure that the cause of a significant condition adverse to
quality was determined and that corrective actions were taken to preclude repetition.
Specifically, voiding of the CCW system that could lead to lack of cooling to important
safety related components is a significant condition adverse to quality. After a May 2010
CCW voiding event, the licensee failed to preclude repetition of this voiding by taking
appropriate corrective actions; voiding recurred in February 2011. Because this finding
was determined to be of very low safety significance (Green) and was entered into the
licensees corrective action program as condition report 33925, this violation is being
treated as a non-cited violation consistent with section 2.3.2 of the NRC Enforcement
Policy: NCV 05000482/2012007-07, Failure to Determine the Cause of Component
Cooling Water System Voiding.
h. Failure to adequately evaluate the suitability of nonsafety-related gaskets, o-rings, and
seals installed in safety-related equipment and to identify extent of the condition
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
Appendix B, Criterion III, Design Control, for the licensees failure to evaluate the
suitability of nonsafety-related gaskets, o-rings, and seals installed in safety-related
components. These nonsafety-related parts were originally installed due to erroneous
Safety Classification Assessments (SCAs). After determining that the parts were
inappropriate in safety-related joints, the licensee failed to promptly correct the condition
and failed to fully identify which components were affected.
Description. On September 21, 2010, a licensee maintenance planner recognized that
during planned maintenance, a nonsafety-related (NSR) pump casing gasket had been
installed on the safety-related (SR) jacket water keep-warm pump for emergency diesel
generator (EDG) B. The planner initiated condition report 28208 to address the issue.
The NSR gasket had been approved for use in SCA 91-0408, a generic SCA for gaskets.
The SCA was written by a vendor and approved for use in August 1991. It permitted the
use of nonsafety-related gaskets in safety-related systems that only interface with water
or steam, where those systems had unlimited make-up capability. This SCA assumed
that all water and steam systems are capable of making up water and steam gasket
leakage losses. The EDG jacket water cooling system has makeup capability provided
- 25 -
by the demineralized water storage and transfer system. This system is not safety-
related and cannot be assumed to be available during a design-basis accident.
Therefore, the application of SCA 91-0408 to allow nonsafety-related gaskets to be used
in the safety-related EDG jacket water cooling system was inappropriate. More broadly,
this SCA and various locally-generated subcomponent SCAs were used to place
nonsafety-related gaskets, o-rings, and seals in many other safety-related systems,
some of which also may not have unlimited makeup capability. This was identified by
the licensee in the root cause evaluation conducted under condition report 28208.
In response to this condition, all nonsafety-related SCAs associated with safety-related
components were reviewed by the licensee, and administratively revised or replaced if
found to be faulted. Nonsafety-related gaskets, o-rings, and seals which were
determined to be inappropriately installed were replaced with safety-related material on
the EDG system only. This effort to replace nonsafety-related components did not
extend to the other affected safety-related systems; the licensee did not review work
history to determine which components in the affected systems actually contained
nonsafety-related material. For example, SCA 10-0086 covers gaskets in the
emergency fuel oil system. This SCA was administratively revised because of an
inadequate nonsafety-related evaluation, but the nonsafety-related gaskets in that
system were not specifically identified or replaced. Other affected systems include,
among others, the reactor coolant system, the residual heat removal system, the
essential service water system, and the auxiliary feedwater system. Engineering
Disposition/Configuration Change Package 13716 described below was generated as
justification.
The licensee approved Engineering Disposition/Configuration Change Package 13716 to
address the inappropriate installation of nonsafety-related gaskets, o-rings, and seals in
safety-related equipment due to the erroneous application of SCA 91-0408. Revision 3
of this Engineering Disposition allowed the facility to use-as-is the affected gaskets
until the next planned work in which the affected joints were to be opened. At that time,
the gaskets would be replaced; the licensee concluded that no new field work was
needed to address the non-conformance. The licensee did not evaluate exactly which
components were affected by this SCA, but rather justified generic acceptance of all
NSR gaskets, o-rings, and seals if they had not leaked prior to refueling outage 18. The
licensee cited historic non-leakage, skill of the craft of maintenance persons installing
the gaskets, and historic high acceptance rate of nonsafety-related gaskets during
commercial grade dedication as sufficient evidence that the affected components were
acceptable for continued use until eventual replacement at indeterminate dates.
