Mid-Cycle Performance Review and Inspection Plan 2011 - Peach Bottom Atomic Power Station
ML112411345
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 09/01/2011
From: Paul Krohn
Reactor Projects Region 1 Branch 4
To: Pacilio M
Exelon Nuclear
KROHN PG
References
IR-11-006
Download: ML112411345 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 September 1, 20II Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.

Warrenville, lL 60555

SUBJECT:

MID-CYCLE LETTER FOR PEACH BOTTOM ATOMIC POWER STATION (05000277 1201 1006 and 0500027 81201 1 006)

Dear Mr. Pacilio:

On August 9, 2011, the NRC completed its mid-cycle performance review of the Peach Bottom Atomic Power Station (PBAPS) Units 2 and 3. The NRC reviewed the most recent quarterly performance indicators (Pls) in addition to inspection results and enforcement actions from July 1 ,2010, through June 30, 2011. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined the performance at Peach Bottom Units 2 and 3 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all Pls indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31,2012.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. In addition to the baseline inspection program, we plan to conduct Inspection Procedure (lP) 71003, "Post-Approval Site Inspection For License Renewal." From July 1, 2010, to June 30, 2011, the NRC issued one severity level lV (SLIV) traditional enforcement non-cited violation associated with a former contract employee failing to provide information about a positive fitness-for-duty test (ML102590516 and ML103140643)1. The NRC followed-up on this non-cited violation during the Biennial Problem ldentification and Resolution Team lnspection completed on August 12, 2011. The results of this inspection will be documented in NRC Inspection Report 05000277 &

I Designation in parenthesis refers to an ADAMS accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS.

M. Pacilio 2 28812011010. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

ln the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRC's processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (Tl) 183, "Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event," and Tl-184, "Availability and Readiness lnspection of Severe Accident Management Guidelines (SAMGS)," at your facility. Results of these inspections can be found here:

http://www.nrc.qovliapan/iapan-activities.html. Additionally, on May 11,2011, the agency issued NRC Butletin 2011-01, "Mitigating Strategies," to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hhx2), and to determine the status of licensee mitigating strategies programs. On July 12,2011, the NRC's Task Force made its recommendations to the Commission in its report, "Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of lnsights from the Fukushima DaiichiAccident." The NRC is currently reviewing the Task Force's recommendations to determine what additional actions may be warranted.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://Www.nrc.qovlreading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5120 with any questions you have regarding this letter.

Sincerely, t'^Jx M Paul G. Krohn, Chief Division of Reactor Projects Projects Branch 4 Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56

Enclosure:

Inspection Plan cc Wencl: Distribution via ListServ

M. Pacilio 288t2011010. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRC's processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (Tl) 183, "Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event," and Tl-184, "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)," at your facility. Results of these inspections can be found here:

http://www.nrc.qov/iapan/iapan-activities.html. Additionally, on May 1 1,2011, the agency issued NRC Bulletin2}ll-01, "Mitigating Strategies," to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hhx2), and to determine the status of licensee mitigating strategies programs. On July 12,2011, the NRC's Task Force made its' recommendations to the Commission in its report, "Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima DaiichiAccident." The NRC is currently reviewing the Task Force's recommendations to determine what additional actions may be warranted.

ln accordance with 10 CFR 2.390 of the NRC's "Rules of Practice, " a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.qov/readinq-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5120 with any questions you have regarding this letter.

Sincerely,

/RA/

Paul G. Krohn, Chief Division of Reactor Projects Projects Branch 4 Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56

Enclosure:

Inspection Plan cc dencl: Distribution via ListServ Distribution: see attached page SUNSI REVTEW COMPLETE: AAR (Reviewer's Initials) ML112411345 DOCUMENT NAME: SIROP.12 MID.CYCLE REVIEMBRANCH 4\PB\PEACH BOTTOM MID'CYCLE ASSESSMENT LETTER.DOCX After declaring this document "An Official Agency Record" it will be released to the Public.

