ML22117A036

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000277/2022001 and 05000278/2022001
ML22117A036
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/27/2022
From: Jon Greives
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Greives J
References
IR 2022001
Download: ML22117A036 (13)


See also: IR 05000277/2022001

Text

April 27, 2022

Mr. David P. Rhoades

Senior Vice President

Constellation Energy Generation, LLC

President and Chief Nuclear Officer (CNO)

Constellation Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 -

INTEGRATED INSPECTION REPORT 05000277/2022001 AND

05000278/2022001

Dear Mr. Rhoades:

On March 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at Peach Bottom Atomic Power Station, Units 2 and 3. On April 22, 2022, the NRC inspectors

discussed the results of this inspection with Mr. David Henry, Site Vice President, and other

members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Digitally signed by Jonathan E.

Jonathan E. Greives

Date: 2022.04.27 10:00:29

Greives -04'00'

Jonathan E. Greives, Chief

Projects Branch 4

Division of Operating Reactor Safety

Docket Nos. 05000277 and 05000278

License Nos. DPR-44 and DPR-56

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML22117A036

x Non-Sensitive x Publicly Available

x SUNSI Review

Sensitive Non-Publicly Available

OFFICE RI/DORS RI/DORS RI/DORS

NAME SRutenkroger LCasey JGreives

DATE 4/27/22 4/26/22 4/27/22

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers: 05000277 and 05000278

License Numbers: DPR-44 and DPR-56

Report Numbers: 05000277/2022001 and 05000278/2022001

Enterprise Identifier: I-2022-001-0050

Licensee: Constellation Energy Generation, LLC

Facility: Peach Bottom Atomic Power Station, Units 2 and 3

Location: Delta, PA 17314

Inspection Dates: January 1, 2022 to March 31, 2022

Inspectors: S. Rutenkroger, Senior Resident Inspector

P. Boguszewski, Resident Inspector

Approved By: Jonathan E. Greives, Chief

Projects Branch 4

Division of Operating Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Peach Bottom Atomic Power Station,

Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight

Process is the NRCs program for overseeing the safe operation of commercial nuclear power

reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

2

PLANT STATUS

Unit 2 began the inspection period at rated thermal power (RTP). On March 8, 2022, operators

reduced power to approximately 35 percent RTP in order to enter the drywell to repair a

nitrogen leak on a main steam isolation valve. Following repairs, the unit was returned to RTP

on March 9, 2022. The unit remained at or near RTP for the remainder of the inspection period.

Unit 3 began the inspection period at rated thermal power (RTP). On March 4, 2022, operators

reduced power to approximately 73 percent RTP for a rod pattern adjustment and returned to

RTP the following day. The unit remained at or near RTP for the remainder of the inspection

period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification

and Resolution, observed risk significant activities, and completed on-site portions of IPs. The

inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel to assess licensee performance and compliance with Commission rules and

regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to the

onset of seasonal cold temperatures for the following systems:

(1) Emergency diesel generators (EDGs), emergency service water (ESW), motor and

diesel driven fire pumps, and the diverse and flexible coping strategies (FLEX)

portable pumps during the week of January 10, 2022

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Unit 2 'A' and 'C' core spray (CS) during 'B' CS logic system functional testing on

January 12, 2022

(2) Unit common, 'E-3' EDG during 'E-1' EDG maintenance on January 31 and

February 1, 2022

3

(3) Unit 2 'B' CS during 'E-1' EDG maintenance on February 2, 2022

(4) Unit common, 'E-3' EDG with degraded alarm cable on March 20, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) Unit common, cable spreading and computer rooms, PF-78H, on February 24, 2022

(2) Unit 2 emergency battery and switchgear rooms, PF-127, on February 24, 2022

(3) Unit 3 emergency battery and switchgear rooms, PF-117, on February 24, 2022

(4) Unit 3 'B' CS, PF-13A, on March 28, 2022

(5) Unit common, hydrogen cylinder storage and radwaste enclosure, PF-150, on

March 20, 2022

(6) Unit 2 high-pressure coolant injection pump (HPCI) room, PF-59, on March 29, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit common, administration building pipe tunnel leak on February 18, 2022