The licensee defined critical gasket acceptance characteristics by citing EPRI TE
CGIGA01, Commercial Grade Item Evaluation for Gaskets, Non-Metallic and Spiral
Wound. Critical characteristics for acceptance were (emphasis added):
- Markings indication the proper item was received
- Configuration proper fit-up
- Material the most important characteristic as it covers a significant number of
critical characteristics for design, such as compressibility, creep relaxation,
pressure rating and resistance to internal and external elements.
- 26 -
- Thickness ensures sealability and pressure retention. Inadequate thickness =
poor seal. Excessive thickness = reduced resistance to internal / external
pressure due to large force acting radially.
The team noted in the above statement that the most important acceptance
characteristic for gaskets was material such as compressibility, creep relaxation,
pressure rating and resistance to internal and external elements. None of the
justifications for accepting continued usage of the non-conforming components can
adequately verify these material characteristics without knowing what materials were
actually installed. Additionally, the licensee cited USA 5059 Resource Manual, Applying
10 CFR 50.59 to Compensatory Actions to Address Nonconforming or Degraded
Conditions, Section 4.2.5, as their method for addressing the non-conformance. This
section allowed three courses of action for addressing non-conforming conditions; the
licensee chose to employ the first of the three, which reads:
If the licensee intends to restore the SSC back to its as-designed condition then this
corrective action should be performed in accordance with 10 CFR 50 Appendix B
(i.e., in a timely manner commensurate with safety). This activity is not subject to 10
CFR 50.59. (emphasis added)
NRC Inspection Manual Part 9900, Section 7.2, Timing of Corrective Actions, requires
that The licensee should establish a schedule for completing a corrective action when
an SSC is determined to be degraded or nonconforming. The team determined that an
indefinite replacement schedule dependent upon the regular course of maintenance for
unidentified nonconforming components did not meet the definition of timely. This
approach will also not allow the licensee to know when conformance has been restored,
because the actual extent of the condition is not known. The licensee documented this
issue in Condition Report 53456.
Analysis. The failure of the licensee to evaluate the suitability of the specific nonsafety-
related material installed in safety-related equipment and to determine the extent to
which this condition existed was a performance deficiency. This performance deficiency
was more than minor because it affected the design control attribute of the mitigating
systems cornerstone objective to ensure the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences.
Specifically, the inadequate evaluation of nonsafety-related gaskets, o-rings, and seals
installed in safety-related equipment adversely affected the reliability of the affected
systems. Using Manual Chapter 0609.04, "Phase 1 - Initial Screening and
Characterization of Findings," the team determined that the finding was of very low
safety significance (Green) because the finding was a design or qualification deficiency
confirmed not to result in loss of operability or functionality. This performance deficiency
had a cross-cutting aspect in the corrective action program component of the problem
identification and resolution cross-cutting area because the licensee did not take
appropriate corrective actions to address safety issues and adverse trends in a timely
manner, commensurate with their safety significance and complexity (P.1(d)).
Enforcement. Title 10 CFR Part 50, Appendix B, Criterion III Design Control, requires,
in part, that measures be shall established for the selection and review for suitability of
application of materials, parts, equipment, and processes that are essential to the safety-
- 27 -
related functions of the structures, systems and components. Contrary to this
requirement, on September 12, 2011, the licensee failed to establish measures for the
selection and review for suitability of application of materials and parts that are essential
to the safety-related functions of structures, systems, and components. Specifically, the
licensee approved Engineering Disposition/Configuration Change Package 013716,
Revision 3, which allowed nonsafety-related gaskets, o-rings, and seals to remain
installed in safety-related piping joints until such time as the affected joints were next
opened in the normal course of maintenance; the engineering disposition did not identify
the specific components affected or the suitability of the installed materials. Because
this finding is of very low safety significance (Green) and was entered into the corrective
action program as condition report 53456, this violation is being treated as a non-cited
violation, consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000482/2012006-08, Failure to Adequately Evaluate the Suitability of Nonsafety-
related Gaskets, O-Rings, and Seals Installed in Safety-Related Equipment and to
Identify Extent of the Condition.