To receive a copy of this document, indicate in box:"C" = Copy w/o attachmenUenclosure, E' = Copy w/ attachment/enclosure,"N"=No copy

)FFICE mmt TYDRP ?I/DRP t/DRP

,IAME iLHansell/AAR for

  • AARosebrooUMR* rGKrohn/PGK

)ATE tgt15t't1 )8115111 )81 18111

  • See Previous Concurrence OFFICIAL RECORD COPY

M. Pacilio Distribution w/encl: (via E-mail)

W, Dean, RA (RIORAMAIL Resource)

D. Lew, DRA (RIORAMAlL Resource)

D. Roberts, DRP (RIDRPMAlL Resource)

J. Clifford, DRP (RIDRPMAIL Resource)

C. Miller, DRS (RlDRSMail Resource)

P. Wilson, DRS (RlDRSMail Resource)

P. Krohn, DRP A. Rosebrook. DRP R. Montgomery, DRP S. lbarrola, DRP S. Hansell, DRP, SRI A. Ziedonis, DRP, Rl S. Schmitt, DRP, OA J. McHale, Rl OEDO DRS Branch Chiefs (6)

N. McNamara, Rl, SLO D. Tifft, RI, SLO D. Screnci, Rl, PAO N. Sheehan, Rl, PAO R. Barkley, Rl, ORA RidsNrrPMPeachBottom Resource Rids N rrDorlLpll -2 Resou rce ROPreports Resource RidsNrrDirslpab Resource ROPassessment Resource

Page 1 of 3 Peach Bottom 08117120'l'l 11:49:11 Inspection / Activity Plan Report 22 07t0112011 - 1213112012 Unit No. of Staff Number on Site EP -EPANNUALREPORT 2,3 0110112011 12t3112011 lP 7'l 11406 Drill Evaluation 711528 - Pl&R 2,3 0712512011 07t2912011 lP 711528 Problem ldentification and Resolution 2.3 08/08/201 1 08t1212011 lP 71152A Problem ldentification and Resolution MC 2561 . SAFSTOR INSPECTION I o8tou2011 0811212011 lP 36801 Organization, Management, And Cost Controls At Permanently Shutdown Reactors 1 08/08/201 1 o811212011 lP 37801 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors 1 08t0812011 08/1212011 lp 40801 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors 1 08/08/201 1 08t1212011 lp 62801 Maintenance And Surveillance At Permanenly Shutdown Reactors 0810812011 08t1212011 lp 71801 Decommissioning Performance And Status Revierw At Permanently Suhutdown Reactors 1 08/08/201 1 08t1212011 lP 83750 Occupational Radiation Exposure I 0810812011 08t12/2011 lp B47SO Radioactive Waste Treatment, And Effluent And Environmental Monitoring 1 08/08/201 1 08t1212011 lp 86750 Solid Radioactive Waste Management And Transportation Of Radioactive Materials HP-71124 . HP.ALARA/AIR/DOSE/INSTRUMENTS/ACCESS z,J 0812212011 08t2612011 lP 71124.01 Radiological Hazard Assessment and Exposure Controls z,t 0812212011 08t2612011 lP 71124.02 Occupational ALARA Planning and Controls 2,3 0812212011 0812612011 lP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2,3 0812212011 08t261201'l lP 71124.04 Occupational Dose Assessment 2,3 0812212011 0812612011 lP 71124.05 Radiation Monitoring Instrumentation HP.71124 . ACCESS/ALARA/AIR/DOSE/INSTRUMENTS z,J ogt19t2011 0912312011 lP 71124.01 Radiological Hazard Assessment and Exposure Controls z,J o911912011 09t23t2011 lP 71124.02 Orcupational ALARA Planning and Controls 2,3 0911912011 09t23t2011 lP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2,3 0911912011 0912312011 lP 71124.04 Orcupational Dose Assessment z,J 0911912011 o9t23t2011 lP 71124.05 Radiation Monitoring lnstrumentation 7111108G - U3INSERVICE INSPECTION 09t1912011 o9t23t2011 lP 71 11108G Inservice Inspection Activities - BWR HP-71124 .ACCESS/ALARA/DOSE/PI 2,3 1111412011 11/18t2011 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 1111412011 1111812011 lP 71124.02 Occupational ALARA Planning and Controls 2,3 11t1412011 11t18t2011 lP 71124.04 Occupational DoseAssessment J 1111412011 11t18t2011 lP 71 151-OR01 Occupational Exposure Control Effectiveness 2 11t14t2A11 11118120'11 lP 71151-PR01 RETS/ODCM Radiological Effluent fhis report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 Peach Bottom 0811712011 11;49:11 Inspection / Activity Plan Report 22 07t01t2011 - 1213112012 Unit No. of Staff Number on Site EP EX . EP EXERCISE EVALUATION 2,3 0312612012 03t3012012 lP 7111401 Exercise Evaluation 2,3 0312612012 03t3012012 lP 7111404 Emergency Action Level and Emergency Plan Changes HP.71124 . ALARA/AIR/DOSE/ACCESS 2,3 04t09t2012 04t1312012 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 04t09t2012 04t1312012 lP 71124.02 Occupational ALARA Planning and Controls 2,3 04t09t2012 o4t13t2012 lP 71124.03 In-Plant Airbome Radioactivity Control and Mitigation 2,3 04t09t2012 04t1312012 lP 71124.04 Occupational Dose Assessment TRI FI . TRIENNIAL FIRE PROTEGTION INSPECTION 2,3 0413012012 0510412012 lp 2S1S117S Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 2.3 ost14t2012 0511812012 lP 7111105T Fire Protection [friennial]

