|
---|
Category:Letter
MONTHYEARIR 05000333/20240902024-10-29029 October 2024 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000333/2024090 IR 05000333/20244022024-10-28028 October 2024 Material Control and Accounting Program Inspection Report 05000333/2024402 (Cover Letter Only) ML24276A1332024-10-17017 October 2024 Issuance of Amendment No. 357 Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision-4, and Administrative Changes ML24282B0302024-10-11011 October 2024 Project Manager Assignment RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24207A0192024-10-0909 October 2024 SE Addendum Related to the License Amendment No. 338 for Implementation of the Alternative Source Term (DPO-2021-001) ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing JAFP-24-0051, Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-0882024-10-0303 October 2024 Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-088 ML24270A0742024-09-30030 September 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0134) - LTR ML24270A1452024-09-26026 September 2024 Notice of Enforcement Discretion for James A. Fitzpatrick Nuclear Power Plant JAFP-24-0046, Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation2024-09-25025 September 2024 Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation JAFP-24-0047, License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software2024-09-25025 September 2024 License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software JAFP-24-0045, Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2024-09-20020 September 2024 Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20240112024-09-19019 September 2024 Follow-up to Inspection Procedure 71153 Report 05000333/2024011 and Preliminary White Finding and Apparent Violation JAFP-24-0044, Core Operating Limits Report Cycle 272024-09-16016 September 2024 Core Operating Limits Report Cycle 27 JAFP-24-0043, Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues2024-09-12012 September 2024 Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues 05000333/LER-2024-002, Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation2024-09-0404 September 2024 Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation ML24165A0382024-09-0404 September 2024 Issuance of Amendment No. 356 Update Fuel Handling Accident Analysis IR 05000333/20240052024-08-29029 August 2024 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2024005) 05000333/LER-2024-001-01, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-08-21021 August 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000333/20240022024-08-0707 August 2024 Integrated Inspection Report 05000333/2024002 JAFP-24-0034, 10 CFR 50.46 Annual Report2024-07-31031 July 2024 10 CFR 50.46 Annual Report ML24208A0492024-07-30030 July 2024 Notice of Consideration of Issuance of Amendments to Facility Operating Licenses and Proposed No Significant Hazards Consideration Determination (Letter) JAFP-24-0036, Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2024-07-29029 July 2024 Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-24-0033, Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test2024-07-23023 July 2024 Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20244032024-07-18018 July 2024 Biennial Problem Identification and Resolution Inspection Report 05000333/2024403 (Cover Letter Only) IR 05000333/20244012024-07-15015 July 2024 Security Baseline Inspection 05000333/2024401 RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24190A1932024-07-0909 July 2024 Correction Letter of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance IR 05000333/20240102024-07-0808 July 2024 Commercial Grade Dedication Inspection Report 05000333/2024010 ML24184A1662024-07-0303 July 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24136A1162024-06-26026 June 2024 Issuance of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance 05000333/LER-2024-001, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24176A2412024-06-24024 June 2024 Licensed Operator Positive Fitness-for-Duty Test JAFP-24-0027, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations JAFP-24-0026, Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance2024-06-12012 June 2024 Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000333/20240012024-05-0909 May 2024 Integrated Inspection Report 05000333/2024001 JAFP-24-0023, 2023 Annual Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Annual Radiological Environmental Operating Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests JAFP-24-0020, 2023 Annual Radioactive Effluent Release Report2024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report JAFP-24-0019, 2023 REIRS Transmittal of NRC Form 52024-04-18018 April 2024 2023 REIRS Transmittal of NRC Form 5 ML24106A0152024-04-15015 April 2024 Request for Withholding Information from Public Disclosure Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling ML24107A6972024-04-12012 April 2024 Engine Systems, Inc Part 21 Report Re EMD Cylinder Liner Water Leak ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24068A0532024-03-28028 March 2024 Issuance of Amendment No. 354 Revise Technical Specifications Section 3.3.1.2, Source Range Monitors Instrumentation JAFP-24-0014, Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2024-03-25025 March 2024 Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis 2024-09-04
[Table view] Category:License-Operator
