MONTHYEARIR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) ML23019A0752023-01-19019 January 2023 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000277/2023011 and 05000278/2023011 IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000277/20210052021-09-0101 September 2021 Updated Inspection Plan for the Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2021005 and 05000278/2021005) IR 05000277/20200062021-03-0303 March 2021 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2020006 and 05000278/2020006) ML21091A1782021-02-0202 February 2021 Ti 2515/194 Inspection Documentation Request ML20296A3342020-10-21021 October 2020 ISI Remote Inspection - Supplemental Request for Information IR 05000277/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Reports 05000277/2020005 and 05000278/2020005) ML20119A8852020-04-28028 April 2020 Stations, Unit 3, Long-Term Steam Dryer Inspection Plan at EPU Conditions IR 05000277/20190062020-03-0303 March 2020 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2019006 and 05000278/2019006) IR 05000277/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000277/2019005 and 05000278/2019005) ML19119A1202019-04-29029 April 2019 Long-Term Steam Dryer Inspection Plan at EPU Conditions IR 05000277/20180062019-03-0404 March 2019 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2018006 and 05000278/2018006) ML18330A0532018-11-21021 November 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000277/2019403 and 05000278/2019403 IR 05000277/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000277/2018005 and 05000278/2018005) IR 05000277/20170062018-02-28028 February 2018 Annual Assessment Letter for Peach Bottom Atomic Power Station Units 2 and 3 -(Report 05000277-2017006 and 05000278-2017006 Report 05000277-2017402 and 05000278-2017402 Report 05000277-2017501 and 05000278-2017501) ML17340A4112017-12-0505 December 2017 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000277/20170052017-08-28028 August 2017 Updated Inspection Plan Letter 05000277/2017005 and 05000278/2017005 with Rpt. 22 IR 05000277/20160062017-03-0101 March 2017 Annual Assessment Letter Units 2 and 3 - Report Nos. 05000277/2016006 and 05000278/2016006 with Report 22 IR 05000277/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 & 3 (Report 05000277/2015006 & 05000278/2015006) IR 05000277/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2015005 and 05000278/2015005) IR 05000277/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Peach Bottom Atomic Power Station (Report 05000277/2014001 and 05000278/2014001) IR 05000277/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000277/2014006 and 05000278/2014006 IR 05000277/20130012014-03-0404 March 2014 ROP-14 2013 Peach Bottom Atomic Power Station Annual Assessment Letter, Report 05000277/2013001 and 05000278/2013001, and Inspection Plan IR 05000277/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000277/2013006 and 05000278/2013006 IR 05000277/20120012013-03-0404 March 2013 Annual Assessment Letter for Peach Bottom Atomic Power Station Units 2 and 3 (Report 05000277/2012001 and 05000278/2012001) ML12318A0022012-11-0909 November 2012 Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1 - 7 and Request for Information IR 05000277/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Peach Bottom Atomic Power Station (Report 05000277/2012006 and 05000278/2012006) IR 05000277/20110012012-03-0505 March 2012 Annual Assessment Letter for Peach Bottom Atomic Power Station (Report 05000277-11-001 and 05000278-11-001) ML1124113452011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Peach Bottom Atomic Power Station IR 05000277/20100012011-03-0404 March 2011 Annual Assessment Letter for Peach Bottom Atomic Power Station, EOC-11 (05000277/2010001 and 05000278/2010001) ML1024404132010-09-0101 September 2010 Mid-Cycle Assessment Letter 2010 - Peach Bottom Atomic Power Station, Units 2 and 3 ML1006210092010-03-0303 March 2010 Annual Assessment Letter - Peach Bottom Atomic Power Station (05000277-10-001 and 05000278-10-001) and Report 22 ML0924402532009-09-0101 September 2009 Mid-Cycle Performance Assessment Letter - Peach Bottom Atomic Power Station IR 05000277/20090012009-03-0404 March 2009 Annual Assessment Letter - Peach Bottom Atomic Power Station (05000277/2009001 and 05000278/2009001) ML0824704542008-09-0202 September 2008 2008 Mid-Cycle Performance Assessment Letter - Peach Bottom ML0734705752007-12-13013 December 2007 ROP - Peach Bottom - Change to Inspection Plan, 12/13/07 ML0724306242007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan, for 07/01/2007 - 12/31/2008 ML0706106152007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Peach Bottom Station (05-277-07-001 and 05-278-07-001) ML0624305232006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station IR 05000277/20060012006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Peach Bottom Atomic Power Station (Report 05000277/2006001 and 05000278/2006001) ML0524207012005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station ML0506107082005-03-0202 March 2005 Annual Assessment Letter 2005001-Peach Bottom ML0424404642004-08-30030 August 2004 2004 Peach Bottom Mid-Cycle Performance Review and Inspection Plan ML0406305452004-03-0303 March 2004 2003-04 Annual Assessment Letter - Peach Bottom IR 05000277/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Peach Bottom Atomic Power Station (Report 50-277/03-001, 50-278/03-001) IR 05000277/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Peach Bottom Atomic Power Station (Report 50-277/02-01, 50-278/02-01 2023-08-31
