Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station
ML052420701
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/30/2005
From: Brian Holian
Division Reactor Projects I
To: Crane C
Exelon Generation Co, Exelon Nuclear
Shanbaky M RGN-I/DRP/PB4/610-337-5209
References
Download: ML052420701 (6)


Text

August 30, 2005 Mr. Christopher M. Crane President and CNO Exelon Nuclear Exelon Generation Company, LLC 200 Exelon Way KSA 3-E Kennett Square, PA 19348

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

PEACH BOTTOM ATOMIC POWER STATION

Dear Mr. Crane:

On August 4, 2005, the NRC staff completed its performance review of Peach Bottom Atomic Power Station Units 2 and 3 for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Plant performance at Peach Bottom Unit 2 for the most recent quarter was within the Regulatory Response column of the NRCs Action Matrix based on one White PI in the Initiating Events cornerstone. Peach Bottom Unit 2 had three scrams with a Loss of Normal Heat Removal within twelve calendar quarters causing this PI to change from Green to White. Inspection findings at Unit 2 were all classified as having very low safety significance (Green). We will perform reactor oversight process (ROP) baseline inspections and one supplemental inspection at Peach Bottom Unit 2 for the instance of a White PI as scheduled in the enclosed inspection plan.

Plant performance at Peach Bottom Unit 3 for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct ROP baseline inspections at Peach Bottom Unit 3.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised

2 Mr. Christopher M. Crane during the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Dr. Mohamed Shanbaky at 610-337-5209 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Brian E. Holian, Director Division of Reactor Projects Docket Nos.:

50-277, 50-278 License Nos.: DPR-44, DPR-56

Enclosure:

Peach Bottom Inspection/Activity Plan cc w/encl Chief Operating Officer, Exelon Generation Company, LLC Site Vice President, Peach Bottom Atomic Power Station Plant Manager, Peach Bottom Atomic Power Station Regulatory Assurance Manager - Peach Bottom Associate General Counsel, Exelon Generation Company J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear Manager, Financial Control & Co-Owner Affairs Director, Nuclear Training Correspondence Control Desk Director, Bureau of Radiation Protection (PA)

R. McLean, Power Plant and Environmental Review Division (MD)

R. Fletcher, Maryland Department of Environment T. Snyder, Director, Air and Radiation Management Administration, Maryland Department of the Environment (SLO, MD)

Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. Ruth, Council Administrator of Harford County Council Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance TMI - Alert (TMIA)

J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams

3 Mr. Christopher M. Crane Distribution w/encl:

(via E-mail)

S. Collins, RA M. Dapas, DRA M. Shanbaky, DRP A. Burritt, DRP F. Bower, DRP - NRC Senior Resident Inspector D. Schroeder, DRP - NRC Resident Inspector S. Schmitt, DRP - NRC Resident OA D. Screnci, PAO N. Sheehan, PAO DRS Director DRS Deputy Director DRS Branch Chiefs RidsNrrDipmlipb@nrc.gov Institute of Nuclear Power Operations (INPO)

S. Lee, RI OEDO J. Clifford, NRR G. Wunder, PM, NRR T. Tate, PM, NRR (Backup)

Region I Docket Room (with concurrences)

ROPreports@nrc.gov (All IRs)

DOCUMENT NAME: S:\\ROP-6 Mid-Cycle Review\\2005 Mid-Cycle Letters\\PB ROP 6 MC letterR1.wpd SISP Review Complete: MMS (Reviewers Initials)

After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP

/

NAME FBower MShanbaky DATE 08/24/05 08/30/05 OFFICIAL RECORD COPY

Peach Bottom Inspection / Activity Plan 08/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 3 08/30/2005 14:26:00 Report 22 1

71121

- OCC RAD SAFETY Baseline Inspections 08/15/2005 08/19/2005 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 08/15/2005 08/19/2005 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 08/15/2005 08/19/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 1

36801

- ORGANIZATION, MANAGMENT, COST CONTROLS Other Routine 07/06/2005 08/06/2005 Organization, Management, And Cost Controls At Permanently Shutdown Reactors IP 36801 1

1 37801

- SAFETY REVIEWS, DESIGN CHANGES, AND MODS Other Routine 07/06/2005 08/06/2005 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors IP 37801 1

1 40801

- SELF ASSESSMENT,AUDIT, CORRECTIVE ACTION Other Routine 07/06/2005 08/06/2005 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors IP 40801 1

1 64704

- FIRE PROTECTION Other Routine 07/06/2005 08/06/2005 Organization, Management, And Cost Controls At Permanently Shutdown Reactors IP 36801 1

1 81700

- PHYSICAL SECURITY ASSESSMENT Other Routine 07/06/2005 08/06/2005 Physical Security Program For Power Reactors IP 81700 1

1 83750

- OCCUPATIONAL RADIATION EXPOSURE Other Routine 07/06/2005 08/06/2005 Occupational Radiation Exposure IP 83750 1

1 84750

- RADWSTE TREAT, EFFLUENT, ENVIRONMENTAL Other Routine 07/06/2005 08/06/2005 Radioactive Waste Treatment, And Effluent And Environmental Monitoring IP 84750 1

1 86750

- SOLID RADWST MANAGMENT Other Routine 07/06/2005 08/06/2005 Solid Radioactive Waste Management And Transportation Of Radioactive Materials IP 86750 1

