Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005)
ML24240A220
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/29/2024
From: Jon Greives
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2024005
Download: ML24240A220 (1)


Text

August 29, 2024

SUBJECT:

UPDATED INSPECTION PLAN FOR PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 (REPORT 05000277/2024005 AND 05000278/2024005)

Dear David Rhoades:

The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Peach Bottom Atomic Power Station, Units 2 and 3. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 610-337-5337 with any questions you have regarding this letter.

Sincerely, Jonathan E. Grieves, Chief Projects Branch 4 Division of Operating Reactor Safety Docket Nos. 05000277 and 05000278 License Nos. DPR44 and DPR-56 Enclosure:

Peach Bottom Inspection Plan cc w/encl: Distribution via ListServ Jonathan E.

Greives Digitally signed by Jonathan E. Greives Date: 2024.08.29 08:40:50 -04'00'

ML24240A220

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DORS RI/DORS

NAME JSchussler JGrevies

DATE 8/27/24 8/27/24

Site Inspection Activity Plan Peach Bottom 07/01/2024 - 06/30/2026 Unit Start End Activity CAC Title Staff Count Fire Protection - Peach Bottom

2,3 7/22/2024 7/26/2024 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

2,3 8/5/2024 8/9/2024 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Access Control, Equipment Testing and Maintenance, Training, SPR

2,3 9/23/2024 9/27/2024 IP 71130.02 000734 Access Control 2,3 9/23/2024 9/27/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2,3 9/23/2024 9/27/2024 IP 71130.07 000739 Security Training 2,3 9/23/2024 9/27/2024 IP 71130.09 001656 Security Plan Changes 2,3 9/23/2024 9/27/2024 IP 71151 001338 Performance Indicator Verification RP - 71124.01 Rad Haz and 71151 PI Verification

2 10/21/2024 10/25/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/21/2024 10/25/2024 IP 71151 000746 Performance Indicator Verification Inservice Inspection - Peach Bottom Unit 2

2 10/28/2024 11/1/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Material Control and Accounting - Peach Bottom

2,3 2/3/2025 2/7/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)

EP Program Inspection - Peach Bottom

2,3 2/24/2025 2/28/2025 IP 71114.02 000717 Alert and Notification System Testing 2,3 2/24/2025 2/28/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2,3 2/24/2025 2/28/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2,3 2/24/2025 2/28/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness 2,3 2/24/2025 2/28/2025 IP 71151 001397 Performance Indicator Verification PB Requal Inspection with P/F Results

2,3 3/24/2025 3/28/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 2,3 3/24/2025 3/28/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP - 71124.06 RETS

2,3 4/7/2025 4/11/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Commercial Grade Dedication - Peach Bottom

2,3 4/21/2025 4/25/2025 IP 71111.21N.03 001808 Commercial Grade Dedication 2,3 5/5/2025 5/9/2025 IP 71111.21N.03 001808 Commercial Grade Dedication RP - 71124.05 Rad. Instruments

2,3 5/5/2025 5/9/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation Prepared on 7/30/2024 9:34:14 AM 1 of 3 Enclosure

Site Inspection Activity Plan Access Control, Protective Strategy, TSR, SPR, PIs - PB

2,3 5/19/2025 5/23/2025 IP 71130.02 000734 Access Control 2,3 5/19/2025 5/23/2025 IP 71130.05 000737 Protective Strategy Evaluation 2,3 5/19/2025 5/23/2025 IP 71130.09 001656 Security Plan Changes 2,3 5/19/2025 5/23/2025 IP 71130.14 000743 Review of Power Reactor Target Sets 2,3 5/19/2025 5/23/2025 IP 71151 001338 Performance Indicator Verification PI&R Biennial Team Inspection - Peach Bottom

2,3 9/8/2025 9/12/2025 IP 71152B 000747 Problem Identification and Resolution 2,3 9/22/2025 9/26/2025 IP 71152B 000747 Problem Identification and Resolution RP -71124.08 Rad Waste and Part 37

2,3 9/15/2025 9/19/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Inservice Inspection - Peach Bottom Unit 3

3 10/27/2025 10/31/2025 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP - 71124.01 Rad. Hazards

3 10/27/2025 10/31/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Access Control, AA, FFD, Sec Plan Review, PI, ISFSI - PB

2,3 1/5/2026 1/9/2026 IP 71130.01 000733 Access Authorization 2,3 1/5/2026 1/9/2026 IP 71130.02 000734 Access Control 2,3 1/5/2026 1/9/2026 IP 71130.08 000740 Fitness-For-Duty Program 2,3 1/5/2026 1/9/2026 IP 71130.09 001656 Security Plan Changes 2,3 1/5/2026 1/9/2026 IP 71151 001338 Performance Indicator Verification 2,3 1/5/2026 1/9/2026 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations 2,3 2/23/2026 2/27/2026 IP 71130.01 000733 Access Authorization 2,3 2/23/2026 2/27/2026 IP 71130.08 000740 Fitness-For-Duty Program Age Related Degradation - Peach Bottom

2,3 1/26/2026 1/30/2026 IP 71111.21N.04 001832 Age-Related Degradation 2,3 2/9/2026 2/13/2026 IP 71111.21N.04 001832 Age-Related Degradation Cyber Security - Peach Bottom

2,3 3/16/2026 3/20/2026 IP 71130.10 000741 Cybersecurity RP - 71124.03 Resp. Protection and 71124.04 Occupational Dose

2,3 4/20/2026 4/24/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 4/20/2026 4/24/2026 IP 71124.04 000728 Occupational Dose Assessment EP Exercise Inspection - Peach Bottom

2,3 4/27/2026 5/1/2026 IP 71114.01 000716 Exercise Evaluation 2,3 4/27/2026 5/1/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Prepared on 7/30/2024 9:34:14 AM 2 of 3

Site Inspection Activity Plan 2,3 4/27/2026 5/1/2026 IP 71151 001397 Performance Indicator Verification 2026 Peach Bottom Initial Operator Licensing Exam

2,3 4/13/2026 4/17/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

2,3 5/11/2026 5/15/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - PB

2,3 5/11/2026 5/15/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2,3 6/1/2026 6/5/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 7/30/2024 9:34:14 AM 3 of 3