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit common, 'E-1' EDG lube oil cooler and air coolant cooler two-year cleaning and

inspection and eddy current testing on January 31 and February 1, 2022

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the main

control room during quarterly Unit 3 control rod testing on February 20, 2022

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training in

the simulator on February 7, 2022

4

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1) Unit 2 standby liquid control system on February 18, 2022

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to

ensure the following SSC remains capable of performing its intended function:

(1) Unit common, 'E-3' EDG cable replacements from March 20, 2022, through

March 25, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1) Unit 2 'C' residual heat removal planned maintenance on January 3, 2022

(2) Unit common, EDG planned cardox system testing on January 5, 2022

(3) Unit common, 'E-1' EDG planned maintenance on January 31, 2022

(4) Unit common, 'E-3' EDG ventilation logic test on February 9, 2022

(5) Unit common, 'E-3' EDG tagged out of service for anticipated maintenance on

March 7, 2022

(6) Unit common, 'E-3' EDG unavailability on March 7, 2022

(7) Unit common, 'E-3' EDG and 'B' ESW pump unavailable for cable replacements on

March 14, 2022

(8) Unit common, 'E-3' EDG and 'B' ESW risk informed completion time implementation

on March 18, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) Unit common, 'E-1' EDG air coolant pump backlash readings out of tolerance on

January 31, 2022

(2) Unit common, 'E-1' EDG stator air gap measurements exceeded allowable tolerance

on February 1, 2022

(3) Unit common, 'E-3' EDG low tube oil temperature on February 1, 2022

5

(4) Unit common, 'E-3' EDG trip on high crankcase pressure during slow start

surveillance testing on February 15, 2022

(5) Unit common, 'E-4' EDG ventilation damper fresh air configuration on

February 25, 2022

(6) Unit common, 'E-3' EDG conduit and cable conditions, including water intrusion and

over-tensioning on March 15 through March 19, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit common, 'E-3' EDG cable replacement from March 20, 2022, through

March 25, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system

operability and/or functionality:

(1) Unit common, 'E-1' EDG replacement of contacts supporting jacket coolant and lube

oil heaters on February 1, 2022

(2) Unit common, 'E-1' EDG following planned maintenance on February 4 and

February 5, 2022

(3) Unit 2 local leak rate testing of personnel hatch following containment entry on

March 9, 2022

(4) Unit common, 'E-3' EDG control cable replacements following completion of cable

pulls and cable terminations on March 19, 2022

(5) Unit common, 'E-3' EDG penetration seal replacements on March 14 through

March 20, 2022

(6) Unit common, 'E-3' EDG maintenance window final testing following control cable

replacements and crankcase vacuum orifice replacement on March 21, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability

and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (1 Sample)

(1) Unit common, 'E-3' EDG run on February 15, 2022

Inservice Testing (IP Section 03.01) (2 Samples)

(1) Unit 3 HPCI and unit cooler functional in-service test on March 1, 2022

(2) Unit common, E-4 EDG slow start full load and in-service test on February 25, 2022

6

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Unit 3 monitored for increased drywell unidentified leakage as of January 31, 2022

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1) The inspectors observed a full scope emergency preparedness drill conducted on

February 14, 2022

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01) (2 Samples)

(1) Unit 2 for the period January 1, 2021, to December 31, 2021

(2) Unit 3 for the period January 1, 2021, to December 31, 2021

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02)

(2 Samples)

(1) Unit 2 for the period January 1, 2021, to December 31, 2021

(2) Unit 3 for the period January 1, 2021, to December 31, 2021

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 2 for the period January 1, 2021, to December 31, 2021

(2) Unit 3 for the period January 1, 2021, to December 31, 2021

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 22, 2022, the inspectors presented the integrated inspection results to

Mr. David Henry, Site Vice President, and other members of the licensee staff.