i. Inappropriately High Threshold for Condition Report Initiation
Introduction. The team identified a Green finding for the licensees failure to ensure that
condition reports were initiated as required by procedure. The licensees implementing
procedure for its corrective action program did not contain clear guidance as to what
conditions were required to be entered into the corrective action program, or how soon
after discovery a condition report was required to be generated. The team identified
several examples where condition reports were not generated, though it appeared from
the guidance that one was required.
Description. Step 6.2.1 of the licensees condition reporting procedure, AP 28A-100,
Condition Reports, Revision 15A, requires personnel to promptly initiate a condition
report for equipment, human, organizational, program, process, or procedure
performance issues. Contrary to this requirement, the team identified a number of
examples where, prior to May 24, 2012, licensee personnel failed to initiate a condition
report:
- On May 10, 2012, during a walkdown of emergency core cooling system (ECCS)
pumps in response to industry operating experience, an operator noted several oil
leaks that appeared to be long-standing but were not documented in an open
condition report, work order, or work request. The team determined that these oil
leaks were adverse conditions as defined in AP 28A-100, and should therefore
have been documented in the corrective action program.
- Also on May 10, 2012, during the ECCS walkdown, the operator noted at least two
deficiency tags that were old, faded, and unreadable. While the operator took
action to replace the tags with readable ones, no condition report was initiated to
document the existence of the old, worn tags. The team determined that the
condition of these tags indicated an issue either (a) of operators and engineers not
routinely reading the tags to ensure existing leaks had not worsened or (b) of
complacency on the part of plant personnel to the tags deteriorating to an
unreadable condition. Thus the team concluded that the licensee failed to initiate a
condition report for a human performance issue as required by AP 28A-100.
- 28 -
- In condition report 51480, initiated on April 11, 2012, the licensee identified an
undocumented diesel fuel oil leak that was found with an absorbant pad underneath
it to collect the leaking oil. The team determined that the existence of the absorbant
pad indicated that the leak had been previously discovered by licensee personnel,
but that the personnel had failed to document the adverse condition in the corrective
action program.
The team further noted two potential discrepancies in procedure AP 28A-100 that could
cause confusion:
First, step 6.1.1 of AP 28A-100 states, Anyone can, and is expected to, initate a
Condition Report (CR) when they discover an Adverse Condition (emphasis added).
Adverse condition is defined in Attachment B as one of seven conditions or trends and is
amplified with a 42-item list of examples. However, as noted above, step 6.2.1 of AP
28A-100 states the requirement that personnel shall promply initate a CR for
equipment, human, organizational, program, process, or procedure performance issues
(emphasis added). The team determined that the difference in language between the
two procedure steps indicated that step 6.2.1 was a requirement while step 6.1.1 was
not.
Second, step 6.2.4 of AP 28A-100 reads, If the issue has any potential to impact the
plant or personnel safety, initiation shall not be later than the end of the work shift. The
team determined that the conditional statement required the condition report initiator to
perform a field evaluation of an adverse condition to determine whether or not it might
impact safety. The initiator may not be the most knowledgable individual about the
identified condition or the most qualified to evaluate it. The initiator may therefore
incorrectly decide that there is no potential safety impact and opt to delay entering the
condition into the corrective action program. The team determined that this could lead to
a potentially safety-significant condition not being promply addressed.
Analysis. The failure of licensee personnel to promptly initiate condition reports for
identified issues, contrary to procedural requirements, is a performance deficiency. This
performance deficiency is more than minor because if left uncorrected, it could lead to a
more significant safety concern. Using Inspection Manual Chapter 0609.04, Phase 1 -
Initial Screening and Characterization of Findings, the team determined that this finding
was of very low safety significance (Green) because it did not involve a design or
qualification deficiency, did not represent a loss of system safety function, and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event. This finding has a cross-cutting aspect in the resources component of
the human performance cross-cutting area because the licensee failed to ensure
procedures necessary for complete, accurate, and up-to-date procedures were available
and adequate to support nuclear safety. Specifically, the corrective action program
procedure was vague in its guidance as to when a condition report was required
(H.2(c)).