1 71121

- OCC RAD SAFETY Baseline Inspections 08/08/2005 08/12/2005 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 08/08/2005 08/12/2005 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 08/08/2005 08/12/2005 Radioactive Material Processing and Transportation IP 7112202 2, 3 2

7111111B

- LSRO INSPECTION-PASS/FAIL RESULTS Baseline Inspections 11/15/2005 11/19/2005 Licensed Operator Requalification Program IP 7111111B 2, 3 1

7111108G

- INSERVICE INSPECTION - U3 Baseline Inspections 09/26/2005 09/30/2005 Inservice Inspection Activities - BWR IP 7111108G 3

1 71121

- OCC RAD SAFETY Baseline Inspections 09/26/2005 09/30/2005 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 09/26/2005 09/30/2005 ALARA Planning and Controls IP 7112102 2, 3 1

95001

- U2 SCRAM WITH LOSS OF HEAT SINK WHITE PI Supplemental Program 11/07/2005 11/11/2005 Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area IP 95001 2

1 71121

- OCC RAD SAFETY Baseline Inspections 11/14/2005 11/18/2005 Access Control to Radiologically Significant Areas IP 7112101 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Peach Bottom Inspection / Activity Plan 08/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 3 08/30/2005 14:26:00 Report 22 1

71121

- OCC RAD SAFETY Baseline Inspections 11/14/2005 11/18/2005 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 11/14/2005 11/18/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 Baseline Inspections 11/14/2005 11/18/2005 Performance Indicator Verification IP 71151 2, 3 3

TRI FIRE

- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 01/23/2006 01/28/2006 Fire Protection [Triennial]

IP 7111105T 2, 3 Baseline Inspections 02/06/2006 02/10/2006 Fire Protection [Triennial]

IP 7111105T 2, 3 5

7111121

- SSD&PC Baseline Inspections 03/13/2006 03/17/2006 Safety System Design and Performance Capability IP 7111121 2, 3 Baseline Inspections 03/27/2006 03/31/2006 Safety System Design and Performance Capability IP 7111121 2, 3 Baseline Inspections 04/10/2006 04/14/2006 Safety System Design and Performance Capability IP 7111121 2, 3 Baseline Inspections 04/17/2006 04/21/2006 Safety System Design and Performance Capability IP 7111121 2, 3 1

71121

- OCCUPATIONAL RAD PROT Baseline Inspections 04/17/2006 04/21/2006 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 04/17/2006 04/21/2006 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 04/17/2006 04/21/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 5

7111401

- EXERCISE EVALUATION & EP PI VERIFICATION Baseline Inspections 04/24/2006 04/28/2006 Exercise Evaluation IP 7111401 2, 3 Baseline Inspections 04/24/2006 04/28/2006 Performance Indicator Verification IP 71151 2, 3 1

71122

- PUBLIC RAD PROT Baseline Inspections 06/12/2006 06/16/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 2, 3 1

7111112B

- MAINTENANCE RULE Baseline Inspections 07/17/2006 07/21/2006 Maintenance Effectiveness IP 7111112B 2, 3 2

7111107B

- HEAT SINK Baseline Inspections 07/24/2006 07/28/2006 Heat Sink Performance IP 7111107B 2, 3 1

71121

- OCC RAD SAF Baseline Inspections 08/07/2006 08/11/2006 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 08/07/2006 08/11/2006 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 08/07/2006 08/11/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 1

7111108G

- INSERVICE INSPECTION - UNIT 2 Baseline Inspections 09/18/2006 09/22/2006 Inservice Inspection Activities - BWR IP 7111108G 2

1 71121

- OCC RAD PROT Baseline Inspections 09/25/2006 09/29/2006 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 09/25/2006 09/29/2006 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 09/25/2006 09/29/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Peach Bottom Inspection / Activity Plan 08/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 3 of 3 08/30/2005 14:26:00 Report 22 1

71121

- OCC RAD PROT Baseline Inspections 10/30/2006 11/03/2006 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 10/30/2006 11/03/2006 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 10/30/2006 11/03/2006 Performance Indicator Verification IP 71151 2, 3 3

2/5EXAM

- OPERATOR LICENSING INITIAL EXAMS Not Applicable 01/08/2007 01/12/2007 PEACH BOTTOM, UNIT 2&3 INITIAL EXAM (2/07)

U01612 2

Not Applicable 02/05/2007 02/09/2007 PEACH BOTTOM, UNIT 2&3 INITIAL EXAM (2/07)

U01612 2

3 7111111B

- LO REQUAL PROGRAM INSPECTION Baseline Inspections 03/19/2007 03/30/2007 Licensed Operator Requalification Program IP 7111111B 2, 3 1

71121

- OCC RAD SAFETY Baseline Inspections 02/12/2007 02/16/2007 Access Control to Radiologically Significant Areas IP 7112101 2, 3 Baseline Inspections 02/12/2007 02/16/2007 ALARA Planning and Controls IP 7112102 2, 3 Baseline Inspections 02/12/2007 02/16/2007 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 3

71111117

- MODS AND 50.59 Baseline Inspections 03/05/2007 03/09/2007 Evaluation of Changes, Tests, or Experiments IP 7111102 2, 3 Baseline Inspections 03/05/2007 03/09/2007 Permanent Plant Modifications IP 7111117B 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.