[Table view] Category:Letter
MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 ML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ML23150A2052023-05-30030 May 2023 Independent Spent Fuel Storage Installation (Isfsi), Annual Radiological Environmental Operating Report 80 January 1, 2022 Through December 31, 2022 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A1582023-05-18018 May 2023 Correction to Technical Specification 3.4.7 (Page 3.4-16) Issued in Amendment No. 337 ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI 2024-01-05
[Table view] |
Text
March 2, 2005 Mr. Christopher M. Crane President and CNO Exelon Nuclear Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
Annual Assessment Letter - Peach Bottom Atomic Power Station (Report 05000277/2005001 and 05000278/2005001)
Dear Mr. Crane:
On February 7, 2005, the NRC staff completed its end-of-cycle plant performance assessment of Peach Bottom Atomic Power Station (Peach Bottom). The end-of-cycle review for Peach Bottom involved the participation of the reactor technical divisions in evaluating performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2004. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Overall, Peach Bottom operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, currently we plan to conduct only baseline inspections at your facility through September 30, 2006. However, one PI for Peach Bottom Unit 2 (number of scrams with a loss of normal heat removal) is still being evaluated by the NRC staff and a separate assessment followup letter may be issued, if appropriate, following completion of the staffs review.
While plant performance for the most recent quarter is within the licensee response column of the Action Matrix, there was a safety significant inspection finding and a performance indicator during the first three quarters of the assessment cycle. In our letter dated February 3, 2004, we forwarded the final significance determination for an inspection finding of low-to-moderate safety significance (White) in the Mitigating System Cornerstone for an inoperable emergency diesel generator (EDG). In the first quarter of 2004 there was a White PI in the Initiating Events Cornerstone for Unit 2 exceeding the number of Unplanned Scrams per 7,000 Critical Hours.
We performed the supplemental inspections for the White inspection finding and the PI during this assessment period and these issues are closed.
In our mid-cycle letter dated August 30, 2004, we advised you that a substantive cross-cutting
Mr. Christopher M. Crane 2 issue still existed in the area of Problem Identification and Resolution involving inadequate corrective action for known equipment problems. The NRC staff has determined that a substantive cross-cutting issue no longer exists due to the reduction in frequency of findings related to this area.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2006. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Dr. Mohamed Shanbaky, Chief, Projects Branch 4 at (610 337-5209) with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
A. Randolph Blough, Director Division of Reactor Projects Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56
Enclosure:
Peach Bottom Inspection/Activity Plan cc w/encl:
Chief Operating Officer, Exelon Generation Company, LLC Site Vice President, Peach Bottom Atomic Power Station Plant Manager, Peach Bottom Atomic Power Station Regulatory Assurance Manager - Peach Bottom Senior Vice President, Nuclear Services Vice President, Mid-Atlantic Operations Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director, Licensing and Regulatory Affairs, Exelon Generation Company, LLC Manager, Licensing - Peach Bottom Atomic Power Station Manager License Renewal
Mr. Christopher M. Crane 3 Vice President, General Counsel and Secretary Associate General Counsel, Exelon Generation Company J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear D. Quinlan, Manager, Financial Control, PSEG R. McLean, Power Plant and Environmental Review Division Director, Nuclear Training Correspondence Control Desk D. Allard, Director, Pennsylvania Bureau of Radiation Protection R. Fletcher, Department of Environment, Radiological Health Program Commonwealth of Pennsylvania (c/o R. Janati, Chief, Division of Nuclear Safety, Pennsylvania Bureau of Radiation Protection)
Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. Ruth, Council Administrator of Harford County Council Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance TMI - Alert (TMIA)