Enforcement. There was no identified violation of NRC requirements associated with
this finding. The licensee documented this deficiency in its corrective action program as
Condition Report 53445. Because this finding did not involve a violation of regulatory
- 29 -
requirements and had very low safety significance (Green), it is identified as a finding:
FIN 05000482/2012007-09, Inappropriate Threshold for Condition Report Initiation.
.6 Miscellaneous Issue Follow-Up
a. (Closed) URI 05000482/2012008-06, Review Actions to Correct Water Hammer Events
in the ESW System
Unresolved Item (URI)05000482/2012008-06 documents long-standing problems of
water hammer events in the essential service water system and the concern that the
actions to correct this problem have not been timely. The team determined that the
licensees efforts to correct a water hammer problem in the essential service water
system warranted additional NRC review and follow-up because this phenomenon has
repetitively challenged the integrity of a risk-significant safety-related system.
This URI was evaluated as part of the violation documented in section 4OA2.5.c of the
report. URI 05000482/2012008-06 is closed.
b. (Closed) URI 05000482/2012008-07, Review ESW Piping Corrosion Inspections
URI 05000482/2012008-07 documented why previous efforts were not sufficient to
detect corrosion problems before they developed into leaks and that water hammer
events made leaks more likely. The team determined that the licensees failure to
examine the condition of vendor-supplied piping associated with the containment coolers
as well as other areas of ESW piping warranted additional NRC review and follow-up.
This URI was evaluated as part of the violation documented in section 4OA2.5.c of the
report. URI 05000482/2012008-07 is closed.
4OA6 Meetings
Exit Meeting Summary
On May 24, 2012, the team presented the inspection results to Mr. M. Sunseri, President and
Chief Executive Officer, and other members of the licensee staff. Licensee management
acknowledged the issues presented. The inspector asked the licensees management whether
any materials examined during the inspection should be considered proprietary. No proprietary
information was identified.
ATTACHMENT: SUPPLEMENTAL INFORMATION
- 30 -
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
T. Baban, Manager Systems
K. Hargis, Supervisor Corrective Action
L. Hauth, Work Control Senior Reactor Operator
S. Henry, Manager Operations
J. Isch, Superintendant Operations Work Controls
W. Muilenburg, Supvervisor Licensing
E. Peterson, Ombudsman
R. Rumas, Manager Quality
G. Sen, Manager Regulatory Affairs
J. Yunk, Manager Corrective Action
NRC personnel
C. Long, Senior Resident Inspector
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
05000482/2012007-03 VIO Failure to Take Timely Corrective Action to Preclude Repetition
(Section 4OA2.5.c)05000482/2012007-06 VIO Failure to Implement Procedures to Test Safety-Related
Equipment (Section 4OA2.5.f)
Opened and Closed
05000482/2012007-01 NCV Inadequate Procedure to Implement Compensatory Measures
(Section 4OA2.5.a)05000482/2012007-02 NCV Failure to Report Conditions that Could have Prevented
Fulfillment of a Safety Function (Section 4OA2.5.b)05000482/2012007-04 NCV Untimely Corrective Action (Section 4OA2.5.d)05000482/2012007-05 NCV Failure to Complete Corrective Actions (Section 4OA2.5.e)05000482/2012007-07 NCV Failure to Prevent Recurrence of Component Cooling Water
