IR 05000277/2022011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000277/2022011 and 05000278/2022011
ML22138A376
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/18/2022
From: Mel Gray
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Gray M
References
IR 2022-011
Download: ML22138A376 (11)


Text

May 18, 2022

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000277/2022011 AND 05000278/2022011

Dear Mr. Rhoades:

On April 8, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station, Units 2 and 3 and discussed the results of this inspection with Mr. David Henry, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000277 and 05000278 License Nos. DPR-44 and DPR-56

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000277 and 05000278

License Numbers:

DPR-44 and DPR-56

Report Numbers:

05000277/2022011 and 05000278/2022011

Enterprise Identifier: I-2022-011-0021

Licensee:

Constellation Energy Generation, LLC

Facility:

Peach Bottom Atomic Power Station, Units 2 and 3

Location:

Delta, PA

Inspection Dates:

March 21, 2022 to April 8, 2022

Inspectors:

E. Dipaolo, Senior Reactor Inspector

D. Kern, Senior Reactor Inspector

N. Mentzer, Reactor Inspector

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Peach Bottom Atomic Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a. Determined whether the sampled power-operated valves (POVs) are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b. Determined whether the sampled POVs are capable of performing their design-basis functions.

c. Determined whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d. Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1) MO-0-33-0498, Emergency Service Water (ESW) Return to Discharge Pond
(2) MO-3-02-053B, Recirculation Pump Discharge Isolation Valve
(3) MO-3-10-013A, Residual Heat Removal Pump 3AP035 Torus Suction Isolation Valve
(4) MO-3-10-025A, Residual Heat Removal Loop A, Inboard Discharge Valve
(5) MO-3-13-021, Reactor Core Isolation Cooling Pump Discharge to B Feedwater Line
(6) MO-3-14-005D, D Core Spray Pump Minimum Flow Valve
(7) MO-3-23-014, High Pressure Coolant Injection Turbine Steam Supply Valve
(8) AO-0-33-0241B, ESW Outlet Block Valve from E2 Diesel Generator Coolers
(9) AO-2-01A-080D, Inboard D Main Steam Isolation Valve
(10) AO-2-03-35B, Scram Discharge Volume Outboard Isolation Vent Valve
(11) AO-2-07B-2511, Torus 18 Vent Inboard Isolation Valve to SBGT/ATMOS
(12) AO-3-01A-080A, Inboard A Main Steam Isolation Valve

INSPECTION RESULTS

Very Low Safety Significance Issue Resolution Process: Emergency Heat Sink (including ESW-0498, ESW Return to Pond) Safety Classification and Inservice Test (IST) Requirements 71111.21 N.02 This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

The Peach Bottom 5th 10-Year Test Interval Inservice Test (IST) Program Plan, Revision 16 identified that valve MO-0-33-0498, ESW Return to Pond, had a passive safety function to remain open. This open safety function supported cooling for the emergency diesel generators and the emergency core cooling system rooms during normal plant operation. The Plan specified that the associated IST requirement was a biennial position indication verification (PI) test.

The inspectors determined MO-0-33-0498 also had an active safety function to close, which was not documented in the 10-Year IST Program Plan. The Peach Bottom Updated Final Safety Analysis Report (UFSAR) credited this active function to provide closed-loop emergency heat sink (EHS) operation to support safe shutdown of Units 2 and 3 in the event of a loss of normal heat sink (Conowingo Pond) or a design basis flood. The inspectors further determined the EHS system, including MO-0-33-0498 was safety-related. The basis for this conclusion included the following:

(1) 10 CFR 50.2 defines safety-related components as those relied upon to remain functional during and following design basis events (DBE) to assure. the capability to maintain the reactor in a safe shutdown condition, or the capability to prevent or mitigate the consequences of accidents leading to offsite exposures comparable to 10 CFR Part 100 exposure guidelines.
(2) Peach Bottom UFSAR Section 2.4.3.5 identified EHS as a safe shutdown system, required to mitigate two design basis events; the design flood condition (Run-up of the Maximum Wave Superimposed on the Probable Maximum Flood Water Level) and a loss of normal heat sink (e.g., seismic DBE damages the Conowingo dam).
(3) UFSAR Section 10.9.3 credited EHS to mitigate both the design flood condition and a loss of normal heat sink (loss of Conowingo pond).
(4) Section ISTA-1100(a) of the ASME OM 2012 Code defines IST scope to include pumps and valves required to shut down a reactor, maintain safe shutdown, or mitigate consequences of an accident.
(5) The inspectors determined that if the EHS was unavailable, a design basis seismic event which caused a loss of normal heat sink event and loss of offsite power could lead to offsite exposures comparable to 10 CFR Part 100 exposure guidelines.