MONTHYEARJAFP-24-0033, Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test2024-07-23023 July 2024 Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test ML24184A1662024-07-0303 July 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24176A2412024-06-24024 June 2024 Licensed Operator Positive Fitness-for-Duty Test ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML24008A0302022-11-0909 November 2022 Examination Administrative Files ML22252A0102022-09-0909 September 2022 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML22252A0052022-09-0909 September 2022 Final Qa/Related Forms (Folder 1) ML23004A1022022-08-30030 August 2022 Draft Written Examination and Operating Test Outlines (Folder 2) RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22073A1112022-03-14014 March 2022 Requalification Program Inspection IR 05000333/20213012021-10-0505 October 2021 Initial Operator Licensing Examination Report 05000333/2021301 ML22355A6502021-08-30030 August 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML22355A6482021-08-30030 August 2021 Final Written Exam and Operating Test Outlines (Folder 3) ML22355A6492021-08-30030 August 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML23004A0932021-08-30030 August 2021 Final Qa/Related Forms (Folder 1) ML21019A4472021-01-20020 January 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20105A2042020-04-15015 April 2020 March 4, 2020, Nrc Generic Fundamentals Examination Results for James A. Fitzpatrick Nuclear Power Plant (Cover Letter Publicly Available, Enclosures Withheld from Public) ML20087G8522020-03-27027 March 2020 Ja Fitzpatrick - Final Operating Test (Sections a, B, and C) (Folder 3) ML20087H5142020-03-27027 March 2020 Ja Fitzpatrick Final Written Exam Questions and Answer Key ML20078K2112020-03-19019 March 2020 Requalification Program Inspection - James A. Fitzpatrick Nuclear Power Plant ML21056A3072020-03-12012 March 2020 Handouts to Applicants (Folder 3) ML21056A2852020-02-15015 February 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML21056A2842020-02-15015 February 2020 Final Qa/Related Forms (Folder 1) ML20043C8092020-02-11011 February 2020 Operator Licensing Examination Approval ML21056A3062020-02-10010 February 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20260H1532020-01-24024 January 2020 Draft Written Examination (Folder 2) ML20260H1542020-01-24024 January 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML20260H1522019-10-14014 October 2019 Draft Written Examination and Operating Test Outlines (Folder 2) ML20260H1502019-10-14014 October 2019 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML20260H1512019-10-14014 October 2019 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML19211C3782019-07-30030 July 2019 Senior Reactor and Reactor Operator Initial License Examinations RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19008A1022019-01-0707 January 2019 Operator Licensing Examination Approval ML18163A2922018-06-12012 June 2018 Senior Reactor and Reactor Operator Initial License Examinations ML18134A2302018-05-14014 May 2018 Operator Licensing Examination Approval RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18086B7042018-03-27027 March 2018 Dec. 2016 GFE Post-Exam Comment and Response ML18086B0252018-02-16016 February 2018 Facility Cover Letter - Ri - March 2018 - GFE ML18029A5822018-01-29029 January 2018 Requalification Program Inspection ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17313A2752017-11-0808 November 2017 Senior Reactor and Reactor Operator Initial License Examinations RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17034A1132017-02-0202 February 2017 December 7, 2016, NRC Generic Fundamentals Examination Results for J. A. Fitzpatrick Nuclear Power Plant (Cover Letter Publicly Available, Enclosures Withheld from Public) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 JAFP-16-0118, NRC Form 536, Operator Licensing Examination Data for Calendar Years 2018 to 20212016-07-18018 July 2016 NRC Form 536, Operator Licensing Examination Data for Calendar Years 2018 to 2021 ML16145A3832016-04-0606 April 2016 Final Qa/Related Forms (Folder 1) ML16145A3692016-03-24024 March 2016 Miscellaneous Exam Material (Folder 1) 2024-07-03
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24184A1662024-07-0303 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML24008A0302022-11-0909 November 2022 Examination Administrative Files ML22252A0102022-09-0909 September 2022 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML22252A0052022-09-0909 September 2022 Final Qa/Related Forms (Folder 1) ML23004A1022022-08-30030 August 2022 Draft Written Examination and Operating Test Outlines (Folder 2) RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000333/20213012021-10-0505 October 2021 Initial Operator Licensing Examination Report 05000333/2021301 ML22355A6502021-08-30030 August 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML23004A0932021-08-30030 August 2021 Final Qa/Related Forms (Folder 1) ML22355A6492021-08-30030 August 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML22355A6482021-08-30030 August 2021 Final Written Exam and Operating Test Outlines (Folder 3) ML21019A4472021-01-20020 January 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20105A2042020-04-15015 April 2020 March 4, 2020, Nrc Generic Fundamentals Examination Results for James A. Fitzpatrick Nuclear Power Plant (Cover Letter Publicly Available, Enclosures Withheld from Public) ML20087G8522020-03-27027 March 2020 Ja Fitzpatrick - Final Operating Test (Sections a, B, and C) (Folder 3) ML20087H5142020-03-27027 March 2020 Ja Fitzpatrick Final Written Exam Questions and Answer Key ML20078K2112020-03-19019 March 2020 Requalification Program Inspection - James A. Fitzpatrick Nuclear Power Plant ML21056A3072020-03-12012 March 2020 Handouts to Applicants (Folder 3) ML21056A2842020-02-15015 February 2020 Final Qa/Related Forms (Folder 1) ML21056A2852020-02-15015 February 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML20043C8092020-02-11011 February 2020 Operator Licensing Examination Approval ML21056A3062020-02-10010 February 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20260H1532020-01-24024 January 2020 Draft Written Examination (Folder 2) ML20260H1542020-01-24024 January 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML20260H1512019-10-14014 October 2019 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20260H1522019-10-14014 October 2019 Draft Written Examination and Operating Test Outlines (Folder 2) ML20260H1502019-10-14014 October 2019 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML19211C3782019-07-30030 July 2019 Senior Reactor and Reactor Operator Initial License Examinations RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19008A1022019-01-0707 January 2019 Operator Licensing Examination Approval