System Voiding (Section 4OA2.5.g)05000482/2012007-08 NCV Failure to Adequately Evaluate the Suitability of Nonsafety-related
Gaskets, O-Rings, and Seals Installed in Safety-Related
Equipment and to Identify Extent of the Condition (Section
4OA2.5.h)05000482/2012007-09 FIN Inappropriately High Threshold for Condition Report Initiation
(Section 4OA2.5.i)
-1- Attachment 1
Closed
05000482/2012008-06 URI Review Actions to Correct Water Hammer Events in the ESW
System (Section 4OA2.6.a)05000482/2012008-07 URI Review ESW Piping Corrosion Inspections (Section 4OA2.6.b)
Discussed
None
LIST OF DOCUMENTS REVIEWED
CONDITION REPORTS
11247 25866 26712 28077 29163 31783 34620 40842 49716
12913 25867 26752 28088 29164 31818 34661 40933 50271 15077 25868 26753 28175 29252 31839 34896 40959 51292
20099 25869 26760 28187 29464 31848 34900 41151 51480
20153 25870 26826 28208 29467 32081 34902 41569 51931
20717 25871 26855 28224 29538 32227 34964 41613 51949
21039 25872 26940 28234 29559 32228 34987 41853 51951
21703 25873 27015 28252 29601 32233 35341 41975 51982
22296 25874 27027 28303 29602 32487 35343 41997 52917 22989 25880 27032 28346 30151 32680 36600 42349 52918 23024 25881 27034 28367 30201 32689 36973 42537 52981 23108 25882 27073 28376 30219 32761 36992 42618 52984 23110 25883 27077 28403 30235 32792 36993 42635 52985 23331 25884 27106 28474 30374 32886 36994 42737 53005
23992 25885 27108 28539 30566 32887 36996 43265 53047
24073 25886 27110 28562 30610 33199 37244 43278 53051
24183 25887 27145 28564 30918 33253 37374 43435 53058
24646 25888 27147 28575 31024 33258 37690 43515 53061
25058 25896 27172 28579 31039 33357 37931 44963 53062
25224 25918 27336 28620 31136 33395 38593 45320 53064
25228 25951 27484 28644 31193 33603 38965 45333 53200
25353 26001 27603 28652 31265 33773 39173 45758 53319
25404 26050 27605 28722 31428 33909 39187 45839 53342
25460 26070 27650 28854 31430 33925 39338 46131 53363
25463 26216 27718 28945 31432 33982 39494 46137 53369
-2-
CONDITION REPORTS
25478 26223 27949 28959 31557 34029 39995 46163 53390
25498 26302 27976 28990 31586 34206 40047 46814 53393
25658 26335 27982 29027 31617 34267 40219 47094 53394
25848 26354 28046 29105 31626 34455 40555 47813 53407
25863 26651 28048 29108 31641 34463 40707 47993 53456
25864 26678 28050 29152 31745 34465 40802 48141 53458
25865 26686 28067 29162 31746 34604 40841 49276
PROCEDURES
REVISION /
NUMBER TITLE DATE
AI 14-006 Severe Weather 12
AI 16C-006 MPAC Work Request/Work Order Process Controls 19
AI 16C-007 Work Order Planning 31
AI 16C-007 Work Order Planning 38
AI 20-001 WCNOC Quality Oversight Report 3
AI 20-004 QA Continuous Improvement 3
AI 20A-005 Quality Assurance Standards and Expectations 1A
AI 20E-001 Industry Operating Experience Group 8
AI 21D-006 Response to Plant Status Control Problems 8
AI 21D-007 Response to Clearance Order Issues 6
AI 21E-003 Clearance Order Improvement 3
AI 22A-001 Operator Work Arounds/Burdens/Control Room Deficiencies 10A
AI 22C-016 Unit Condition and Operational Residual Risk 0
AI 28A-010 Screening Condition Reports 11
AI 28A-010 Screening Condition Reports 12
AI 28A-023 Evaluation of Maintenance Rule Functional Failure CRs 2A
AI 28A-100 Cause Evaluations 0
AI 28A-100 Cause Evaluations 1A
AI 28A-100 Condition Reports 15A
AI 29B-003 Guidance to Prevent Unacceptable Preconditioning Prior to 2
