Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005)
ML23241A118
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/31/2023
From: Erin Carfang
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023005
Download: ML23241A118 (1)


Text

August 31, 2023

SUBJECT:

UPDATED INSPECTION PLAN FOR JAMES A. FITZPATRICK NUCLEAR POWER PLANT (REPORT 05000333/2023005)

Dear David Rhoades:

The enclosed inspection plan lists the inspections scheduled through June 30, 2025, for James A. FitzPatrick Nuclear Power Plant. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Erin Carfang at (610) 337-5120 with any questions you have regarding this letter.

Sincerely, Digitally signed by Erin E.

Erin E. Carfang Date: 2023.08.31 Carfang 08:18:33 -04'00'

Erin Carfang, Chief Projects Branch 1 Division of Operating Reactor Safety Docket No. 05000333 License No. DPR59 Enclosure:

FitzPatrick Inspection Plan cc w/encl: Distribution via ListServ

ML23241A118 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DORS RI/DORS NAME MHardgrove ECarfang DATE 8/23/2023 8/28/2023

Site Inspection Activity Plan FitzPatrick 07/01/2023 - 06/30/2025 Unit Start End Activity CAC Title Staff Count Access Control, Equipment, Sec Trng, Sec Plan Review, PI- Fitz 3 1 7/10/2023 7/13/2023 IP 71130.02 000734 Access Control 1 7/10/2023 7/13/2023 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 7/10/2023 7/13/2023 IP 71130.07 000739 Security Training 1 7/10/2023 7/13/2023 IP 71130.09 001656 Security Plan Changes 1 7/10/2023 7/13/2023 IP 71151 001338 Performance Indicator Verification FY23 - Fitz Initial Licensing Examination 4 1 7/9/2023 7/14/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 8/6/2023 8/18/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

RP - 71124.04 Dosimetry 1 1 8/28/2023 9/1/2023 IP 71124.04 000728 Occupational Dose Assessment PI&R Team Inspection - Fitzpatrick 4 1 9/18/2023 9/22/2023 IP 71152B 000747 Problem Identification and Resolution 1 10/2/2023 10/6/2023 IP 71152B 000747 Problem Identification and Resolution ISFSI Loading Campaign (60855) - Fitz 2 1 10/2/2023 10/6/2023 IP 60855 001001 Operation Of An ISFSI RP - 71124.08 Radwaste Shipping and 71151 PIV 1 1 10/9/2023 10/13/2023 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation 1 10/9/2023 10/13/2023 IP 71151 000746 Performance Indicator Verification Cyber Security - Fitzpatrick 4 1 10/23/2023 10/27/2023 IP 71130.10 000741 Cybersecurity RP- 71124.03 Airborne 1 1 3/11/2024 3/15/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Access Control, Protective Strategy, TSR, SPR 4 1 4/22/2024 4/26/2024 IP 71130.02 000734 Access Control 1 4/22/2024 4/26/2024 IP 71130.05 000737 Protective Strategy Evaluation 1 4/22/2024 4/26/2024 IP 71130.09 001656 Security Plan Changes 1 4/22/2024 4/26/2024 IP 71130.14 000743 Review of Power Reactor Target Sets 1 4/22/2024 4/26/2024 IP 71151 001338 Performance Indicator Verification Fitz Requal Insp with P/F Results 1 1 5/6/2024 5/10/2024 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance Prepared on 8/22/2023 3:13:55 PM 1 of 3 Enclosure

Site Inspection Activity Plan 1 5/6/2024 5/10/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP - 71124.04 Dosimetry 1 1 5/6/2024 5/10/2024 IP 71124.04 000728 Occupational Dose Assessment Material Control and Accounting- Fitzpatrick 1 1 5/6/2024 5/10/2024 IP 71130.11 000742 Material Control and Accounting (MC&A)

Commercial Grade Dedication - Fitzpatrick 3 1 6/10/2024 6/14/2024 IP 71111.21N.03 001808 Commercial Grade Dedication 1 6/24/2024 6/28/2024 IP 71111.21N.03 001808 Commercial Grade Dedication EP Program Inspection - Fitzpatrick 1 1 7/15/2024 7/19/2024 IP 71114.02 000717 Alert and Notification System Testing 1 7/15/2024 7/19/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 7/15/2024 7/19/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 7/15/2024 7/19/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 7/15/2024 7/19/2024 IP 71151 001397 Performance Indicator Verification RP - 71124.01 Rad Hazards RFO 1 1 9/9/2024 9/13/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Inservice Inspection - Fitzpatrick 1 1 9/16/2024 9/20/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP - 71124.06 RETS and 71151 PIV 1 1 10/7/2024 10/11/2024 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 10/7/2024 10/11/2024 IP 71151 000746 Performance Indicator Verification 2025 Fitz Initial License Examination 4 1 1/20/2025 1/24/2025 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 2/17/2025 2/21/2025 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Access Authorization, FFD - FP 2 1 2/3/2025 2/7/2025 IP 71130.01 000733 Access Authorization 1 2/3/2025 2/7/2025 IP 71130.08 000740 Fitness For Duty Program 1 2/10/2025 2/14/2025 IP 71130.01 000733 Access Authorization 1 2/10/2025 2/14/2025 IP 71130.08 000740 Fitness For Duty Program RP - 71124.01 Rad Hazards 1 1 3/10/2025 3/14/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Age Related Degradation Inspection - Fitzpatrick 3 1 4/28/2025 5/2/2025 IP 71111.21N.04 001832 Age-Related Degradation 1 5/12/2025 5/16/2025 IP 71111.21N.04 001832 Age-Related Degradation RP - 71124.05 Instruments 1 Prepared on 8/22/2023 3:13:55 PM 2 of 3

Site Inspection Activity Plan 1 5/5/2025 5/9/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation Prepared on 8/22/2023 3:13:55 PM 3 of 3