HP-71124 . ACCESS/ALARA'DOSE/INSTRUMENTS z,J 06t0412012 06t0812012 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 06t04t2012 06t0812012 lP 71124.02 Occupational ALAM Planning and Controls 2,3 o6to4t2012 06t08/2012 lP 71124.04 Occr:pational Dose Assessment z,J 06t04t2012 06t0812012 lP 71124.05 Radiation Monitoring Instrumentation HP-71124 - ALARA/AIR/DOSE/INSTRUMENTS/ACCESS 2,3 0710912012 07t1312012 lp 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants z,J 07t09t2012 07t1312012 lP 71124.01 Radiotogical Hazard Assessment and Exposure Controls 2,3 07t09t2012 07t1312012 lP 71124.02 Occupational ALARA Planning and Controls z,J 07t09t2012 0711312012 lP 71124.03 In-Plant Airbome Radioactivity Control and Mitigation 2,3 07t09t2012 07t1312012 lP 71124.04 Occupational Dose Assessment 2,3 07109t2012 0711312012 lP 71124.05 Radiation Monitoring Instrumentation 2561 - SAFSTOR INSPECTION 1 07t30t2012 0811712012 lp 36801 Organization, Management, And Cost Controls At Permanently Shutdown Reactors 1 07t30t2012 o8t't712012 lp 37801 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors 1 0713012012 0811712012 lP 4080i Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors 1 07t30t2012 o8t17t2012 lp 62801 Maintenance And Surveillance At Permanenly Shutdown Reactors 1 07t30t2012 o8t1712012 lp 71801 Decommissioning Performance And Status Revierw At Permanently Suhutdown Reactors I 0713012012 0811712012 lP 83750 Occupational Radiation Exposure 1 07t30t2012 0811712012 lp 84750 Radioactive Waste Treatment, And Effluent And Environmental Monitoring 1 0713012012 08t1712012 lp 86750 Solid Radioactive Waste Management And Transportation Of Radioactive Materials 71003 . LR COMMITMENTS INSP - OUTAGE 09t17t2012 09t21120'12 lP 71003 Post-Approval Site Inspection for License Renewal fhis report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Peach Bottom Ogl17l2011 11:49:11 Inspection / Activity Plan Report 22 07101t2011 - 12t3112012 Unit No. of Staff Number on Site 7111108G . U2INSERVICE INSPECTION 2 09t17t2012 o9t21t2012 lP 71 11108G InseMce lnspection Activities - BWR HP-71124 . ALARA/AIR/DOSE/INSTRUMENTS/ACCESS 2,3 09t24t2012 0912812012 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 09t2412012 0912812012 lP 71124.02 Occupational ALARA Planning and Controls 2,3 09t2412012 09t2812012 lP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2,3 09t24t2012 09t28t2012 lP 71124.04 Occupational Dose Assessment 2,3 0912412012 09t2812012 lP 71124.05 Radiation Monitoring Instrumentation HP.7 1 124 . ALARA/AIR/DOSE/INSTRUMENTS/ACCESS 2,3 1011512012 1011912012 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 10t1512012 1011912012 lP 71124.02 Occupational ALARA Planning and Controls 2,3 10t15t2012 10hs12012 lP 71124.03 In-Plant Airbome Radioactivity Control and Mitigation 2,3 10t15t2012 1011912012 lP 71124.04 Occupational Dose Assessment 2,3 10t15t2012 1011912012 lP 71124.05 Radiation Monitoring Instrumentation HP-71124 . ALARA/AIR/DOSE/INSTRUMENTS/ACCESS 2.3 12t0312012 12t07t2012 lP 71124.01 Radiological Hazard Assessment and Exposure Controls 2,3 't2t03t2012 12t07t2012 lP 71'124.02 Occupational ALARA Planning and Controls 2,3 12tO3t2012 12t0712012 lP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2,3 12t03t2012 12t07t2012 lP 71124-04 Occupational Dose Assessment 2,3 't2t03t2g',t2 12t0712012 lP 71124.05 Radiation Monitoring Instrumentation 2,3 12t03t2012 12t07t2012 lP 71151-PR01 RETS/ODCM Radiolooical Effluent fhis report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.