Testing
AI 30E-003 Training Needs Analysis/Design Scope and Planning 14
-3-
PROCEDURES
REVISION /
NUMBER TITLE DATE
AI-28A-100 Cause Evaluations 0
AIF-16C-011-02 Walkdown Form ----
AP 05J-001 Quality Group D (Augmented) Quality Program 5
Requirements
AP 10-002 Fire Protection Program Requirements 7
AP 14A-003 Scaffold Construction and Use, For Category I Building and 18A
Structures
AP 14A-004 Scaffold Construction and Use, For Non-Category I Building 2
and Structures
AP 15C-002 Procedure Use and Adherence 35
AP 15C-004 Preparation, Review and Approval of Procedures, 41
Instructions and Forms
AP 20-001 Quality Stop Work and Escalation Processes 5
AP 20A-003 QA Audit Requirements, Frequencies and Scheduling 22
AP 20A-004 Conduct of Internal Audits 15
AP 20A-006 QA Issue Development, Reporting and Follow-up Processes 14
AP 20A-008 QA Surveillance and Station Monitoring Program 13
AP 20A-009 Quality Organization 4A
AP 20E-001 Industry Operating Experience Program 20
AP 20G-001 Control of Inspection Planning and Inspection Activities 13
AP 21-001 Conduct of Operations 54A
AP 21D-005 Plant Component Status Control 12
AP 21E-001 Clearance Orders 30
AP 21I-001 Temporary Modifications 8A
AP 22-001 Conduct of Pre-Job and Post-Job Briefs 13
AP 23-008 Equipment Reliability Program 4
AP 23E-001 Emergency Diesel Generator Reliability Program 7A
AP 24E-006 Replacement Item Selection 4
AP 28-007 Nonconforming and Degraded Conditions 9
AP 28A-100 Condition Reports 15A
-4-
PROCEDURES
REVISION /
NUMBER TITLE DATE
AP 28A-100 Condition Reports 16
AP 30D-010 Supplemental Personnel Training and Qualification 9
AP 30G-001 Training, Qualification, and Certification of Audit Personnel 8
AP 30G-002 Training by Quality 4C
AP-13-001 Fatigue Management 18
APF 22-001-01 Pre-Job Brief Checklist 16
APF 26A-003-01 Applicability Determination 12
APF 26B-003-01 USAR Change Request for 9.4 Tornado Damper 5
APF 30E-004-01 Basic Bearing and Lubrication Lesson Plan: Fabricate and 5
Install Threaded Piping
APF 30E-004-01 Corrective Action Program Leadership Process/Software 4
Training
GEN 00-004 Power Operation 69
GEN 00-005 Minimum Load to Hot Standby 71
I-ENG-004 Lubricating Oil Analysis 4
MGE LT-008 Routine Electrical Limitorque Operator Maintenance 6
MPM LT-001 Limitorque Operator Minor Maintenance, Lubrication, and 13A
Inspection
OFN AF-025 Unit Limitations 37
OFN BB-031 Shutdown LOCA 21
OFN MA-001 Load Rejection or Turbine Trip 17
OFN RP-013 Control Room Not Habitable 17
OFN RP-013A Hot Standby to Cold Shutdown from Outside the Control 1
Room
OFN RP-014 Hot Standby to Cold Shutdown from Outside the Control 14
Room
OFN RP-017 Control Room Evacuation 40
SEC 50-123 Security of Normal Requirements 23
STN AC-007 Turbine Overspeed Trip Test 28
STS AB-205 Main Steam System Inservice Valve Test 29
-5-
PROCEDURES
REVISION /
NUMBER TITLE DATE
STS AB-206 Main Steam System Inservice Valve Test (MSIVs Retest) 8
STS AC-001 Main Turbine Valve Cycle Test 26
STS PE-007 Periodic Verification of Motor Operated Valves 4
SYS AB-120 Main Steam and Steam Dump Startup and Operations 30A
SYS BG-201 Shifting Charging Pumps 50
WCQPM Wolf Creek Quality Program Manual 8
OPERATIONAL BURDENS / WORK-AROUNDS / CONTROL ROOM DEFICIENCIES
11-OW108 11-OB107 10-CRD120 11-CRD118 12-CRD119
12-OW101 11-OB125 08-CRD100 11-CRD195 12-CRD122
10-OB117 12-CRD111 11-CRD203
WORK ORDERS
08-305414 11-340104 11-346698 11-346174