ML18163A2922018-06-12012 June 2018 Senior Reactor and Reactor Operator Initial License Examinations ML18134A2302018-05-14014 May 2018 Operator Licensing Examination Approval RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18086B7042018-03-27027 March 2018 Dec. 2016 GFE Post-Exam Comment and Response ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17313A2752017-11-0808 November 2017 Senior Reactor and Reactor Operator Initial License Examinations RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17034A1132017-02-0202 February 2017 December 7, 2016, NRC Generic Fundamentals Examination Results for J. A. Fitzpatrick Nuclear Power Plant (Cover Letter Publicly Available, Enclosures Withheld from Public) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 JAFP-16-0118, NRC Form 536, Operator Licensing Examination Data for Calendar Years 2018 to 20212016-07-18018 July 2016 NRC Form 536, Operator Licensing Examination Data for Calendar Years 2018 to 2021 ML16145A3832016-04-0606 April 2016 Final Qa/Related Forms (Folder 1) ML16145A3692016-03-24024 March 2016 Miscellaneous Exam Material (Folder 1) ML16081A1592016-03-0303 March 2016 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML16085A2472016-03-0303 March 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML16085A2462016-03-0101 March 2016 Final Outlines (Folder 3) ML16085A2482016-03-0101 March 2016 Handouts to Applicants - Summary of References(Folder 3) ML16081A0772016-02-29029 February 2016 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML16085A2492016-02-25025 February 2016 Final Operating Exam (Sections a, B, and C) (Folder 3) 2024-07-03
[Table view] |
Text
July 3, 2024
David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer (CNO)
Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - SENIOR REACTOR AND REACTOR OPERATOR INITIAL LICENSE EXAMINATIONS
Dear David Rhoades:
In a telephone conversation on June 20, 20 24, between Manan Patel, Chief Examiner, and Don Kelly, Facility Exam Author, arrangements were made for the administration of licensing examinations at James A. FitzPatrick Nuclear Power Plant, during the week of February 17, 2025. In addition, the U.S. Nuclear Regulatory Commission (NRC) will make an examination validation visit to your facility the week of January 20, 2025.
As agreed upon during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by September 20, 2024. The NRC staff provided the written examination outline on January 31, 2024. The written examinations, operating tests, and supporting reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by December 4, 2024. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 55.40(b)(3), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready to use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled.
To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
D. Rhoades 2
ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) control number 3150- 0090) at least 60 days before the first examination date (if possible). Contact Manan Patel, Chief Examiner to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150- 0090) and medical certifications (OMB control number 3150- 0024) should be submitted at least 30 days before the first examination date. If the NRC does not receive the preliminary applications at least 30 days before the examination date, a postponement may be necessary. Final, signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for waiver or excusal requests call for their receipt at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60- day guideline above). Resolutions resulting from verbal inquiries by the facility licensee to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e.,
using NRC Form 398 or as directed by Manan Patel when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement
This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the OMB, approval number 3150- 0018.
The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M), U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by email to Infocollects.Resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150- 0018), Attn:
Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC 20503; email: oira_submission@omb.eop.gov.
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB control number.
In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter and its enclosures will be available electronically for public inspection through the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible on the NRCs website at http://www.nrc.gov/reading-rm/adams.html.
D. Rhoades 3
After you have been notified by the NRC Chief Examiner or Branch Chief that operator licenses have been issued, please direct any inquiries concerning a formal presentation of certificates to this office. Our goal is to have the operator certificates available for your celebration. At least one-month advance notice of your celebration arrangements would be appreciated to plan our senior manager attendance and process the certificates.
Thank you for your cooperation in this matter. Don Kelly has been advised of the policies and guidelines referenced in this letter. If you have any questions about the NRCs examination procedures and guidelines, please contact Manan Patel at (610) 337-5304 or me at (610) 337-5306.
Sincerely,
Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety
Docket No. 05000 333 License No. DPR-59
cc: Distribution via ListServ
D. Rhoades 4
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - SENIOR REACTOR AND REACTOR OPERATOR INITIAL LICENSE EXAMINATIONS DATED JULY 3, 2024
DISTRIBUTION:
MPatel, DORS DJackson, DORS ECarfang, DORS EEve, DORS KSmetana, DORS EAdams, DORS EMiller, DORS, SRI VFisher, DORS, RI ATrudell, DORS, AA MSimmons, RI OEDO RidsNrrPMFitzPatrick Resource RidsNrrDorlLpl1 Resource
DOCUMENT NAME: G:\\DRS\\Operations Branch\\PATEL\\ Exam FY25-FitzPatrick 17 Feb 2025\\ Letters\\FitzPatrick 2025 Exam-CorpNotifyLtr.docx ADAMS Package No: ML24101A001 ADAMS Accession No: ML24184A166 SUNSI Review n -Sensitive Publvlle
Sensitive n -Publiclyvlable
OFFICE RI/DO RS/OB : RI/DO RS/OB :
ME MPat/ M DEckson / J TE 07/ 4 07/02/2024 OFFIAL RERD CO