Forwards LER 96-003-00 Re re-analysis of High Energy Line Break,Error Found in Existing Analysis.Rept Contains Submitted New NRC Commitments
ML20117D841
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 05/08/1996
From: Hill W
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20117D845 List:
References
NUDOCS 9605140492
Download: ML20117D841 (1)


LER-2096-003, Forwards LER 96-003-00 Re re-analysis of High Energy Line Break,Error Found in Existing Analysis.Rept Contains Submitted New NRC Commitments
Event date:
Report date:
2632096003R00 - NRC Website

text

- _ . _ _ _ - _ _ _ _ _ _ _ .

. i May 8,1996 '

10 CFR Pad 50 Section 50.73 US Nuclear Regulatory Commission  ;

Attn: Document Control Desk Washington, DC 20555 l

I MONTICELLO NUCLEAR GENERATING Pl. ANT Docket No. 50-263 License No. DPR-22 LER 96-003 During a Re-analysis of the High Energy Une Break, An Error was found in the Existing Analysis The Licensee Event Repc,rt for this occurrence is attached. An extension of the submittal due date to May 10,1996 was obtained from the NRC Resident inspector for this report. This report contains the following new NRC commitments:

Modifications will be performed such that the HELB of concem does not result in harsh environments for the 4kV switchgear, MCC-142 and MCC-143 areas.

Please contact Tom Parker at (612) 295-1014 if you require further information.

i N ny &

l William J Hill i Plant Manager l

Monticello Nuclear Generating Plant '

l c: Regional Administrator-Ill NRC Sr Resident inspector, NRC l NRR Project Manager, NRC State of Minnesota, Attn: Kris Sanda Attachment i

i 1

l i

1 1

140073 9605140492 960508 op!

(/