10-325126 10-325125 10-325123 10-324270
08-308675 08-308676 08-308673 07-294389
09-322158-002 09-322158-001 10-325122 08-305212
MISCELLANEOUS DOCUMENTS
NUMBER TITLE REVISION /
DATE
Corrective Action Backlog Reduction Initiative 2
Corrective Action Recovery Monitoring Metrics March 2012
Corrective Action Recovery Monitoring Metrics April 2012
New Employee Orientation Checklist 11/10/11
QA Audit 12-04-CAP Corrective Action Program Exit
QA Audit Report 12-04-12: Corrective Action Program 5/21/12
Reportability Evaluation Request 2010-079 9/22/10
-6-
MISCELLANEOUS DOCUMENTS
NUMBER TITLE REVISION /
DATE
Control Room Deficiency / Operator Workaround / 5/11/2012
Operator Burden / Work Request Tag Log
EDG SCA Review - Procurement Engineering ----
EDG System Performance Team Charter ----
Emergency Diesel Generator Reliability / Availability 6
Improvement Plan
Management Review Meeting Presentation: EDG 3/23/2012
Reliability Improvement Program
NSR SCA in SR System Review - Procurement ----
Engineering
Operations Crews D and E Work Hours: 1/5/2012 to ----
1/27/2012
WCNOC Westinghouse Sensitivity Study for MSPI ----
Margin
10-04-CAP Quality Assurance Audit Report Corrective Action 6/7/10
Program
10-07-FP Quality Assurance Audit Report Fire Protection 10/05/10
Program
10-11-FM QA Audit Report of Fatigue Management Program 6/7/2010
11-03-SEC Quality Assurance Audit Report Security 4/5/11
11-04-ENG Quality Assurance Audit Report Engineering Programs 9/14/11
11-05-SEC Quality Assurance Audit Report Security Program 7/19/11
11-06-EP Quality Assurance Audit Report Emergency 8/18/11
Preparedness Program
11-07-QA Quality Assurance Audit Report Quality Assurance 9/9/11
Program
12-04 CAP Corrective Action Program 4/25/2012
2010-1195-8 Status Control Training 8/2/2010
2011-1175-1 Status Control Training Rev 1 7/12/2011
2011-1205-1 Status Control Errors Continue 7/29/2011
2011-1375-1 Status Control Training 12/20/2011
-7-
MISCELLANEOUS DOCUMENTS
NUMBER TITLE REVISION /
DATE
APF 05-002-01 Engineering Screening: NSR Gaskets Installed in SR 0
Equipment. CCP 13716
APF 20-002-01 Plant Personnel Statements: January 2012 Post-Trip 10
Interviews (13)
CCP 13716 NSR Gaskets Installed in SR Equipment Revs 1-3
CR 40555 Class 1E equipment temperatures on loss of A/C unit 0
NO1131601 NSO Watchstanding Principles 1
OP1333201 Plant Status Control 0
PI 113 18 01 Overview of Trending Process for Corrective Action 000
Program
QA-OBS-54464 Fatigue Management ----
SA-2012-0021 2012 Mid Cycle Self Assessment 2/17/2012
SCA-91-0408 Safety Classification Analysis 91-0408 Revs 4-6
SEL 2009-150 Corrective Action Program Improvements 8/17/2009
TNA 2011-1002-1 Procedure Changes Gap
TNA 2012-1087-1 Extra COW Training Needed
WCNOC-12-21456 Life Cycle Management Plan for Emergency Diesel April 2012
Generators
-8-
Information Request
February 8, 2012
Biennial Problem Identification and Resolution Inspection
May 7 - May 25, 2012
Wolf Creek Generating Station
Inspection Report 05000482/2012007
This inspection will cover the period from May 26, 2010 to May 25, 2012. All requested
information should be limited to this period or to the date of this request unless otherwise
specified. To the extent possible, the requested information should be provided electronically in
Adobe PDF or Microsoft Office format. Lists of documents should be provided in Microsoft
Excel or a similar sortable format.