Notwithstanding these conclusions, the inspectors noted the design did not provide for redundancy in the MO-0-33-0498 closure function as would be typical for a safety-related system. The inspectors further noted the closed-loop EHS function was added late in the original licensing of Peach Bottom Units 2 and 3 as a result of additional oversight reviews.

Section III-3600 of the ASME OM 2012 Code required active motor operated valves (MOVs)to be exercised (e.g., stroked open and closed) at least once per refueling cycle. Section ISTA-3110 of the ASME OM 2012 Code required the 10-year IST Program Plan to include the code requirements for each component and the test(s) to be performed. The inspectors reviewed station operating procedures and identified 19 EHS components (pumps and valves), including MO-0-33-0498, which were operated or verified by operators when placing EHS in closed-loop operation. Accordingly, the inspectors determined all 19 components were required to be tested in accordance with the ASME OM Code.

The inspectors verified that, with the exception of the MO-0-33-0498 active closure function, the ASME OM Code IST test requirements for the EHC system were properly identified in the 10-year IST Plan. Even EHS pumps and valves with no safety function identified in the Plan, had appropriate tests specified as though the components were credited for active safety functions. The inspectors also determined that MO-0-33-0498 was exercised and PI verified in accordance with annual surveillance test ST-O-033-310-2 (last performed 1/14/22).

Although Constellation staff considered the MO-0-33-0498 active closure function to be non-safety-related and outside of the ASME OM Code scope, they have been performing the testing required by the ASME OM Code for an active MOV. The inspectors reviewed maintenance and test records for the last 5 years and found no problems identified for MO-0-33-0498.

Licensing Basis: Constellation staff classified MO-0-33-0498 as safety-related and therefore within the scope of ASME OM Code IST requirements, for its passive safety function to remain open to return ESW cooling water from the emergency diesel generators and emergency core cooling system loads to the Conowingo Pond (e.g., river). The active function of MO-0-33-0498 to close isolates the return flow path to the Conowingo Pond and supports closed-loop operation of the EHS in the case of the Loss of Conowingo Pond Special Event. Constellation engineers acknowledged that the loss of Conowingo Pond was part of Peach Bottoms design and licensing basis. However, Constellation staff determined the EHS and the MO-0-33-0498 active closure function were augmented quality (non-safety-related), because they were not credited to mitigate any analyzed design basis accident or transient described in Chapter 14 of the UFSAR. Therefore, Constellation staff concluded EHS and the MO-0-33-0498 active closure function did not fall within the scoping criteria specified in ASME OM Code, ISTA-1100 because they were non-safety-related.

Constellation staff also stated that two previous NRC-approved licensing actions (Peach Bottom conversion to Improved Standard Technical Specifications (ISTS) and Peach Bottom IST Program Third 10-year Interval Update) accepted the licensee determination that EHS and the MO-0-33-0498 active closure function were augmented quality (non-safety-related). The NRC safety evaluation report (SER) for the ISTS conversion (dated 8/30/95)documented the licensee statement that the emergency cooling water pump (part of EHS)was not credited for mitigation of design bases accidents or transients, and accepted the licensees proposed alternative testing. The NRC SER for the IST Program Update (dated 5/11/98) stated the licensee should evaluate the applicability of MO-0-33-0498 and EHS components to the IST program. The licensee responded (dated 1/29/99) that the classification of EHS and the MO-0-33-0498 closure function was augmented quality (non-safety-related) because the components did not support mitigation of any design basis transient or accident. The NRC response (dated 3/15/00) to this letter repeated the licensee position that the components were augmented quality and found the alternative testing proposed by the licensee to be acceptable.

The inspectors noted the purpose of the two licensing actions was for the licensee to request NRC approval for alternative test requirements, in lieu of the existing IST Code and Peach Bottom technical specification test requirements. The associated NRC SERs stated that the specified components were subject to the testing requirements of the IST program and approved the proposed alternative test requirements. However, after stating the components were subject to requirements of the IST program, the SER documented the licensee position that the components were not credited with mitigation of design basis accidents and were augmented quality. These statements appear to conflict. The inspectors concluded the SERs and associated documentation did not make a clear determination of whether MO-0-33-0498 and the EHS were safety-related quality or were non-safety-related quality.

Significance: For the purpose of the VLSSIR process, the inspectors screened the issue of concern through IMC 0612, Issue Screening, and determined the issue of concern would likely be of minor significance had a performance deficiency been identified. Additionally, the issue of concern was similar to IMC 0612, Appendix E, Examples of Minor Issues, example 3.b, because the documentation error in the 10-year IST Plan did not result in any missed IST tests or adversely impact MO-0-33-0498 reliability.