J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams T. Snyder, Director, Air and Radiation Management Administration, Maryland Department of the Environment (SLO)
Mr. Christopher M. Crane 4 Distribution w/encl:
S. Collins, RA J. Wiggins, DRA M. Shanbaky, DRP A. Burritt, DRP F. Bower, DRP - NRC Senior Resident Inspector D. Schroeder, DRP - NRC Resident Inspector S. Schmitt, DRP - NRC Resident OA S. Lee, RI OEDO J. Clifford, NRR G. Wunder, PM, NRR T. Tate, PM, NRR (Backup)
Region I Docket Room (with concurrences)
ROPreports@nrc.gov (All IRs)
DRP/DRS Division Directors DRP/DRS Deputy Directors DRS Branch Chiefs RidsNrrDipmIipb@nrc.gov Institute of Nuclear Power Operations (INPO)
DOCUMENT NAME: S:\ROP5 End of Cycle Review\Branch 4\Peach Bottom ROP5 Annual Assessment Letter Rev1.wpd SISP Review Complete: mms (Reviewers Initials)
After declaring this document An Official Agency Record it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI:DRP RI:DRP RI:DRP NAME Burritt Shanbaky Blough DATE 02/24/05 02/24/05 03/01/05 OFFICIAL RECORD COPY
Page 1 of 2 Peach Bottom 03/01/2005 14:49:46 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7111111B - LO REQUAL PROG. & PASS/FAIL RESULTS 3 2, 3 IP 7111111B Licensed Operator Requalification Program 03/14/2005 03/17/2005 Baseline Inspections 2, 3 IP 7111111B Licensed Operator Requalification Program 03/21/2005 03/25/2005 Baseline Inspections MODS - MODS & 50.59 4 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 03/14/2005 03/18/2005 Baseline Inspections 2, 3 IP 7111117B Permanent Plant Modifications 03/14/2005 03/18/2005 Baseline Inspections 6/13 EXM - PB/LM (LSRO) O.L. INITIAL EXAM 2 2 U01574 LIMERICK/PEACH BOTTOM LSRO EXAM (6/5-10/05) 05/16/2005 05/20/2005 Not Applicable 2 U01574 LIMERICK/PEACH BOTTOM LSRO EXAM (6/5-10/05) 06/13/2005 06/24/2005 Not Applicable 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 04/25/2005 04/29/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 04/25/2005 04/29/2005 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 04/25/2005 04/29/2005 Baseline Inspections 71152B - PI&R 4 2, 3 IP 71152B Identification and Resolution of Problems 07/11/2005 07/15/2005 Baseline Inspections 2, 3 IP 71152B Identification and Resolution of Problems 07/25/2005 07/29/2005 Baseline Inspections 7112203 - PUB RAD SAFETY - REMP 1 2, 3 IP 7112203 Radiological Environmental Monitoring Program 07/25/2005 07/29/2005 Baseline Inspections 71114 - EP PROGRAM INSP & PI VERIFICATION 1 2, 3 IP 7111402 Alert and Notification System Testing 07/25/2005 07/29/2005 Baseline Inspections 2, 3 IP 7111403 Emergency Response Organization Augmentation Testing 07/25/2005 07/29/2005 Baseline Inspections 2, 3 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/25/2005 07/29/2005 Baseline Inspections 2, 3 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 07/25/2005 07/29/2005 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 07/25/2005 07/29/2005 Baseline Inspections 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 08/08/2005 08/12/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 08/08/2005 08/12/2005 Baseline Inspections 2, 3 IP 7112202 Radioactive Material Processing and Transportation 08/08/2005 08/12/2005 Baseline Inspections 7111108G - INSERVICE INSPECTION - U3 1 3 IP 7111108G Inservice Inspection Activities - BWR 09/26/2005 09/30/2005 Baseline Inspections 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 09/26/2005 09/30/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 09/26/2005 09/30/2005 Baseline Inspections 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 11/14/2005 11/18/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Peach Bottom 03/01/2005 14:49:46 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 2, 3 IP 7112102 ALARA Planning and Controls 11/14/2005 11/18/2005 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/14/2005 11/18/2005 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 11/14/2005 11/18/2005 Baseline Inspections 7111111B - LSRO INSPECTION 1 2, 3 IP 7111111B Licensed Operator Requalification Program 11/15/2005 11/19/2005 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 2, 3 IP 7111105T Fire Protection 03/13/2006 03/18/2006 Baseline Inspections 2, 3 IP 7111105T Fire Protection 03/27/2006 03/31/2006 Baseline Inspections 7111401 - EXERCISE EVALUATION & EP PI VERIFICATION 2 2, 3 IP 7111401 Exercise Evaluation 04/24/2006 04/28/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 04/24/2006 04/28/2006 Baseline Inspections SSDI - SSDI 7 2, 3 IP 7111121 Safety System Design and Performance Capability 06/05/2006 06/09/2006 Baseline Inspections 2, 3 IP 7111121 Safety System Design and Performance Capability 06/19/2006 06/23/2006 Baseline Inspections 7111112B - MAINTENANCE RULE 1 2, 3 IP 7111112B Maintenance Effectiveness 07/17/2006 07/21/2006 Baseline Inspections 7111107B - HEAT SINK 2 2, 3 IP 7111107B Heat Sink Performance 07/24/2006 07/28/2006 Baseline Inspections 7111108G - INSERVICE INSPECTION - UNIT 2 1 2 IP 7111108G Inservice Inspection Activities - BWR 09/18/2006 09/22/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.