7

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Corrective Action 4471280

Documents 4401855

Procedures AO 29.2 Discharge Canal to Intake Pond Cross-Tie Gate Operation, Revision 34

Frazil Ice Mitigation, and Icing Condition Operations

CC-PB-118 Peach Bottom Implementation of Diverse and Flexible Revision 14

Coping Strategies (FLEX) and Spent Fuel Pool

Instrumentation Program

FSG-003 Pre-Staging FLEX Equipment Revision 2

71111.04 Corrective Action 4442542

Documents 4445073

4464924

4468814

71111.05 Miscellaneous Barrier Breach

Permit No. 22-

029

Barrier Breach

Permit No. 22-

053

FSI #00015076

FSI #00015285

Procedures PF-117 Unit 3 Turbine Building, Emergency Battery Switchgear Revision 11

Rooms, Elevation 135'-0"

PF-127 Unit 2 Turbine Building, Emergency Battery Switchgear Revision 11

Rooms, Elevation 135'-0"

PF-150 Hydrogen Cylinder Storage & Radwaste Enclosure Revision 7

PF-78H Turbine Building Common, Cable Spreading and Computer Revision 9

Rooms, Elevation 150'-0"

71111.07A Miscellaneous 0AE377 Lube Oil Cooler Final Report 02/2022

0AE378 Air Coolant Cooler Final Report 02/2022

71111.12 Corrective Action AR 4485805

Documents

Corrective Action AR 4486635

8

Inspection Type Designation Description or Title Revision or

Procedure Date

Documents 4486620

Resulting from

Inspection

Miscellaneous Engineering

Change Request

635851

71111.13 Corrective Action 4486302

Documents AR 04477072

Corrective Action 4475037

Documents 4475047

Resulting from

Inspection

Miscellaneous RICT Record, 'E-3' EDG and 'B' ESW RICT for 'E-3' EDG Cable

WW-2211 Replacement

Procedures ER-AA-600-1052 Risk Management Support of RICT Revision 001

OP-AA-108-118 Risk Informed Completion Time Revision 2

WC-AA-101 On-Line Work Control Process Revision 32

WC-AA-101-1006 On-Line Risk Management and Assessment Revision 4

71111.15 Corrective Action IR 4474937

Documents IR 4475171

IR 4475245

IR 4478230

IR 4480707

IR 4484847

4486620

4486635

Miscellaneous Technical

Evaluation

636000

Procedures M-052-001 Diesel Generator Maintenance Revision 11

SO52A.8.A Diesel Generator Daily Shutdown Inspection Revision 66

Work Orders 05067200

71111.19 Corrective Action 4475362

Documents IR 4486620

9

Inspection Type Designation Description or Title Revision or

Procedure Date

IRs

4475899

4476115

4476116

4475914

4476053

Operability RT-O-052-251-2 E-1 Diesel Generator Inspection Post-Maintenance Revision

Evaluations Functional Test 38A

Procedures M-056-001 480 Volt Motor Control Center Circuit Breaker Assembly and Revision 36

Cubicle Terminal Maintenance

ST-I-052-251-2 E-1 Diesel Generator Inspection Post-Maintenance Revision 9

Instrumentation and Logic Test

ST-O-052-411-2 E-1 Diesel Generator Fast Start and Full Load Revision 24

Work Orders 05227164

05228431

05228481

05228708

4688253

5019993

5019994

5057721

5176138

71111.22 Corrective Action 04478230

Documents IR 4481499

Procedures ST-O-023-300-3 HPCI Pump, Valve, and Flow and Unit Cooler Functional and Revision 21

In-Service Test Without Vibration Data Collection

ST-O-052-314-2 'E-4' Diesel Generator Slow Start Full Load and IST Test Revision 23

Work Orders 05205860

05228030

WR 01511354

WO 04250947

71114.06 Corrective Action IRs 4478221

Documents 4478227

10

Inspection Type Designation Description or Title Revision or

Procedure Date

4479208

Corrective Action IR 4479134

Documents

Resulting from

Inspection

11