The inspectors also verified the following information which provides reasonable assurance that EHS and MO-0-33-0498 will continue to meet the regulatory requirements of 10 CFR 50.55a(B)(3)(ii):

(1) Constellation is currently testing the required EHS components iaw ASME OM 2012 Code;
(2) Regulatory commitments by Constellation and procedures are in place regarding this periodic IST testing;
(3) Constellation staff informed the inspectors that there are no current plans to revise this testing; and
(4) The inspectors noted that changes to the associated IST test procedures would require review through the 10 CFR 50.59 safety evaluation process.

Technical Assistance Request: No Technical Assistance Request was processed in support of this issue.

Corrective Action Reference: Constellation entered the issue into the corrective action program as Issue Report

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 8, 2022, the inspectors presented the design basis assurance inspection (programs) inspection results to Mr. David Henry, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.02 Corrective Action

Documents

01335599

01420676

01537143

04013582

04378793

Corrective Action

Documents

Resulting from

Inspection

04486879

04486979

04486991

04487131

04487138

04487271

04490276

04490281

04490910

04491096

04491472

04492216

04494831

Drawings

280-M-315, Sht.

Emergency Service Water and High Pressure Service

Water

Revision 92

280-M-315, Sht.

Emergency Service Water and High Pressure Service

Water

Revision 95

280-M-330

Sht.1

Emergency Cooling System

Revision 39

Engineering

Changes

EC 07-00344

Differing Detail of Tech Spec Basis & PIMS CRL Safety

Function

Revision 0

EC 556030

MO-3-23-014 Actuator Upgrade SMB1 to SB1

Revision 0

EC 626985

Approve MPR Anti-Rotation Device for Recirculation

Valves

Revision 0

EC 630174

Evaluate BWROG Document TP16-1-112, Revision 5 for

Applicability to Peach Bottom Recirculation Valves

Revision 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations

JOG MOV

Evaluation

Report MO-3-02-

053B

AC Motor Operated GL 96-05 Gate Valve

Revision 11

PMC-21-128124

Peach Bottom, System 14 Core Spray MOV/IST Alternate

Treatment Plan

2/23/2021

Miscellaneous

BWR Main Steam Isolation Valve (MSIV) PM Template

Revision 2

280-M-1-JJ-80

MSIV Vendor Technical Manual

Revision 1

910328 NRC

GNL 88-14

Peach Bottom Response to NCR P-91152

03/28/1991

A-391-VC-8

Vendor Technical Manual

Revision 1

Commitment

Change

Evaluation

290603,

Assignment 02-

2/24/2020

DBD P-S-09

Residual Heat Removal System

Revision 19

F-130-VC-273

Vendor Technical Manual

Revision 0

NRC Information Notice 2013-14

Potential Design Deficiency in Motor-Operated Valve

Control Circuitry

08/23/2013

P-S-19

Recirculation System

Revision 19

P-S-25B

Primary Containment Auxiliary Systems

Revision 10

PB-5069-14-14A-

003

CFR 50.69 System Categorization Document - Core

Spray System

Revision 1

ST-O-003-450-2

Scram Discharge Vent and Drain Valve Functional Test

01/08/2022

ST-O-007-410-3

PCIS Valves Colder Shutdown Inservice Test

11/05/2021

ST-O-010-302-3

"A" RHR Loop Pump, Valve, Flow and Unit Cooler

Functional and Inservice Comprehensive Test

03/01/2021

ST-O-023-300-3

HPCI Pump, Valve, Flow and Unit Cooler Functional and

In-service Test without Vibration Data Collected

2/28/2022

ST-O-02A-400-3

Recirculation Pump Discharge Valve Operability Test

11/01/2021

ST-O-033-410-2

IST Exercise of ESW Air Operated Valves

2/26/2022

ST-O-07G-470-3

Main Steam Isolation Valve Closure Timing

11/03/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

ER-AA-200

Preventive Maintenance Program

Revision 5

ER-AA-200-1004

PCM Templates

Revision 1

ER-AA-569-1004

CFR 50.69 Alternative Treatment Implementation

Process

Revision 5

MA-AA-723-300

Diagnostic Testing of Motor Operated Valves

Revision 14

MA-AA-723-301

Periodic Inspection of Limitorque Model SMB/SB/SBD

SBD-000 through 5 Motor Operated Valves

Revision 15

MA-AA-796-024

Scaffold Installation, Inspection, and Removal

Revision 12

MA-MA-796-024-

1001

Scaffolding Criteria for the Mid Atlantic Stations

Revision 9

OP-AA-201-009

Control of Transient Combustible Material

Revision 26

SO 48.1.B

Emergency Cooling Water System Startup

Revision 20

ST-O-032-301-2

HPSW Pump, Valve and Flow Functional and Inservice

Test

Revision 42

Work Orders

246550

247914

250943

252128

264168

04306865

04869070

04880360

05133013

R1155387

R1196156