A supplemental information request will likely be sent during the week of April 30, 2012.
Please provide the following no later than April 16, 2012:
1. Document Lists
Note: For these summary lists, please include the document/reference number, the
document title or description of the issue, initiation date, current status, and long text
descriptions of the issues.
a. Summary list of all corrective action documents related to significant conditions
adverse to quality that were opened, closed, or evaluated during the period
b. Summary list of all corrective action documents related to conditions adverse to
quality that were opened or closed during the period
c. Summary lists of all corrective action documents which were upgraded or
downgraded in priority/significance during the period
d. Summary list of all corrective action documents that subsume or roll up one or
more smaller issues for the period
e. Summary lists of operator workarounds, engineering review requests and/or
operability evaluations, temporary modifications, and control room and safety
system deficiencies opened, closed, or evaluated during the period
f. Summary list of plant safety issues raised or addressed by the Employee
Concerns Program (or equivalent)
g. Summary list of all Apparent Cause Evaluations completed during the period
h. Summary list of all Root Cause Evaluations planned or in progress but not
complete at the end of the period
2. Full Documents with Attachments
a. Root Cause Evaluations completed during the period
b. Quality assurance audits performed during the period
Attachment 2
c. All audits/surveillances performed during the period of the Corrective Action
Program, of individual corrective actions, and of cause evaluations
d. Corrective action activity reports, functional area self-assessments, and non-
NRC third party assessments completed during the period (do not include INPO
assessments)
e. Corrective action documents generated during the period for the following:
i. All Cited and Non-Cited Violations issued to Wolf Creek Generating
Station
ii. All Licensee Event Reports issued by Wolf Creek Generating Station
f. Corrective action documents generated for the following, if they were determined
to be applicable to Wolf Creek Generating Station (for those that were evaluated
but determined not to be applicable, provide a summary list):
i. NRC Information Notices, Bulletins, and Generic Letters issued or
evaluated during the period
ii. Part 21 reports issued or evaluated during the period
iii. Vendor safety information letters (or equivalent) issued or evaluated
during the period
iv. Other external events and/or Operating Experience evaluated for
applicability during the period
g. Corrective action documents generated for the following:
i. Emergency planning drills and tabletop exercises performed during the
period
ii. Maintenance preventable functional failures which occurred or were
evaluated during the period
iii. Adverse trends in equipment, processes, procedures, or programs which
were evaluated during the period
iv. Action items generated or addressed by plant safety review committees
during the period
3. Logs and Reports
a. Corrective action performance trending/tracking information generated during the
period and broken down by functional organization
b. Corrective action effectiveness review reports generated during the period
c. Current system health reports or similar information
d. Radiation protection event logs during the period
e. Security event logs and security incidents during the period (sensitive information
can be provided by hard copy during first week on site)
f. Employee Concern Program (or equivalent) logs (sensitive information can be
provided by hard copy during first week on site)
g. List of Training deficiencies, requests for training improvements, and simulator
deficiencies for the period
4. Procedures
a. Corrective action program procedures, to include initiation and evaluation
procedures, operability determination procedures, apparent and root cause
evaluation/determination procedures, and any other procedures which implement
the corrective action program at Wolf Creek Generating Station
b. Quality Assurance program procedures
c. Employee Concerns Program (or equivalent) procedures
d. Procedures which implement/maintain a Safety Conscious Work Environment
5. Other
a. List of risk significant components and systems
b. Organization charts for plant staff and long-term/permanent contractors
Note: Corrective action documents refers to condition reports, notifications, action requests,
cause evaluations, and/or other similar documents, as applicable to Wolf Creek Generating
Station.
As it becomes available, but no later than April 16, 2012, this information should be uploaded
onto the Certrec IMS website. When these documents have been compiled (and by April 17,
2012), please download these documents onto a CD or DVD and send 4 copies via overnight
carrier to:
Ron Cohen
U.S. NRC Region IV
1600 East Lamar Blvd.
Arlington, TX 76011-4511
Please note that the NRC is not able to accept electronic documents on thumb drives or other
similar digital media. However, CDs and DVDs are acceptable.